Apex Infratec
Survey No. 1154, Near Akra Maruti Temple, Opp. Akra Lake, Umbergaon Sanjan Road, Umbergaon.
Approved
10th Apr 2019
Completed
30th Sept 2023
Registration No.
PR/GJ/VALSAD/UMBERGAON/Others/MAA05250/EX1/011022
Acknowledgement No.
PR/VALSAD/UMBERGAON/VALSAD TPO/190228/006828
Project Type
Mixed Development
Approving Authority
Umargam Area Development Authority
District
Valsad
Taluka
Umbergaon
State
Gujarat
| Project Name | Apex Lake View |
| RERA Number | PR/GJ/VALSAD/UMBERGAON/Others/MAA05250/EX1/011022 |
| Acknowledgement Number | PR/VALSAD/UMBERGAON/VALSAD TPO/190228/006828 |
| Project Description | Residential Cum Commercial High Rise Building ( Ground Floor + 8 Floors ) |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Valsad |
| Taluka | Umbergaon |
| Address | Survey No. 1154, Near Akra Maruti Temple, Opp. Akra Lake, Umbergaon Sanjan Road, Umbergaon. |
| Pincode | 396170 |
| State | Gujarat |
| Approving Authority | Umargam Area Development Authority |
| Approved On | 2019-04-10 |
| Start Date | 2019-03-15 |
| End Date | 2023-09-30 |
| Submission Date | 2019-02-15 |
| Months Delayed | 0 |
| Total Land Area | 4944.0 |
| Total Covered Area | 1235.93 |
| Total Open Area | 3708.07 |
| Open Parking Area | 1273.13 |
| Covered Parking Area | 89.75 |
| Covered Parking Count | 9 |
| Parking for Sale Count | 115 |
| Cost of Land | 24945900 |
| Estimated Project Cost | 165500000 |
| Total Project Cost | 190445900 |
| Moje | UMARGAM |
| Promoter Name | Apex Infratec |
| Promoter Type | PARTNERSHIP FIRM |
| info@apexinfratec.com | |
| Mobile | 9821086980 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ABIFA7815Q |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
| Partner 1 | Jagdish Babu Salian |
| Address | D-604, Gokul Vihar-1, Near Cambridge School, Thakur Complex, Kandivali (E), Mumbai |
| Partner 2 | Devshankar Sushil Choudhary |
| Address | A/1701, Shree Siddhivinayak Tower, Padma Nagar, Chikuwadi, Opp. Phoenix Hospital, Borivali (W), Mumbai. |
| Partner 3 | Parag Bipinbhai Shah |
| Address | B-201, Umang Building, Mathurdas Extn Road, Opp. Atul Tower, Kandivali (W), Mumbai. |
| Apex Lake View A Wing - Start Date | 2019-03-15 |
| Apex Lake View A Wing - End Date | 2023-09-30 |
| Apex Lake View A Wing - Progress | 63.64% |
| Apex Lake View A Wing - Booked Units | 28 |
| Apex Lake View A Wing - Unbooked Units | 16 |
| Apex Lake View B Wing - Start Date | 2019-03-15 |
| Apex Lake View B Wing - End Date | 2023-09-30 |
| Apex Lake View B Wing - Progress | 65.62% |
| Apex Lake View B Wing - Booked Units | 21 |
| Apex Lake View B Wing - Unbooked Units | 11 |
| Apex Lake View C Wing - Start Date | 2019-03-15 |
| Apex Lake View C Wing - End Date | 2023-09-30 |
| Apex Lake View C Wing - Progress | 65.22% |
| Apex Lake View C Wing - Booked Units | 30 |
| Apex Lake View C Wing - Unbooked Units | 16 |
| Shop - Total Units | 22 |
| Shop - Completed Units | 0 |
| Shop - Booked Units | 0 |
| Shop - Carpet Area | 975.66 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| Residential - Total Units | 100 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 6889.73 |
| Residential - Exclusive Area | 1361.45 |
| Residential - Open Terrace Area | 0.0 |
| September 2019 | 12.75% |
| December 2019 | 12.75% |
| March 2020 | 25.5% |
| September 2020 | 41.01% |
| December 2020 | 41.56% |
| March 2021 | 49.47% |
| June 2021 | 56.57% |
| September 2021 | 64.81% |
| December 2021 | 67.29% |
| March 2022 | 68.53% |
| June 2022 | 70.04% |
| September 2022 | 72.25% |
| December 2022 | 79.96% |
| March 2023 | 90.69% |
| June 2023 | 91.76% |
| September 2023 | 91.76% |
| Contractor | ABS Enterprises |