Project Details
| Project Name | SHIVABHI LUXURIA |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA04073/EX1/280520 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/171003/003413 |
| Project Description | Shivabhiluxuria is residential based project consisting of low rise towers. |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Opp. Jiji Mata mandir, Nr. ABB compound, Makarpura Main road, |
| Pincode | 390014 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-11-19 |
| Start Date | 2012-07-01 |
| End Date | 2021-06-30 |
| Submission Date | 2017-10-03 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 28115.79 |
| Total Land Area (Registered) | 28115.79 |
| Total Covered Area | 9976.53 |
| Total Open Area | 18139.26 |
| Total Carpet Area | 35310.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 483.09 |
| Covered Parking Count | 20 |
| Parking for Sale Count | 0 |
| Cost of Land | 0 |
| Estimated Project Cost | 0 |
| Total Project Cost | 0 |
Land Details
| Moje | Jambuva Makarpura |
Promoter Details
| Promoter Name | GURUPRASAD INFRASTRUCTURE PRIVATE LIMITED |
| Promoter Type | COMPANY |
| bui*****************@gmail.com | |
| Mobile | 93******** |
| Company Registration No. | U45201GJ2010PTC059654 |
| PAN | AAD******* |
| Date of Incorporation | 2010-02-20 |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 15000 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | PRAMOD JETHANAND DASWANI |
| PAN | ABW******* |
| Address | 5-6,Shri Ram Nagar, Sant Cover Colony,, Warsiya, |
| Partner 2 | KAPIL JETHANAND DASVANI |
| PAN | AFC******* |
| Address | 5-6,Shri Ram Nagar, Sant Cover Colony,, Warsiya, |
| Partner 3 | JETHANAND KEVALRAM DASWANI |
| PAN | ACS******* |
| Address | 5-6,Shri Ram Nagar, Sant Cover Colony, Warsiya, |
| Partner 4 | SHEELA JETHANAND DASWANI |
| PAN | ADD******* |
| Address | 5-6,Shri Ram Nagar, Sant Cover Colony, Warsiya, |
| Partner 5 | JYOTI PRAMODKUMAR DASWANI |
| PAN | ACM******* |
| Address | 5-6,Shri Ram Nagar, Sant Cover Colony, Warsiya, |
Building Blocks
| TOWER E - Start Date | 2012-07-01 |
| TOWER E - End Date | 2021-06-30 |
| TOWER E - Progress | 93.75% |
| TOWER E - Booked Units | 15 |
| TOWER E - Unbooked Units | 1 |
| TOWER F - Start Date | 2012-07-01 |
| TOWER F - End Date | 2021-06-30 |
| TOWER F - Progress | 93.75% |
| TOWER F - Booked Units | 15 |
| TOWER F - Unbooked Units | 1 |
| TOWER G - Start Date | 2012-07-01 |
| TOWER G - End Date | 2021-06-30 |
| TOWER G - Progress | 71.43% |
| TOWER G - Booked Units | 10 |
| TOWER G - Unbooked Units | 4 |
| TOWER H - Start Date | 2012-07-01 |
| TOWER H - End Date | 2021-06-30 |
| TOWER H - Progress | 100.0% |
| TOWER H - Booked Units | 14 |
| TOWER H - Unbooked Units | 0 |
| TOWER I - Start Date | 2012-07-01 |
| TOWER I - End Date | 2021-06-30 |
| TOWER I - Progress | 100.0% |
| TOWER I - Booked Units | 16 |
| TOWER I - Unbooked Units | 0 |
| TOWER J - Start Date | 2012-07-01 |
| TOWER J - End Date | 2021-06-30 |
| TOWER J - Progress | 68.75% |
| TOWER J - Booked Units | 11 |
| TOWER J - Unbooked Units | 5 |
| TOWER K - Start Date | 2012-07-01 |
| TOWER K - End Date | 2021-06-30 |
| TOWER K - Progress | 100.0% |
| TOWER K - Booked Units | 16 |
| TOWER K - Unbooked Units | 0 |
| TOWER L - Start Date | 2012-07-01 |
| TOWER L - End Date | 2021-06-30 |
| TOWER L - Progress | 100.0% |
| TOWER L - Booked Units | 14 |
| TOWER L - Unbooked Units | 0 |
| TOWER M - Start Date | 2012-07-01 |
| TOWER M - End Date | 2021-06-30 |
| TOWER M - Progress | 100.0% |
| TOWER M - Booked Units | 14 |
| TOWER M - Unbooked Units | 0 |
| TOWER N - Start Date | 2012-07-01 |
| TOWER N - End Date | 2021-06-30 |
| TOWER N - Progress | 100.0% |
| TOWER N - Booked Units | 14 |
| TOWER N - Unbooked Units | 0 |
| TOWER O - Start Date | 2012-07-01 |
| TOWER O - End Date | 2021-06-30 |
| TOWER O - Progress | 100.0% |
| TOWER O - Booked Units | 16 |
| TOWER O - Unbooked Units | 0 |
| TOWER P - Start Date | 2012-07-01 |
| TOWER P - End Date | 2021-06-30 |
| TOWER P - Progress | 100.0% |
| TOWER P - Booked Units | 14 |
| TOWER P - Unbooked Units | 0 |
| TOWER Q - Start Date | 2012-07-01 |
| TOWER Q - End Date | 2021-06-30 |
| TOWER Q - Progress | 100.0% |
| TOWER Q - Booked Units | 16 |
| TOWER Q - Unbooked Units | 0 |
| TOWER R - Start Date | 2012-07-01 |
| TOWER R - End Date | 2021-06-30 |
| TOWER R - Progress | 100.0% |
| TOWER R - Booked Units | 16 |
| TOWER R - Unbooked Units | 0 |
| TOWER S - Start Date | 2012-07-01 |
| TOWER S - End Date | 2021-06-30 |
| TOWER S - Progress | 100.0% |
| TOWER S - Booked Units | 16 |
| TOWER S - Unbooked Units | 0 |
| TOWER T - Start Date | 2012-07-01 |
| TOWER T - End Date | 2021-06-30 |
| TOWER T - Progress | 100.0% |
| TOWER T - Booked Units | 16 |
| TOWER T - Unbooked Units | 0 |
| TOWER U - Start Date | 2012-07-01 |
| TOWER U - End Date | 2021-06-30 |
| TOWER U - Progress | 100.0% |
| TOWER U - Booked Units | 16 |
| TOWER U - Unbooked Units | 0 |
| TOWER V - Start Date | 2012-07-01 |
| TOWER V - End Date | 2021-06-30 |
| TOWER V - Progress | 100.0% |
| TOWER V - Booked Units | 12 |
| TOWER V - Unbooked Units | 0 |
| TOWER W - Start Date | 2012-07-01 |
| TOWER W - End Date | 2021-06-30 |
| TOWER W - Progress | 100.0% |
| TOWER W - Booked Units | 12 |
| TOWER W - Unbooked Units | 0 |
| TOWER X - Start Date | 2012-07-01 |
| TOWER X - End Date | 2021-06-30 |
| TOWER X - Progress | 100.0% |
| TOWER X - Booked Units | 11 |
| TOWER X - Unbooked Units | 0 |
| TOWER Y - Start Date | 2012-07-01 |
| TOWER Y - End Date | 2021-06-30 |
| TOWER Y - Progress | 100.0% |
| TOWER Y - Booked Units | 12 |
| TOWER Y - Unbooked Units | 0 |
| TOWER Z - Start Date | 2012-07-01 |
| TOWER Z - End Date | 2021-06-30 |
| TOWER Z - Progress | 100.0% |
| TOWER Z - Booked Units | 12 |
| TOWER Z - Unbooked Units | 0 |
Inventory Units
| Flats - Total Units | 180 |
| Flats - Carpet Area | 1325.0 |
| Flats - Exclusive Area | 0.0 |
| Flats - Open Terrace Area | 0.0 |
Quarterly Progress
| April 2019 | 93.47% |
| July 2019 | 93.82% |
| October 2019 | 94.55% |
| January 2020 | 95.28% |
| October 2020 | 97.03% |
| January 2021 | 97.42% |
| April 2021 | 97.61% |
| July 2021 | 98.5% |
| July 2021 | 99.59% |
Professionals
| Architect | Pramukh Engineers |
| Licence No. | ER48/0910 |
| Engineer | Swati Associates |
| Licence No. | notavailable |
| Contractor | MAVJIBHAI VEGDA |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in