SHREE GANESH INFRA HOMES
SHYAMAL PARK, OPP.SHREEM SHRUSTI, NR.NILAMBER ORIENCE,, SUN PHARMA ROAD, VADODARA.
Approved
14th Sept 2018
Pending
30th Sept 2026
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA03409/140918
Acknowledgement No.
PR/VADODARA/VADODARA/GANDHINAGAR TPO/180804/005884
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | SHYAMAL PARK |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA03409/140918 |
| Acknowledgement Number | PR/VADODARA/VADODARA/GANDHINAGAR TPO/180804/005884 |
| Project Description | TOTAL 990 UNITS 619 FLATS 371 SHOPS & OFFICES TOTAL 24 NUMBER OF BUILDINGS COMMERCIAL A B C D E F G H I J K L M N O P Q R S T A1B1 C1D1 E1 |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | SHYAMAL PARK, OPP.SHREEM SHRUSTI, NR.NILAMBER ORIENCE,, SUN PHARMA ROAD, VADODARA. |
| Pincode | 390012 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-09-14 |
| Start Date | 2018-07-07 |
| End Date | 2026-09-30 |
| Submission Date | 2018-08-04 |
| Months Delayed | 0 |
| Total Land Area | 47013.0 |
| Total Covered Area | 16163.86 |
| Total Open Area | 12114.14 |
| Open Parking Area | 9444.49 |
| Covered Parking Area | 12384.79 |
| Covered Parking Count | 30 |
| Parking for Sale Count | 16 |
| Cost of Land | 604322295 |
| Estimated Project Cost | 1170000000 |
| Total Project Cost | 1904322295 |
| Moje | Vadodara |
| TP No. | 27 |
| TP Name | Tandalaja |
| Plot No. | Tandalja |
| Sub Plot No. | - |
| Promoter Name | SHREE GANESH INFRA HOMES |
| Promoter Type | PARTNERSHIP FIRM |
| shyamalpark501@gmail.com | |
| Mobile | 9427212665 |
| Company Registration No. | GUJVA101192 |
| PAN | ADAFS6446F |
| Date of Incorporation | 2016-04-11 |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 92903 |
| Projects Completed | 0 |
| Ongoing Projects | 4 |
| Partner 1 | CHIRAG RAMNIKLAL TILVA |
| PAN | ADNPT9776E |
| Address | 401, KISHAN HIGHTS, NR.AKOTA STADIUM,, AKOTA, VADODARA. |
| Partner 2 | AMITKUMAR RAMNIKLAL TILVA |
| PAN | ADNPT9775H |
| Address | 401, KISHAN HIGHTS, NR.AKOTA STADIUM,, AKOTA |
| Partner 3 | EKTA CHIRAG TILVA |
| PAN | AIPPT5836Q |
| Address | 401-Kisan Hights, 27-Guruprasad Society, Opp.Akota Stadium, Akota,, AKOTA |
| Partner 4 | NIRJU AMIT TILVA |
| PAN | AIPPT5719A |
| Address | 401-Kisan Hights, 27-Guruprasad Society, Opp.Akota Stadium, Akota,, AKOTA |
| Partner 5 | RAMNIKLAL SAVJIBHAI TILVA |
| PAN | AAWPT3618B |
| Address | B/30 NILAGAN APPT NEAR TADAV DARVAJA, JUNAGARH |
| Partner 6 | VANITAGAURI RAMNIKLAL TILVA |
| PAN | AAYPT4596J |
| Address | 401-Kisan Hights, 27-Guruprasad Society, Opp.Akota Stadium, Akota,, AKOTA |
| COMMERCIAL - Start Date | 2018-07-07 |
| COMMERCIAL - End Date | 2026-09-30 |
| COMMERCIAL - Progress | 16.09% |
| COMMERCIAL - Booked Units | 56 |
| COMMERCIAL - Unbooked Units | 292 |
| TOWER A - Start Date | 2018-07-07 |
| TOWER A - End Date | 2026-09-30 |
| TOWER A - Progress | 100.0% |
| TOWER A - Booked Units | 26 |
| TOWER A - Unbooked Units | 0 |
| TOWER B - Start Date | 2018-07-07 |
| TOWER B - End Date | 2026-09-30 |
| TOWER B - Progress | 100.0% |
| TOWER B - Booked Units | 26 |
| TOWER B - Unbooked Units | 0 |
| TOWER C - Start Date | 2018-07-07 |
| TOWER C - End Date | 2026-09-30 |
| TOWER C - Progress | 80.77% |
| TOWER C - Booked Units | 21 |
| TOWER C - Unbooked Units | 5 |
| TOWER D - Start Date | 2018-07-07 |
| TOWER D - End Date | 2026-09-30 |
| TOWER D - Progress | 73.08% |
| TOWER D - Booked Units | 19 |
| TOWER D - Unbooked Units | 7 |
| TOWER E - Start Date | 2018-07-07 |
| TOWER E - End Date | 2026-09-30 |
| TOWER E - Progress | 61.54% |
| TOWER E - Booked Units | 16 |
| TOWER E - Unbooked Units | 10 |
| TOWER F - Start Date | 2018-07-07 |
| TOWER F - End Date | 2026-09-30 |
| TOWER F - Progress | 76.92% |
| TOWER F - Booked Units | 20 |
| TOWER F - Unbooked Units | 6 |
| TOWER G - Start Date | 2018-07-07 |
| TOWER G - End Date | 2026-09-30 |
| TOWER G - Progress | 65.38% |
| TOWER G - Booked Units | 17 |
| TOWER G - Unbooked Units | 9 |
| TOWER H - Start Date | 2018-07-07 |
| TOWER H - End Date | 2026-09-30 |
| TOWER H - Progress | 50.0% |
| TOWER H - Booked Units | 13 |
| TOWER H - Unbooked Units | 13 |
| TOWER I - Start Date | 2018-07-07 |
| TOWER I - End Date | 2026-09-30 |
| TOWER I - Progress | 38.46% |
| TOWER I - Booked Units | 10 |
| TOWER I - Unbooked Units | 16 |
| TOWER J - Start Date | 2018-07-07 |
| TOWER J - End Date | 2026-09-30 |
| TOWER J - Progress | 34.62% |
| TOWER J - Booked Units | 9 |
| TOWER J - Unbooked Units | 17 |
| TOWER K - Start Date | 2018-07-07 |
| TOWER K - End Date | 2026-09-30 |
| TOWER K - Progress | 30.77% |
| TOWER K - Booked Units | 8 |
| TOWER K - Unbooked Units | 18 |
| TOWER L - Start Date | 2018-07-07 |
| TOWER L - End Date | 2026-09-30 |
| TOWER L - Progress | 38.46% |
| TOWER L - Booked Units | 10 |
| TOWER L - Unbooked Units | 16 |
| TOWER M - Start Date | 2018-07-07 |
| TOWER M - End Date | 2026-09-30 |
| TOWER M - Progress | 100.0% |
| TOWER M - Booked Units | 7 |
| TOWER M - Unbooked Units | 0 |
| TOWER N - Start Date | 2018-07-07 |
| TOWER N - End Date | 2026-09-30 |
| TOWER N - Progress | 69.23% |
| TOWER N - Booked Units | 18 |
| TOWER N - Unbooked Units | 8 |
| TOWER O - Start Date | 2018-07-07 |
| TOWER O - End Date | 2026-09-30 |
| TOWER O - Progress | 96.15% |
| TOWER O - Booked Units | 25 |
| TOWER O - Unbooked Units | 1 |
| TOWER P - Start Date | 2018-07-07 |
| TOWER P - End Date | 2026-09-30 |
| TOWER P - Progress | 92.31% |
| TOWER P - Booked Units | 24 |
| TOWER P - Unbooked Units | 2 |
| TOWER Q - Start Date | 2018-07-07 |
| TOWER Q - End Date | 2026-09-30 |
| TOWER Q - Progress | 92.31% |
| TOWER Q - Booked Units | 24 |
| TOWER Q - Unbooked Units | 2 |
| TOWER R - Start Date | 2018-07-07 |
| TOWER R - End Date | 2026-09-30 |
| TOWER R - Progress | 92.31% |
| TOWER R - Booked Units | 24 |
| TOWER R - Unbooked Units | 2 |
| TOWER S - Start Date | 2018-07-07 |
| TOWER S - End Date | 2026-09-30 |
| TOWER S - Progress | 92.31% |
| TOWER S - Booked Units | 24 |
| TOWER S - Unbooked Units | 2 |
| TOWER T - Start Date | 2018-07-07 |
| TOWER T - End Date | 2026-09-30 |
| TOWER T - Progress | 96.15% |
| TOWER T - Booked Units | 25 |
| TOWER T - Unbooked Units | 1 |
| TOWER A1B1 - Start Date | 2018-07-07 |
| TOWER A1B1 - End Date | 2026-09-30 |
| TOWER A1B1 - Progress | 89.23% |
| TOWER A1B1 - Booked Units | 58 |
| TOWER A1B1 - Unbooked Units | 7 |
| TOWER C1D1 - Start Date | 2018-07-07 |
| TOWER C1D1 - End Date | 2026-09-30 |
| TOWER C1D1 - Progress | 88.0% |
| TOWER C1D1 - Booked Units | 44 |
| TOWER C1D1 - Unbooked Units | 6 |
| TOWER E1 - Start Date | 2018-07-07 |
| TOWER E1 - End Date | 2026-09-30 |
| TOWER E1 - Progress | 100.0% |
| TOWER E1 - Booked Units | 26 |
| TOWER E1 - Unbooked Units | 0 |
| RESIDENTIAL & COMMERCIAL - Total Units | 990 |
| RESIDENTIAL & COMMERCIAL - Carpet Area | 64273.02 |
| RESIDENTIAL & COMMERCIAL - Exclusive Area | 8248.44 |
| RESIDENTIAL & COMMERCIAL - Open Terrace Area | 0.0 |
| February 2019 | 24.13% |
| May 2019 | 24.5% |
| August 2019 | 31.59% |
| November 2019 | 31.73% |
| February 2020 | 37.71% |
| August 2020 | 39.87% |
| November 2020 | 42.31% |
| February 2021 | 45.68% |
| May 2021 | 48.07% |
| August 2021 | 60.17% |
| November 2021 | 63.28% |
| February 2022 | 68.52% |
| May 2022 | 71.87% |
| August 2022 | 75.11% |
| November 2022 | 76.71% |
| February 2023 | 80.94% |
| May 2023 | 82.09% |
| August 2023 | 85.27% |
| November 2023 | 86.94% |
| January 2024 | 86.97% |
| April 2024 | 88.21% |
| July 2024 | 89.17% |
| October 2024 | 89.29% |
| October 2025 | 99.59% |
| April 2026 | 99.64% |
| Architect | RUCHIR SHETH |
| Licence No. | CA/2011/53220 |
| Engineer | AASHUTOSH A. DESAI |
| Licence No. | SH-78 |
| Contractor | SHREE GANESH INFRASTRUCTURE |