shivam enclave duplex
shivam engineers
fp no 14 tp scheme no 44 village bapod ajwa road vadodara, beside kamlanagar ajwa road vadodara
Approved
11th Sept 2017
Completed
20th Jul 2018
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA00117/110917
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170731/001292
Project Type
Residential/Group Housing
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | shivam enclave duplex |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA00117/110917 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170731/001292 |
| Project Description | 38 residential duplex having A B C D E situated on fp no 14 tp scheme no 44 village bapod ajwa road vadodara |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | fp no 14 tp scheme no 44 village bapod ajwa road vadodara, beside kamlanagar ajwa road vadodara |
| Pincode | 390019 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2017-09-11 |
| Start Date | 2015-07-20 |
| End Date | 2018-07-20 |
| Submission Date | 2017-07-31 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 4367.0 |
| Total Covered Area | 1542.0 |
| Total Open Area | 1347.0 |
| Open Parking Area | 380 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 38 |
| Cost of Land | 34935680 |
| Estimated Project Cost | 78419440 |
| Total Project Cost | 113355120 |
Land Details
| Moje | Bapod |
| TP No. | 44 |
| TP Name | Bapod |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | shivam engineers |
| Promoter Type | PARTNERSHIP FIRM |
| shi******@hotmail.com | |
| Mobile | 92******** |
| Company Registration No. | AASFS8214Q |
| PAN | AAS******* |
| Experience (Years) | 28 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 1 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | nilesh manibhai patel |
| Address | 255 amit nagar society, amit nagar circle vip road karelibaug vadodara |
Building Blocks
| D 01 - Start Date | 2015-07-20 |
| D 01 - End Date | 2018-07-20 |
| D 01 - Progress | 100.0% |
| D 01 - Booked Units | 1 |
| D 01 - Unbooked Units | 0 |
| A 02 - Start Date | 2015-07-20 |
| A 02 - End Date | 2018-07-20 |
| A 02 - Progress | 100.0% |
| A 02 - Booked Units | 1 |
| A 02 - Unbooked Units | 0 |
| A 03 - Start Date | 2015-07-20 |
| A 03 - End Date | 2018-07-20 |
| A 03 - Progress | 100.0% |
| A 03 - Booked Units | 1 |
| A 03 - Unbooked Units | 0 |
| A 04 - Start Date | 2015-07-20 |
| A 04 - End Date | 2018-07-20 |
| A 04 - Progress | 100.0% |
| A 04 - Booked Units | 1 |
| A 04 - Unbooked Units | 0 |
| A 05 - Start Date | 2015-07-20 |
| A 05 - End Date | 2018-07-20 |
| A 05 - Progress | 100.0% |
| A 05 - Booked Units | 1 |
| A 05 - Unbooked Units | 0 |
| A 06 - Start Date | 2015-07-20 |
| A 06 - End Date | 2018-07-20 |
| A 06 - Progress | 0.0% |
| A 06 - Booked Units | 0 |
| A 06 - Unbooked Units | 1 |
| A 07 - Start Date | 2015-07-20 |
| A 07 - End Date | 2018-07-20 |
| A 07 - Progress | 100.0% |
| A 07 - Booked Units | 1 |
| A 07 - Unbooked Units | 0 |
| B 08 - Start Date | 2015-07-20 |
| B 08 - End Date | 2018-07-20 |
| B 08 - Progress | 100.0% |
| B 08 - Booked Units | 1 |
| B 08 - Unbooked Units | 0 |
| C 09 - Start Date | 2015-07-20 |
| C 09 - End Date | 2018-07-20 |
| C 09 - Progress | 0.0% |
| C 09 - Booked Units | 0 |
| C 09 - Unbooked Units | 1 |
| A 10 - Start Date | 2015-07-20 |
| A 10 - End Date | 2018-07-20 |
| A 10 - Progress | 0.0% |
| A 10 - Booked Units | 0 |
| A 10 - Unbooked Units | 1 |
| A 11 - Start Date | 2015-07-20 |
| A 11 - End Date | 2018-07-20 |
| A 11 - Progress | 0.0% |
| A 11 - Booked Units | 0 |
| A 11 - Unbooked Units | 1 |
| A 12 - Start Date | 2015-07-20 |
| A 12 - End Date | 2018-07-20 |
| A 12 - Progress | 0.0% |
| A 12 - Booked Units | 0 |
| A 12 - Unbooked Units | 1 |
| A 13 - Start Date | 2015-07-20 |
| A 13 - End Date | 2018-07-20 |
| A 13 - Progress | 0.0% |
| A 13 - Booked Units | 0 |
| A 13 - Unbooked Units | 1 |
| D 14 - Start Date | 2015-07-20 |
| D 14 - End Date | 2018-07-20 |
| D 14 - Progress | 100.0% |
| D 14 - Booked Units | 1 |
| D 14 - Unbooked Units | 0 |
| D 15 - Start Date | 2015-07-20 |
| D 15 - End Date | 2018-07-20 |
| D 15 - Progress | 100.0% |
| D 15 - Booked Units | 1 |
| D 15 - Unbooked Units | 0 |
| A 16 - Start Date | 2015-07-20 |
| A 16 - End Date | 2018-07-20 |
| A 16 - Progress | 100.0% |
| A 16 - Booked Units | 1 |
| A 16 - Unbooked Units | 0 |
| D 17 - Start Date | 2015-07-20 |
| D 17 - End Date | 2018-07-20 |
| D 17 - Progress | 100.0% |
| D 17 - Booked Units | 1 |
| D 17 - Unbooked Units | 0 |
| D 18 - Start Date | 2015-07-20 |
| D 18 - End Date | 2018-07-20 |
| D 18 - Progress | 100.0% |
| D 18 - Booked Units | 1 |
| D 18 - Unbooked Units | 0 |
| A 19 - Start Date | 2015-07-20 |
| A 19 - End Date | 2018-07-20 |
| A 19 - Progress | 100.0% |
| A 19 - Booked Units | 1 |
| A 19 - Unbooked Units | 0 |
| A 20 - Start Date | 2015-07-20 |
| A 20 - End Date | 2018-07-20 |
| A 20 - Progress | 100.0% |
| A 20 - Booked Units | 1 |
| A 20 - Unbooked Units | 0 |
| A 21 - Start Date | 2015-07-20 |
| A 21 - End Date | 2018-07-20 |
| A 21 - Progress | 100.0% |
| A 21 - Booked Units | 1 |
| A 21 - Unbooked Units | 0 |
| A 22 - Start Date | 2015-07-20 |
| A 22 - End Date | 2018-07-20 |
| A 22 - Progress | 100.0% |
| A 22 - Booked Units | 1 |
| A 22 - Unbooked Units | 0 |
| D 23 - Start Date | 2015-07-20 |
| D 23 - End Date | 2018-07-20 |
| D 23 - Progress | 100.0% |
| D 23 - Booked Units | 1 |
| D 23 - Unbooked Units | 0 |
| D 24 - Start Date | 2015-07-20 |
| D 24 - End Date | 2018-07-20 |
| D 24 - Progress | 100.0% |
| D 24 - Booked Units | 1 |
| D 24 - Unbooked Units | 0 |
| D 25 - Start Date | 2015-07-20 |
| D 25 - End Date | 2018-07-20 |
| D 25 - Progress | 100.0% |
| D 25 - Booked Units | 1 |
| D 25 - Unbooked Units | 0 |
| D 26 - Start Date | 2015-07-20 |
| D 26 - End Date | 2018-07-20 |
| D 26 - Progress | 100.0% |
| D 26 - Booked Units | 1 |
| D 26 - Unbooked Units | 0 |
| A 27 - Start Date | 2015-07-20 |
| A 27 - End Date | 2018-07-20 |
| A 27 - Progress | 100.0% |
| A 27 - Booked Units | 1 |
| A 27 - Unbooked Units | 0 |
| D 28 - Start Date | 2015-07-20 |
| D 28 - End Date | 2018-07-20 |
| D 28 - Progress | 100.0% |
| D 28 - Booked Units | 1 |
| D 28 - Unbooked Units | 0 |
| D 29 - Start Date | 2015-07-20 |
| D 29 - End Date | 2018-07-20 |
| D 29 - Progress | 0.0% |
| D 29 - Booked Units | 0 |
| D 29 - Unbooked Units | 1 |
| E 30 - Start Date | 2015-07-20 |
| E 30 - End Date | 2018-07-20 |
| E 30 - Progress | 0.0% |
| E 30 - Booked Units | 0 |
| E 30 - Unbooked Units | 1 |
| E 31 - Start Date | 2015-07-20 |
| E 31 - End Date | 2018-07-20 |
| E 31 - Progress | 0.0% |
| E 31 - Booked Units | 0 |
| E 31 - Unbooked Units | 1 |
| E 32 - Start Date | 2015-07-20 |
| E 32 - End Date | 2018-07-20 |
| E 32 - Progress | 100.0% |
| E 32 - Booked Units | 1 |
| E 32 - Unbooked Units | 0 |
| E 33 - Start Date | 2015-07-20 |
| E 33 - End Date | 2018-07-20 |
| E 33 - Progress | 0.0% |
| E 33 - Booked Units | 0 |
| E 33 - Unbooked Units | 1 |
| E 34 - Start Date | 2015-07-20 |
| E 34 - End Date | 2018-07-20 |
| E 34 - Progress | 100.0% |
| E 34 - Booked Units | 1 |
| E 34 - Unbooked Units | 0 |
| E 35 - Start Date | 2015-07-20 |
| E 35 - End Date | 2018-07-20 |
| E 35 - Progress | 0.0% |
| E 35 - Booked Units | 0 |
| E 35 - Unbooked Units | 1 |
| E 36 - Start Date | 2015-07-20 |
| E 36 - End Date | 2018-07-20 |
| E 36 - Progress | 0.0% |
| E 36 - Booked Units | 0 |
| E 36 - Unbooked Units | 1 |
| E 37 - Start Date | 2015-07-20 |
| E 37 - End Date | 2018-07-20 |
| E 37 - Progress | 100.0% |
| E 37 - Booked Units | 1 |
| E 37 - Unbooked Units | 0 |
| D 38 - Start Date | 2015-07-20 |
| D 38 - End Date | 2018-07-20 |
| D 38 - Progress | 100.0% |
| D 38 - Booked Units | 1 |
| D 38 - Unbooked Units | 0 |
Inventory Units
| 38 units A 16 units B 1 unit C 1 unit D 12 units E 8 units - Total Units | 19 |
| 38 units A 16 units B 1 unit C 1 unit D 12 units E 8 units - Carpet Area | 3168.0 |
| 38 units A 16 units B 1 unit C 1 unit D 12 units E 8 units - Exclusive Area | 37.0 |
| 38 units A 16 units B 1 unit C 1 unit D 12 units E 8 units - Open Terrace Area | 1741.0 |
Quarterly Progress
| May 2018 | 99.58% |
| August 2018 | 99.58% |
| August 2018 | 99.58% |
Professionals
| Architect | RISHI ARCHITECT AND INTERIOR DESIGNERS |
| Licence No. | ER 07 2016 2019 |
| Engineer | P M PATEL & COMPANY |
| Licence No. | VMC SH 93 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in