Star City I
SAMANVAY SPARSH
Near Vasna Bhayli Crossing, Tandalja Sun Pharma Road
Approved
16th Sept 2019
Completed
30th Sept 2023
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA06040/160919
Acknowledgement No.
PR/VADODARA/VADODARA/GANDHINAGAR TPO/190820/007949
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | Star City I |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA06040/160919 |
| Acknowledgement Number | PR/VADODARA/VADODARA/GANDHINAGAR TPO/190820/007949 |
| Project Description | Mixed Development |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Near Vasna Bhayli Crossing, Tandalja Sun Pharma Road |
| Pincode | 390012 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2019-09-16 |
| Start Date | 2019-08-06 |
| End Date | 2023-09-30 |
| Submission Date | 2019-08-07 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 11472.0 |
| Total Covered Area | 4202.94 |
| Total Open Area | 7269.06 |
| Open Parking Area | 545.54 |
| Covered Parking Area | 5357.59 |
| Covered Parking Count | 31 |
| Parking for Sale Count | 2 |
| Cost of Land | 227896069 |
| Estimated Project Cost | 482000000 |
| Total Project Cost | 709896060 |
Land Details
| Moje | Tandalja |
| TP No. | 26 |
| TP Name | Tandalja |
Promoter Details
| Promoter Name | SAMANVAY SPARSH |
| Promoter Type | PARTNERSHIP FIRM |
| sta***********@gmail.com | |
| Mobile | 83******** |
| Company Registration No. | GUJVA101475 |
| PAN | ADD******* |
| Date of Incorporation | 2016-08-31 |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 2000000 |
| Projects Completed | 9 |
| Ongoing Projects | 2 |
Promoter Partners
| Partner 1 | RAVI JAYESHBHAI RAO |
| PAN | AJJ******* |
| Address | SOLITAIRE, 9 VEMALI, SAMA SAVLI ROAD |
| Partner 2 | ANKUR ATISH PAREKH |
| PAN | BMB******* |
| Address | 8 PRABHUPARK SOCIETY, RACE COURSE |
| Partner 3 | VISHAL KANUBHAI PATEL |
| PAN | BRF******* |
| Address | A14/2, 202, SAMANVAY SAPTARSHI, MORE MEGA STORE CAMPUS MANJALPUR |
| Partner 4 | CHINTAN DIVYANG BRAHMBHATT |
| PAN | BAE******* |
| Address | 16-B, SHANTIVAN PARK SOCIETY, NEAR, VACCINE INSTITUTE |
Building Blocks
| Tower A - Start Date | 2019-08-06 |
| Tower A - End Date | 2023-09-30 |
| Tower A - Progress | 83.87% |
| Tower A - Booked Units | 26 |
| Tower A - Unbooked Units | 5 |
| Tower B - Start Date | 2019-08-06 |
| Tower B - End Date | 2023-09-30 |
| Tower B - Progress | 88.24% |
| Tower B - Booked Units | 30 |
| Tower B - Unbooked Units | 4 |
| Tower C - Start Date | 2019-08-06 |
| Tower C - End Date | 2023-09-30 |
| Tower C - Progress | 94.12% |
| Tower C - Booked Units | 32 |
| Tower C - Unbooked Units | 2 |
| Tower D - Start Date | 2019-08-06 |
| Tower D - End Date | 2023-09-30 |
| Tower D - Progress | 78.12% |
| Tower D - Booked Units | 25 |
| Tower D - Unbooked Units | 7 |
| Tower E - Start Date | 2019-08-06 |
| Tower E - End Date | 2023-09-30 |
| Tower E - Progress | 83.78% |
| Tower E - Booked Units | 31 |
| Tower E - Unbooked Units | 6 |
| Tower F - Start Date | 2019-08-06 |
| Tower F - End Date | 2023-09-30 |
| Tower F - Progress | 72.73% |
| Tower F - Booked Units | 24 |
| Tower F - Unbooked Units | 9 |
| Tower G - Start Date | 2019-08-06 |
| Tower G - End Date | 2023-09-30 |
| Tower G - Progress | 77.42% |
| Tower G - Booked Units | 24 |
| Tower G - Unbooked Units | 7 |
| Tower H - Start Date | 2019-08-06 |
| Tower H - End Date | 2023-09-30 |
| Tower H - Progress | 96.43% |
| Tower H - Booked Units | 27 |
| Tower H - Unbooked Units | 1 |
| Tower I - Start Date | 2019-08-06 |
| Tower I - End Date | 2023-09-30 |
| Tower I - Progress | 96.43% |
| Tower I - Booked Units | 27 |
| Tower I - Unbooked Units | 1 |
| Tower J - Start Date | 2019-08-06 |
| Tower J - End Date | 2023-09-30 |
| Tower J - Progress | 96.43% |
| Tower J - Booked Units | 27 |
| Tower J - Unbooked Units | 1 |
| Tower K - Start Date | 2019-08-06 |
| Tower K - End Date | 2023-09-30 |
| Tower K - Progress | 91.67% |
| Tower K - Booked Units | 33 |
| Tower K - Unbooked Units | 3 |
| Tower L - Start Date | 2019-08-06 |
| Tower L - End Date | 2023-09-30 |
| Tower L - Progress | 82.14% |
| Tower L - Booked Units | 46 |
| Tower L - Unbooked Units | 10 |
| Tower M - Start Date | 2019-08-06 |
| Tower M - End Date | 2023-09-30 |
| Tower M - Progress | 92.86% |
| Tower M - Booked Units | 52 |
| Tower M - Unbooked Units | 4 |
Inventory Units
| Shops and Flats - Total Units | 464 |
| Shops and Flats - Carpet Area | 20970.8 |
| Shops and Flats - Exclusive Area | 1442.31 |
| Shops and Flats - Open Terrace Area | 718.81 |
Quarterly Progress
| August 2020 | 43.22% |
| November 2020 | 43.22% |
| February 2021 | 44.73% |
| May 2021 | 44.73% |
| August 2021 | 44.73% |
| November 2021 | 44.71% |
| February 2022 | 45.87% |
| May 2022 | 59.91% |
| August 2022 | 62.32% |
| November 2022 | 70.66% |
| February 2023 | 73.03% |
| May 2023 | 82.63% |
| August 2023 | 84.41% |
| October 2023 | 100.0% |
Professionals
| Architect | Nirmal Shah |
| Licence No. | CA/2017/82643 |
| Engineer | Zarna Associates |
| Licence No. | SEOR-1/63 |
| Contractor | Jay Ambe enterprise |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in