THE FLORENCE
ARCH INFRA
THE FLORENCE , NR. SWAMINARAYAN TEMPLE, VASNA BHAYLI ROAD
Approved
25th Jun 2018
Completed
30th Jun 2024
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA02997/250618
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/180530/005456
Project Type
Mixed Development
Approving Authority
Vadodara Urban Development Authority
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | THE FLORENCE |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA02997/250618 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/180530/005456 |
| Project Description | RESIDENCIAL CUM COMMERCIAL |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | THE FLORENCE , NR. SWAMINARAYAN TEMPLE, VASNA BHAYLI ROAD |
| Pincode | 391410 |
| State | Gujarat |
| Approving Authority | Vadodara Urban Development Authority |
| Approved On | 2018-06-25 |
| Start Date | 2018-05-25 |
| End Date | 2024-06-30 |
| Submission Date | 2018-05-30 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 3833.0 |
| Total Covered Area | 1732.0 |
| Total Open Area | 2101.0 |
| Open Parking Area | 1506 |
| Covered Parking Area | 891.0 |
| Covered Parking Count | 5 |
| Parking for Sale Count | 7 |
| Cost of Land | 35350000 |
| Estimated Project Cost | 230000000 |
| Total Project Cost | 266310000 |
Land Details
| Moje | Bhayli |
| TP No. | 4 |
| TP Name | ( Bhayli ) |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | ARCH INFRA |
| Promoter Type | PARTNERSHIP FIRM |
| the************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | 24ABDFA9548B1ZO |
| PAN | ABD******* |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 14000 |
| Projects Completed | 02 |
| Ongoing Projects | 01 |
Promoter Partners
| Partner 1 | GOVINDBHAI BHARWAD |
| Address | THE FLORENE , NR. LALITA PARTY PLOT ,, B/S SWAMINARAYAN TEMPLE , VASNA BHAYLI ROAD , |
Building Blocks
| A - Start Date | 2018-05-25 |
| A - End Date | 2024-06-30 |
| A - Progress | 91.18% |
| A - Booked Units | 31 |
| A - Unbooked Units | 3 |
| B - Start Date | 2018-05-25 |
| B - End Date | 2024-06-30 |
| B - Progress | 100.0% |
| B - Booked Units | 28 |
| B - Unbooked Units | 0 |
| C - Start Date | 2018-05-25 |
| C - End Date | 2024-06-30 |
| C - Progress | 100.0% |
| C - Booked Units | 38 |
| C - Unbooked Units | 0 |
| D - Start Date | 2018-05-25 |
| D - End Date | 2024-06-30 |
| D - Progress | 91.18% |
| D - Booked Units | 31 |
| D - Unbooked Units | 3 |
| E - Start Date | 2018-05-25 |
| E - End Date | 2024-06-30 |
| E - Progress | 100.0% |
| E - Booked Units | 28 |
| E - Unbooked Units | 0 |
Inventory Units
| 0 - Total Units | 0 |
| 0 - Carpet Area | 9436.0 |
| 0 - Exclusive Area | 956.0 |
| 0 - Open Terrace Area | 0.0 |
Quarterly Progress
| November 2018 | 14.34% |
| February 2019 | 15.3% |
| May 2019 | 26.46% |
| August 2019 | 39.23% |
| November 2019 | 53.88% |
| February 2020 | 55.42% |
| August 2020 | 66.0% |
| November 2020 | 69.41% |
| February 2021 | 71.68% |
| May 2021 | 72.83% |
| August 2021 | 73.24% |
| November 2021 | 81.34% |
| February 2022 | 86.72% |
| May 2022 | 93.93% |
| July 2024 | 100.0% |
Professionals
| Architect | RUCHIR SHETH |
| Licence No. | ca/2011/53220 |
| Engineer | zarna associates |
| Licence No. | SH-64 |
| Contractor | Shreeji construction |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in