SAMANVAY SPARSH
Near Vasna Bhayli Crossing, Tandalja Sun Pharma Road
Approved
16th Sept 2019
Completed
30th Sept 2023
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA06040/160919
Acknowledgement No.
PR/VADODARA/VADODARA/GANDHINAGAR TPO/190820/007949
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | Star City I |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA06040/160919 |
| Acknowledgement Number | PR/VADODARA/VADODARA/GANDHINAGAR TPO/190820/007949 |
| Project Description | Mixed Development |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Near Vasna Bhayli Crossing, Tandalja Sun Pharma Road |
| Pincode | 390012 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2019-09-16 |
| Start Date | 2019-08-06 |
| End Date | 2023-09-30 |
| Submission Date | 2019-08-07 |
| Months Delayed | 0 |
| Total Land Area | 11472.0 |
| Total Covered Area | 4202.94 |
| Total Open Area | 7269.06 |
| Open Parking Area | 545.54 |
| Covered Parking Area | 5357.59 |
| Covered Parking Count | 31 |
| Parking for Sale Count | 2 |
| Cost of Land | 227896069 |
| Estimated Project Cost | 482000000 |
| Total Project Cost | 709896060 |
| Moje | Tandalja |
| TP No. | 26 |
| TP Name | Tandalja |
| Promoter Name | SAMANVAY SPARSH |
| Promoter Type | PARTNERSHIP FIRM |
| starcity3.rera@gmail.com | |
| Mobile | 8347834433 |
| Company Registration No. | GUJVA101475 |
| PAN | ADDFS7131E |
| Date of Incorporation | 2016-08-31 |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 2000000 |
| Projects Completed | 9 |
| Ongoing Projects | 2 |
| Partner 1 | RAVI JAYESHBHAI RAO |
| PAN | AJJPR8142C |
| Address | SOLITAIRE, 9 VEMALI, SAMA SAVLI ROAD |
| Partner 2 | ANKUR ATISH PAREKH |
| PAN | BMBPP3074K |
| Address | 8 PRABHUPARK SOCIETY, RACE COURSE |
| Partner 3 | VISHAL KANUBHAI PATEL |
| PAN | BRFPP7611D |
| Address | A14/2, 202, SAMANVAY SAPTARSHI, MORE MEGA STORE CAMPUS MANJALPUR |
| Partner 4 | CHINTAN DIVYANG BRAHMBHATT |
| PAN | BAEPB2109N |
| Address | 16-B, SHANTIVAN PARK SOCIETY, NEAR, VACCINE INSTITUTE |
| Tower A - Start Date | 2019-08-06 |
| Tower A - End Date | 2023-09-30 |
| Tower A - Progress | 83.87% |
| Tower A - Booked Units | 26 |
| Tower A - Unbooked Units | 5 |
| Tower B - Start Date | 2019-08-06 |
| Tower B - End Date | 2023-09-30 |
| Tower B - Progress | 88.24% |
| Tower B - Booked Units | 30 |
| Tower B - Unbooked Units | 4 |
| Tower C - Start Date | 2019-08-06 |
| Tower C - End Date | 2023-09-30 |
| Tower C - Progress | 94.12% |
| Tower C - Booked Units | 32 |
| Tower C - Unbooked Units | 2 |
| Tower D - Start Date | 2019-08-06 |
| Tower D - End Date | 2023-09-30 |
| Tower D - Progress | 78.12% |
| Tower D - Booked Units | 25 |
| Tower D - Unbooked Units | 7 |
| Tower E - Start Date | 2019-08-06 |
| Tower E - End Date | 2023-09-30 |
| Tower E - Progress | 83.78% |
| Tower E - Booked Units | 31 |
| Tower E - Unbooked Units | 6 |
| Tower F - Start Date | 2019-08-06 |
| Tower F - End Date | 2023-09-30 |
| Tower F - Progress | 72.73% |
| Tower F - Booked Units | 24 |
| Tower F - Unbooked Units | 9 |
| Tower G - Start Date | 2019-08-06 |
| Tower G - End Date | 2023-09-30 |
| Tower G - Progress | 77.42% |
| Tower G - Booked Units | 24 |
| Tower G - Unbooked Units | 7 |
| Tower H - Start Date | 2019-08-06 |
| Tower H - End Date | 2023-09-30 |
| Tower H - Progress | 96.43% |
| Tower H - Booked Units | 27 |
| Tower H - Unbooked Units | 1 |
| Tower I - Start Date | 2019-08-06 |
| Tower I - End Date | 2023-09-30 |
| Tower I - Progress | 96.43% |
| Tower I - Booked Units | 27 |
| Tower I - Unbooked Units | 1 |
| Tower J - Start Date | 2019-08-06 |
| Tower J - End Date | 2023-09-30 |
| Tower J - Progress | 96.43% |
| Tower J - Booked Units | 27 |
| Tower J - Unbooked Units | 1 |
| Tower K - Start Date | 2019-08-06 |
| Tower K - End Date | 2023-09-30 |
| Tower K - Progress | 91.67% |
| Tower K - Booked Units | 33 |
| Tower K - Unbooked Units | 3 |
| Tower L - Start Date | 2019-08-06 |
| Tower L - End Date | 2023-09-30 |
| Tower L - Progress | 82.14% |
| Tower L - Booked Units | 46 |
| Tower L - Unbooked Units | 10 |
| Tower M - Start Date | 2019-08-06 |
| Tower M - End Date | 2023-09-30 |
| Tower M - Progress | 92.86% |
| Tower M - Booked Units | 52 |
| Tower M - Unbooked Units | 4 |
| Shops and Flats - Total Units | 464 |
| Shops and Flats - Carpet Area | 20970.8 |
| Shops and Flats - Exclusive Area | 1442.31 |
| Shops and Flats - Open Terrace Area | 718.81 |
| August 2020 | 43.22% |
| November 2020 | 43.22% |
| February 2021 | 44.73% |
| May 2021 | 44.73% |
| August 2021 | 44.73% |
| November 2021 | 44.71% |
| February 2022 | 45.87% |
| May 2022 | 59.91% |
| August 2022 | 62.32% |
| November 2022 | 70.66% |
| February 2023 | 73.03% |
| May 2023 | 82.63% |
| August 2023 | 84.41% |
| October 2023 | 100.0% |
| Architect | Nirmal Shah |
| Licence No. | CA/2017/82643 |
| Engineer | Zarna Associates |
| Licence No. | SEOR-1/63 |
| Contractor | Jay Ambe enterprise |