JPG GREEN VIEW

ARRYA INFRATECH

Ballari

Approved

6th Apr 2023

Completed

31st Dec 2024

Registration No.

PRM/KA/RERA/1248/469/PR/060423/005844

Acknowledgement No.

ACK/KA/RERA/1248/469/PR/050323/006914

Project Type

Plotted Development

District

Ballari

Taluka

Ballari

State

Karnataka

Project Details

Number of Survey No./CMC No./CTS No./PID No.5
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmPartnership Firm
Promoter NameARRYA INFRATECH
Main ObjectivesFORMATION OF RESIDENTIAL LAYOUTS
Registration NumberBLYF144201920
PANAXFPM1528H
GSTIN29ABRFA0394B1ZE
Promoter AddressNO.05, GROUND FLOOR, KARNATAKA ENGINEERS ASSOCIATION BUILDING,S N PET MAIN ROAD ,Ballari ,Ballari-583101
DistrictBallari
TalukBallari
PIN Code583101
Name of Authorized SignatoryM MADHUSUDHAN REDDY
Number of Partners4
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?YES
Project NameGADIGI'S EMPIRE-8
Project DescriptionRESIDENTIAL LAYOUT AT SIRIVARA VILLAGE BALLARI TALUK & DISTRICT IN 3.43 ACRES
Type of ProjectPlotted Development
Current StatusCompleted
Is there any case pending ?NO
Is Payment Pertaining to Project Land Pending ?NO
Project AddressSY NO 143/A SIRIVARA VILLAGE BALLARI TALUK & DISTRICT
State/UTKarnataka
Pin Code583103
Expected Completion Date31-03-2023
Present AddressMANIKANTA NILAYA 1ST LINK ROAD VENKATESWARA NAGAR , Ballari , Karnataka - 583101
Permanent AddressMANIKANTA NILAYA 1ST LINK ROAD VENKATESWARA NAGAR , Ballari , Karnataka - 583101
Official AddressARRYA INFRATECH NO.05 GROUND FLOOR, KARNATAKA ENGINEERS ASSOCIATION BUILDING, S N PET MAIN ROAD , Ballari , Karnataka - 583101
Sl No.
Sl No._1
Sl No._2

Modification Plan Details

Type of InventoryODD SITES
No of Inventory15
Carpet Area (Sq Mtr)2461 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11INTERMEDIATEODD440.79525NANA24.1427.1617.1417.23Site No. 02Sy No.218/69 Mtr RoadSy No. 213
22INTERMEDIATEODD242.1419NANA7.8812.142424.3830 Mtr RoadSite No. 01Site No. 3 & 4Sy No. 213
33CORNER - COMMERCIAL12 mtr x 15 mtr180NANA1212151530 Mtr RoadSite No. 049 Mtr RoadSite No. 02
44INTERMEDIATE9 mtr x 12 mtr108NANA121299Site No. 03Site No. 019 Mtr RoadSite No. 02
55CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 06Site No. 129 Mtr Road
66INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 05Site No. 07Site No. 119 Mtr Road
77INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 06Site No. 08Site No. 109 Mtr Road
88INTERMEDIATEODD124.2NANA15158.348.22Site No. 07Sy No.218/6Site No. 099 Mtr Road
99INTERMEDIATEODD126.075NANA15158.478.34Site No. 10Sy No.218/69 Mtr RoadSite No. 08
1010INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 11Site No. 099 Mtr RoadSite No. 07
1111INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 12Site No. 109 Mtr RoadSite No. 06
1212CORNER - COMMERCIAL15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 119 Mtr RoadSite No. 05
1313CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 14Site No. 209 Mtr Road
1414INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 13Site No. 15Site No. 199 Mtr Road
1515INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 14Site No. 16Site No. 189 Mtr Road
1616INTERMEDIATEODD129NANA15158.548.66Site No. 15Sy No.218/6Site No. 179 Mtr Road
1717INTERMEDIATEODD130.875NANA15158.798.66Site No. 18Sy No.218/69 Mtr RoadSite No. 16
1818INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 19Site No. 179 Mtr RoadSite No. 15
1919INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 20Site No. 189 Mtr RoadSite No. 14
2020CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 199 Mtr RoadSite No. 13
2121CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 22Site No. 289 Mtr Road
2222INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 21Site No. 23Site No. 279 Mtr Road
2323INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 22Site No. 24Site No. 269 Mtr Road
2424INTERMEDIATEODD133.8NANA15158.988.86Site No. 23Sy No.218/6Site No. 259 Mtr Road
2525INTERMEDIATEODD135.675NANA15159.118.98Site No. 26Sy No.218/69 Mtr RoadSite No. 24
2626INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 27Site No. 259 Mtr RoadSite No. 23
2727INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 28Site No. 269 Mtr RoadSite No. 22
2828CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 279 Mtr RoadSite No. 21
2929CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 30Site No. 369 Mtr Road
3030INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 29Site No. 31Site No. 359 Mtr Road
3131INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 30Site No. 32Site No. 349 Mtr Road
3232INTERMEDIATEODD138.6NANA15159.39.18Site No. 31Sy No.218/6Site No. 339 Mtr Road
3333INTERMEDIATEODD140.475NANA15159.439.3Site No. 34Sy No.218/69 Mtr RoadSite No. 32
3434INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 35Site No. 339 Mtr RoadSite No. 31
3535INTERMEDIATE9 mtr x 15 mtr135NANA151599Site No. 36Site No. 349 Mtr RoadSite No. 30
3636CORNER15 mtr x 15 mtr225NANA1515151530 Mtr RoadSite No. 359 Mtr RoadSite No. 29
3737CORNER12 mtr x 15 mtr180NANA1212151530 Mtr RoadSite No. 38Site No. 419 Mtr Road
3838INTERMEDIATE9 mtr x 12 mtr108NANA121299Site No. 37Site No. 39Site No. 419 Mtr Road
3939INTERMEDIATEODD223.245NANA24.5825.0399Site No. 38 & 41Site No. 409 Mtr Road9 Mtr Road
4040INTERMEDIATEODD242.544NANA25.0325.59.79.5Site No. 39Sy No.218/69 Mtr Road9 Mtr Road
4141CORNERODD287.34035NANA11.412.5823.932430 Mtr RoadSite No. 399 Mtr RoadSite No. 37 & 38
4242INTERMEDIATEODD199.140125NANA11.8814.471515.23Sy No. 218/430 Mtr RoadSite No. 43Sy No. 213
4343INTERMEDIATE15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 44Site No. 42
4444INTERMEDIATE12 mtr x 15 mtr180NANA12121515Sy No. 218/430 Mtr RoadSite No. 45Site No. 43
4545CORNER12 mtr x 15 mtr180NANA12121515Sy No. 218/430 Mtr Road9 Mtr RoadSite No. 44
4646CORNER15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 479 Mtr Road
4747INTERMEDIATE15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 48Site No. 46
4848INTERMEDIATE - COMMERCIAL9 mtr x 15 mtr135NANA991515Sy No. 218/430 Mtr RoadSite No. 49Site No. 47
4949INTERMEDIATE15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 50Site No. 48
5050CORNER15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr Road9 Mtr RoadSite No. 49
5151CORNER15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 529 Mtr Road
5252INTERMEDIATE15 mtr x 15 mtr225NANA15151515Sy No. 218/430 Mtr RoadSite No. 53Site No. 51
5353INTERMEDIATE9 mtr x 15 mtr135NANA991515Sy No. 218/430 Mtr RoadSite No. 54Site No. 52
5454INTERMEDIATE12 mtr x 15 mtr180NANA12121515Sy No. 218/430 Mtr RoadSite No. 55Site No. 53
5555CORNERODD143.1954NANA9.179.9115.0215Sy No. 218/430 Mtr Road9 Mtr RoadSite No. 54

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes01-01-202331-03-2023
2Formation Of Road, FootpathYes01-04-202330-06-2023
3Construction Of Water Supply InfrastuctureYes01-07-202330-09-2023
4Construction Of Sewage System InfrastuctureYes01-10-202331-12-2023
5Power Supply Work(Transformer & Substation)Yes01-01-202431-03-2024
6Construction Of Storm Water DrainageYes01-04-202430-06-2024
7Solid Waste Management and DisposalNo
8Tree Plantation And LandScape WorkYes01-10-202431-12-2024
9Street LightingYes01-09-202430-09-2024
10Sewage Treatment Plant (STP)No
11Other Miscellaneous WorkYes01-12-202431-12-2024

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksNo
11Power BackupNo
12Piped GasNo
13Water and SanitationNo
14Air conditioningNo

Post Registration Details

Total number of Plots55
No. of Public and Semi Pubic Sites0
Area of Public and Semi Pubic Sites(in Sq.m)0
No. of Parks and Open Spaces0
Area of Parks and Open Spaces(in Sq.m)0
Area of Road/Transportation(in Sq.m)8492

Completion Details

Project Start Date01-01-2023
Project End Date31-12-2024
If any extension of time has been grantedNO
Cost of land12970199
Cost of construction7038801
Total cost20009000
Total amount collected From buyers850000
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project29285641
Total No of sites of Project55
Total No of sites sold1
Total No of sites unsold54
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Bangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy