SHIVAM BLISS
SHREE UMA ENTERPRISE
Revenue Survey 865/3, T.P. No. - 52, F.P. No. – 865/3/1 (Phase-1) & 865/3/2 (Phase-2), Moje - Tarsali, Taluka-District: Vadodara
Approved
21st Apr 2023
Pending
28th Feb 2028
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA11642/210423
Acknowledgement No.
PR/VADODARA/VADODARA/GUJRERA/230316/014312
Project Type
Residential/Group Housing
Approving Authority
Others
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | SHIVAM BLISS |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA11642/210423 |
| Acknowledgement Number | PR/VADODARA/VADODARA/GUJRERA/230316/014312 |
| Project Description | 86 RESIDENTIAL UNITS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Revenue Survey 865/3, T.P. No. - 52, F.P. No. – 865/3/1 (Phase-1) & 865/3/2 (Phase-2), Moje - Tarsali, Taluka-District: Vadodara |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2023-04-21 |
| Start Date | 2023-03-01 |
| End Date | 2028-02-28 |
| Submission Date | 2023-03-10 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 10840.0 |
| Total Land Area (Registered) | 10657.07 |
| Total Covered Area | 4289.4 |
| Total Open Area | 6550.6 |
| Total Carpet Area | 6697.78 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 77521400 |
| Estimated Project Cost | 272650000 |
| Total Project Cost | 350171400 |
Promoter Details
| Promoter Name | SHREE UMA ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| shi*************@gmail.com | |
| Mobile | 97******** |
| Company Registration No. | GUJVA103471 |
| PAN | AEK******* |
| Date of Incorporation | 2021-04-12 |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 8400 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | ASHOK DAMJIBHAI PRAJAPATI |
| PAN | ANF******* |
| Address | F 26 Raghuvir Nagar Near MGM School, New Sama Road |
| Partner 2 | JAGDISH ANILBHAI PATEL |
| PAN | ADB******* |
| Address | 111, HIRABAUG SOCIETY SUSSEN TARSALI ROAD |
| Partner 3 | PRAVIN MOHANBHAI PATEL |
| PAN | ACQ******* |
| Address | 31 B AMIN PARK NEAR KIRAN NAGAR, MANJALPUR VADODARA |
| Partner 4 | MUKESHBHAI PRAVINBHAI PATEL |
| PAN | AQZ******* |
| Address | GORVA FALIYU, TARSALI GAM |
| Partner 5 | MANOJBHAI JASHBHAI PATEL |
| PAN | ADR******* |
| Address | NAVI NAGRI, ABHOL |
| Partner 6 | JITENDRA JASHBHAI PATEL |
| PAN | AAO******* |
| Address | A 1 PRAMUKH SOCIETY NEAR SANDESARA ESTATE, ATLADRA |
| Partner 7 | JASVANTSINH KANAKSINH SINORA |
| PAN | AFS******* |
| Address | A1 96 SIDDHARTH BUNGLOWS, NEAR KENDRIYA SCHOOL SAMA SAVLI ROAD |
| Partner 8 | NIRMALA GOVINDPRASAD AGRAWAL |
| PAN | AEE******* |
| Address | 2 SOHAM BUNGLOWS 1 SAIYAD VASNA ROAD, NEAR MANISHA CHOKDI |
| Partner 9 | NAUSAD SAMSUDDIN BAXI |
| PAN | ABX******* |
| Address | A 6 7 BASERA DUPLEX NEAR SAMARAPAN SOCIETY, VASNA AKOTA |
| Partner 10 | KARAMSHIBHAI DAHYABHAI PRAJAPATI |
| PAN | ADT******* |
| Address | 172 1 KENYA NAGAR, ABHILASHA CHAR RASTA |
| Partner 11 | KAUSHIK KUMAR ARVINDBHAI PATEL |
| PAN | BBS******* |
| Address | GORWA FALIYU, NEAR RANCHODRAI TEMPLE |
| Partner 12 | PRITESH LAVJIBHAI KATUDIYA |
| PAN | BJJ******* |
| Address | B 42 SACHIDANAND SOCIETY SWATI SOCIETY, NEW SAMA ROAD |
| Partner 13 | DHRUVIL PATEL |
| PAN | CVX******* |
| Address | GORWA FALIYU, TARSALI NEAR RANCHODRAI TEMPLE |
| Partner 14 | PUNIT DEVSHIBHAI PATHAR |
| PAN | EEE******* |
| Address | 203 SANVELI RESIDENCY, SARTHANA JAKATNAKA SURAT CITY |
| Partner 15 | MANOJKUMAR RAJPUT |
| PAN | ABW******* |
| Address | A 71 TULJANAGAR 2, BEHIND MAKARPURA DEPO |
| Partner 16 | SANGITABEN BHAVANBHAI PRAJAPATI |
| PAN | BXE******* |
| Address | C 13 NILKANTHESHWAR SOCIETY, NEAR AKASH GANGA SOCEITY NEW SAMA ROAD |
Building Blocks
| PLOT 1 TO 20 - Start Date | 2023-03-01 |
| PLOT 1 TO 20 - End Date | 2028-02-28 |
| PLOT 1 TO 20 - Progress | 70.0% |
| PLOT 1 TO 20 - Booked Units | 14 |
| PLOT 1 TO 20 - Unbooked Units | 6 |
| PLOT 21 - Start Date | 2023-03-01 |
| PLOT 21 - End Date | 2028-02-28 |
| PLOT 21 - Progress | 100.0% |
| PLOT 21 - Booked Units | 1 |
| PLOT 21 - Unbooked Units | 0 |
| PLOT 22 - Start Date | 2023-03-01 |
| PLOT 22 - End Date | 2028-02-28 |
| PLOT 22 - Progress | 100.0% |
| PLOT 22 - Booked Units | 1 |
| PLOT 22 - Unbooked Units | 0 |
| PLOT 23 TO 38 - Start Date | 2023-03-01 |
| PLOT 23 TO 38 - End Date | 2028-02-28 |
| PLOT 23 TO 38 - Progress | 93.75% |
| PLOT 23 TO 38 - Booked Units | 15 |
| PLOT 23 TO 38 - Unbooked Units | 1 |
| PLOT 39 TO 51 - Start Date | 2023-03-01 |
| PLOT 39 TO 51 - End Date | 2028-02-28 |
| PLOT 39 TO 51 - Progress | 69.23% |
| PLOT 39 TO 51 - Booked Units | 9 |
| PLOT 39 TO 51 - Unbooked Units | 4 |
| PLOT 52 - Start Date | 2023-03-01 |
| PLOT 52 - End Date | 2028-02-28 |
| PLOT 52 - Progress | 100.0% |
| PLOT 52 - Booked Units | 1 |
| PLOT 52 - Unbooked Units | 0 |
| PLOT 53 - Start Date | 2023-03-01 |
| PLOT 53 - End Date | 2028-02-28 |
| PLOT 53 - Progress | 0.0% |
| PLOT 53 - Booked Units | 0 |
| PLOT 53 - Unbooked Units | 1 |
| PLOT 54 TO 63 - Start Date | 2023-03-01 |
| PLOT 54 TO 63 - End Date | 2028-02-28 |
| PLOT 54 TO 63 - Progress | 80.0% |
| PLOT 54 TO 63 - Booked Units | 8 |
| PLOT 54 TO 63 - Unbooked Units | 2 |
| PLOT 64 - Start Date | 2023-03-01 |
| PLOT 64 - End Date | 2028-02-28 |
| PLOT 64 - Progress | 100.0% |
| PLOT 64 - Booked Units | 1 |
| PLOT 64 - Unbooked Units | 0 |
| PLOT 65 - Start Date | 2023-03-01 |
| PLOT 65 - End Date | 2028-02-28 |
| PLOT 65 - Progress | 100.0% |
| PLOT 65 - Booked Units | 1 |
| PLOT 65 - Unbooked Units | 0 |
| PLOT 66 TO 75 - Start Date | 2023-03-01 |
| PLOT 66 TO 75 - End Date | 2028-02-28 |
| PLOT 66 TO 75 - Progress | 30.0% |
| PLOT 66 TO 75 - Booked Units | 3 |
| PLOT 66 TO 75 - Unbooked Units | 7 |
| PLOT 76 - Start Date | 2023-03-01 |
| PLOT 76 - End Date | 2028-02-28 |
| PLOT 76 - Progress | 100.0% |
| PLOT 76 - Booked Units | 1 |
| PLOT 76 - Unbooked Units | 0 |
| PLOT 77 - Start Date | 2023-03-01 |
| PLOT 77 - End Date | 2028-02-28 |
| PLOT 77 - Progress | 100.0% |
| PLOT 77 - Booked Units | 1 |
| PLOT 77 - Unbooked Units | 0 |
| PLOT 78 TO 85 - Start Date | 2023-03-01 |
| PLOT 78 TO 85 - End Date | 2028-02-28 |
| PLOT 78 TO 85 - Progress | 87.5% |
| PLOT 78 TO 85 - Booked Units | 7 |
| PLOT 78 TO 85 - Unbooked Units | 1 |
| PLOT 86 - Start Date | 2023-03-01 |
| PLOT 86 - End Date | 2028-02-28 |
| PLOT 86 - Progress | 0.0% |
| PLOT 86 - Booked Units | 0 |
| PLOT 86 - Unbooked Units | 1 |
Inventory Units
| RESIDENTIAL UNITS - Total Units | 86 |
| RESIDENTIAL UNITS - Carpet Area | 6697.78 |
| RESIDENTIAL UNITS - Exclusive Area | 0.0 |
| RESIDENTIAL UNITS - Open Terrace Area | 173.72 |
Quarterly Progress
| September 2023 | 17.72% |
| December 2023 | 18.19% |
| July 2024 | 34.67% |
| October 2024 | 40.79% |
| October 2025 | 64.59% |
| January 2026 | 75.95% |
| April 2026 | 84.38% |
Professionals
| Architect | KIRAN RASHIKBHAI PATEL |
| Licence No. | CA/2011/51825 |
| Engineer | DHRUV C PATEL |
| Licence No. | EOR-258/2019-2024 |
| Contractor | DEVSHIBHAI V PATHAR |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in