SHREE RAM CORPORATION
RAJRATNAPLATINA OPP. AMBESCHOOL VAIKUNTH-1 CROSSING, WAGHODIA ROAD
Approved
8th Mar 2018
Completed
30th Sept 2020
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA01942/EX1/290319
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170915/002404
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | RAJRATNA PLATINA |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA01942/EX1/290319 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170915/002404 |
| Project Description | 2&3 BHK FLATS & SHOP |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | RAJRATNAPLATINA OPP. AMBESCHOOL VAIKUNTH-1 CROSSING, WAGHODIA ROAD |
| Pincode | 390019 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-03-08 |
| Start Date | 2016-09-20 |
| End Date | 2020-09-30 |
| Submission Date | 2017-09-15 |
| Months Delayed | 0 |
| Total Land Area | 3959.0 |
| Total Covered Area | 1425.0 |
| Total Open Area | 1834.0 |
| Open Parking Area | 502 |
| Covered Parking Area | 748.0 |
| Covered Parking Count | 4 |
| Parking for Sale Count | 4 |
| Cost of Land | 64165405 |
| Estimated Project Cost | 137584500 |
| Total Project Cost | 201749905 |
| Moje | Bopad |
| TP No. | 43 |
| TP Name | Bapod |
| Plot No. | - |
| Promoter Name | SHREE RAM CORPORATION |
| Promoter Type | PARTNERSHIP FIRM |
| mvparikh7.mp@gmail.com | |
| Mobile | 9825407025 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ADAFS8425N |
| Experience (Years) | 2 |
| Area Constructed (sqm) | 396 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | MINISH PARIKH |
| Address | A-101, SUKAN -03,, NEAR WATER TANK, KARELIBAUG, |
| TOWER A - Start Date | 2016-09-20 |
| TOWER A - End Date | 2020-09-30 |
| TOWER A - Progress | 85.71% |
| TOWER A - Booked Units | 24 |
| TOWER A - Unbooked Units | 4 |
| TOWER B - Start Date | 2016-09-20 |
| TOWER B - End Date | 2020-09-30 |
| TOWER B - Progress | 93.33% |
| TOWER B - Booked Units | 28 |
| TOWER B - Unbooked Units | 2 |
| TOWER C - Start Date | 2016-09-20 |
| TOWER C - End Date | 2020-09-30 |
| TOWER C - Progress | 100.0% |
| TOWER C - Booked Units | 28 |
| TOWER C - Unbooked Units | 0 |
| TOWER D - Start Date | 2016-09-20 |
| TOWER D - End Date | 2020-09-30 |
| TOWER D - Progress | 100.0% |
| TOWER D - Booked Units | 32 |
| TOWER D - Unbooked Units | 0 |
| TOWER E - Start Date | 2016-09-20 |
| TOWER E - End Date | 2020-09-30 |
| TOWER E - Progress | 100.0% |
| TOWER E - Booked Units | 20 |
| TOWER E - Unbooked Units | 0 |
| TOWER F - Start Date | 2016-09-20 |
| TOWER F - End Date | 2020-09-30 |
| TOWER F - Progress | 100.0% |
| TOWER F - Booked Units | 20 |
| TOWER F - Unbooked Units | 0 |
| 2&3BHK FLATS & SHOP - Total Units | 153 |
| 2&3BHK FLATS & SHOP - Carpet Area | 6345.0 |
| 2&3BHK FLATS & SHOP - Exclusive Area | 262.0 |
| 2&3BHK FLATS & SHOP - Open Terrace Area | 1490.0 |
| August 2018 | 86.26% |
| November 2018 | 98.94% |
| February 2019 | 100.0% |
| May 2019 | 100.0% |
| August 2019 | 100.0% |
| November 2019 | 100.0% |
| February 2020 | 100.0% |
| May 2020 | 100.0% |
| August 2020 | 100.0% |
| October 2020 | 100.0% |
| Architect | MR. CHIRAG PATEL |
| Licence No. | VMC-ER07/2016TO2019 VUDA-E218/2013TO2018 |
| Engineer | Dr. V.R PATEL |
| Licence No. | VMC-SH64/16-19 VUDA-S21/13-18 |
| Contractor | GHANSHYAM BHAI J PRAJAPATI |