Shreenathji Builders Darshan
Shreenathji Darshan, B/h Krishna Darshan Villa, Before Gayatri Temple, New Waghodiya Road
Approved
22nd Dec 2017
Completed
3rd Oct 2019
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA01094/EX1/280219
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170902/002042
Project Type
Residential/Group Housing
Approving Authority
Vadodara Urban Development Authority
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | Shreenathji Darshan |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA01094/EX1/280219 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170902/002042 |
| Project Description | 5.5 BHK Triplex Bungalows |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Shreenathji Darshan, B/h Krishna Darshan Villa, Before Gayatri Temple, New Waghodiya Road |
| Pincode | 390019 |
| State | Gujarat |
| Approving Authority | Vadodara Urban Development Authority |
| Approved On | 2017-12-22 |
| Start Date | 2017-06-27 |
| End Date | 2019-10-03 |
| Submission Date | 2017-09-02 |
| Months Delayed | 0 |
| Total Land Area | 2823.0 |
| Total Covered Area | 1008.86 |
| Total Open Area | 1814.14 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 18114300 |
| Estimated Project Cost | 70000000 |
| Total Project Cost | 105000000 |
| Moje | Ankhol |
| Promoter Name | Shreenathji Builders Darshan |
| Promoter Type | PARTNERSHIP FIRM |
| shreenathjidarshan9987@gmail.com | |
| Mobile | 9974673693 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ADGFS2637G |
| Experience (Years) | 2 |
| Area Constructed (sqm) | 25000 |
| Projects Completed | 1 |
| Ongoing Projects | 4 |
| Partner 1 | Daxesh Shah |
| Address | SF-206, SAKAR COMPLEX, NR. SUPER BAKERY, NEW VIP ROAD |
| 1 - Start Date | 2017-06-27 |
| 1 - End Date | 2019-10-03 |
| 1 - Progress | 100.0% |
| 1 - Booked Units | 1 |
| 1 - Unbooked Units | 0 |
| 2 - Start Date | 2017-06-27 |
| 2 - End Date | 2019-10-03 |
| 2 - Progress | 100.0% |
| 2 - Booked Units | 1 |
| 2 - Unbooked Units | 0 |
| 3 - Start Date | 2017-06-27 |
| 3 - End Date | 2019-10-03 |
| 3 - Progress | 100.0% |
| 3 - Booked Units | 1 |
| 3 - Unbooked Units | 0 |
| 4 - Start Date | 2017-06-27 |
| 4 - End Date | 2019-10-03 |
| 4 - Progress | 0.0% |
| 4 - Booked Units | 0 |
| 4 - Unbooked Units | 1 |
| 5 - Start Date | 2017-06-27 |
| 5 - End Date | 2019-10-03 |
| 5 - Progress | 0.0% |
| 5 - Booked Units | 0 |
| 5 - Unbooked Units | 1 |
| 6 - Start Date | 2017-06-27 |
| 6 - End Date | 2019-10-03 |
| 6 - Progress | 0.0% |
| 6 - Booked Units | 0 |
| 6 - Unbooked Units | 1 |
| 7 - Start Date | 2017-06-27 |
| 7 - End Date | 2019-10-03 |
| 7 - Progress | 100.0% |
| 7 - Booked Units | 1 |
| 7 - Unbooked Units | 0 |
| 8 - Start Date | 2017-06-27 |
| 8 - End Date | 2019-10-03 |
| 8 - Progress | 100.0% |
| 8 - Booked Units | 1 |
| 8 - Unbooked Units | 0 |
| 9 - Start Date | 2017-06-27 |
| 9 - End Date | 2019-10-03 |
| 9 - Progress | 100.0% |
| 9 - Booked Units | 1 |
| 9 - Unbooked Units | 0 |
| 10 - Start Date | 2017-06-27 |
| 10 - End Date | 2019-10-03 |
| 10 - Progress | 100.0% |
| 10 - Booked Units | 1 |
| 10 - Unbooked Units | 0 |
| 11 - Start Date | 2017-06-27 |
| 11 - End Date | 2019-10-03 |
| 11 - Progress | 100.0% |
| 11 - Booked Units | 1 |
| 11 - Unbooked Units | 0 |
| 12 - Start Date | 2017-06-27 |
| 12 - End Date | 2019-10-03 |
| 12 - Progress | 100.0% |
| 12 - Booked Units | 1 |
| 12 - Unbooked Units | 0 |
| 13 - Start Date | 2017-06-27 |
| 13 - End Date | 2019-10-03 |
| 13 - Progress | 100.0% |
| 13 - Booked Units | 1 |
| 13 - Unbooked Units | 0 |
| 14 - Start Date | 2017-06-27 |
| 14 - End Date | 2019-10-03 |
| 14 - Progress | 100.0% |
| 14 - Booked Units | 1 |
| 14 - Unbooked Units | 0 |
| 15 - Start Date | 2017-06-27 |
| 15 - End Date | 2019-10-03 |
| 15 - Progress | 100.0% |
| 15 - Booked Units | 1 |
| 15 - Unbooked Units | 0 |
| 16 - Start Date | 2017-06-27 |
| 16 - End Date | 2019-10-03 |
| 16 - Progress | 100.0% |
| 16 - Booked Units | 1 |
| 16 - Unbooked Units | 0 |
| 17 - Start Date | 2017-06-27 |
| 17 - End Date | 2019-10-03 |
| 17 - Progress | 100.0% |
| 17 - Booked Units | 1 |
| 17 - Unbooked Units | 0 |
| 18 - Start Date | 2017-06-27 |
| 18 - End Date | 2019-10-03 |
| 18 - Progress | 100.0% |
| 18 - Booked Units | 1 |
| 18 - Unbooked Units | 0 |
| 19 - Start Date | 2017-06-27 |
| 19 - End Date | 2019-10-03 |
| 19 - Progress | 100.0% |
| 19 - Booked Units | 1 |
| 19 - Unbooked Units | 0 |
| 20 - Start Date | 2017-06-27 |
| 20 - End Date | 2019-10-03 |
| 20 - Progress | 0.0% |
| 20 - Booked Units | 0 |
| 20 - Unbooked Units | 1 |
| 21 - Start Date | 2017-06-27 |
| 21 - End Date | 2019-10-03 |
| 21 - Progress | 0.0% |
| 21 - Booked Units | 0 |
| 21 - Unbooked Units | 1 |
| 22 - Start Date | 2017-06-27 |
| 22 - End Date | 2019-10-03 |
| 22 - Progress | 0.0% |
| 22 - Booked Units | 0 |
| 22 - Unbooked Units | 1 |
| Residential - Total Units | 22 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 2530.44 |
| Residential - Exclusive Area | 2530.44 |
| Residential - Open Terrace Area | 0.0 |
| May 2018 | 37.44% |
| August 2018 | 49.11% |
| Architect | Anjali Associate |
| Licence No. | ER 36 2016-2017 |
| Engineer | Zarna Associates |
| Licence No. | SH 64 16-19 |
| Contractor | Set Square Construction |