M ALLAH BAKSHA
Sy No.39/2A, 8TH WARD, KONDANAYAKANAHALLI,, HOSAPETE TALUK BELLARY DISTRICT
Approved
22nd Dec 2020
Completed
31st Mar 2021
Registration No.
PRM/KA/RERA/1248/440/PR/201222/003757
Acknowledgement No.
ACK/KA/RERA/1248/440/PR/201121/004379
Project Type
Plotted Development
Approving Authority
Local Planing Authority
District
Ballari
Taluka
Hospet
State
Karnataka
| Project Name | M A B LAYOUT PHASE I |
| Project Description | Residential Layout with 22 plots of different dimensions |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 01-12-2018 |
| Proposed Project Completion Date | 31-03-2021 |
| Total Area Of Land (Sq Mtr) | 3035 |
| Total Coverd Area (Sq Mtr) | 2113 |
| Total Open Area (Sq Mtr) | 922 |
| Estimated Cost of Construction (INR) | 2450000 |
| Cost of Land (INR) | 3732750 |
| Total Project Cost (INR) | 6182750 |
| Project Address | Sy No.39/2A, 8TH WARD, KONDANAYAKANAHALLI,, HOSAPETE TALUK BELLARY DISTRICT |
| District | Ballari |
| Taluk | Hospet |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | Residential Layout |
| No of Inventory | 22 |
| Carpet Area (Sq Mtr) | 0SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | Axis Bank |
| Branch | Hospet (KT) |
| ifscCode | UTIB0000618 |
| Account No.(70% Account) | 917010007515927 |
| State | Karnataka |
| Name | Bharathi Hiremath |
| Address | Behind Markandeshwara School, ,M.P.Prakash Nagar, Hosapet |
| Pin Code | 583201 |
| Year Of Establishment | 1993 |
| Number of Project Completed | 40 |
| Reg. Of COA No. | CA 98 23892 |
| Local Authority Licence Number | HPT BL 10052 19 20 |
| Firm Type | Individual |
| Name | M ALLAH BAKSHA |
| Father's Name | Late M Hussain Sab |
| PAN Number | AGAPA9327Q |
| Fax Number | 0 |
| Address | H.NO 377,29TH WARD,NEAR 100 BED HOSPITAL ROAD,,M J NAGAR, 3RD MAIN CROSS, HOSAPETE |
| State/UT | Karnataka |
| PIN Code | 583201 |
| Sl No. |
| Type of Inventory | Residential Layout |
| No of Inventory | 22 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | odd | odd | 102.412 sq mt | Phase 1 | NA | odd | odd | odd | odd | 9m road | plot no 2 | 9m road | s.no.39/1 |
| 2 | 2 | even | 9*12 m | 108sq mt | Phase 2 | NA | 12m | 12m | 9m | 9m | plot no 1 | plot no 3 | 9m road | s.no.39/1 |
| 3 | 3 | even | 9*12 m | 108sq mt | Phase 3 | NA | 12m | 12m | 9m | 9m | plot no 2 | plot no 4 | 9m road | s.no.39/1 |
| 4 | 4 | even | 9*12 m | 108sq mt | Phase 4 | NA | 12m | 12m | 9m | 9m | plot no3 | plot no5 | 9m road | s.no.39/1 |
| 5 | 5 | even | 9*12 m | 108sq mt | Phase 5 | NA | 12m | 12m | 9m | 9m | plot no4 | plot no6 | 9m road | s.no.39/1 |
| 6 | 6 | even | 9*12 m | 108sq mt | Phase 6 | NA | 12m | 12m | 9m | 9m | plot no5 | plot no7 | 9m road | s.no.39/1 |
| 7 | 7 | even | 9*12 m | 108sq mt | Phase 7 | NA | 12m | 12m | 9m | 9m | plot no6 | plot no8 | 9m road | s.no.39/1 |
| 8 | 8 | even | 9*12 m | 108sq mt | Phase 8 | NA | 12m | 12m | 9m | 9m | plot no7 | plot no9 | 9m road | s.no.39/1 |
| 9 | 9 | even | 9*12 m | 108sq mt | Phase 9 | NA | 12m | 12m | 9m | 9m | plot no8 | plot no10 | 9m road | s.no.39/1 |
| 10 | 10 | even | 9*12 m | 108sq mt | Phase 10 | NA | 12m | 12m | 9m | 9m | plot no9 | plot no11 | 9m road | s.no.39/1 |
| 11 | 11 | even | 9*12 m | 108sq mt | Phase 11 | NA | 12m | 12m | 9m | 9m | plot no 10 | s.no.39/4 | 9m road | s.no.39/1 |
| 12 | 12 | uneven | 9*odd | 105.3 sq mt | Phase 12 | NA | odd | odd | 9m | 9m | plot no 13 | s.no.39/4 | s.no.39/2b | 9m road |
| 13 | 13 | uneven | 9*odd | 105.3 sq mt | Phase 13 | NA | odd | odd | 9m | 9m | plot no14 | plot no12 | s.no.39/2b | 9m road |
| 14 | 14 | uneven | 9*odd | 105.3 sq mt | Phase 14 | NA | odd | odd | 9m | 9m | plot no15 | plot no13 | s.no.39/2b | 9m road |
| 15 | 15 | uneven | 9*odd | 105.3 sq mt | Phase 15 | NA | odd | odd | 9m | 9m | plot no16 | plot no14 | s.no.39/2b | 9m road |
| 16 | 16 | uneven | 9*odd | 105.3 sq mt | Phase 16 | NA | odd | odd | 9m | 9m | plot no17 | plot no15 | s.no.39/2b | 9m road |
| 17 | 17 | uneven | 9*odd | 105.3 sq mt | Phase 17 | NA | odd | odd | 9m | 9m | plot no18 | plot no16 | s.no.39/2b | 9m road |
| 18 | 18 | uneven | 9*odd | 105.3 sq mt | Phase 18 | NA | odd | odd | 9m | 9m | plot no19 | plot no17 | s.no.39/2b | 9m road |
| 19 | 19 | uneven | 9*odd | 105.3 sq mt | Phase 19 | NA | odd | odd | 9m | 9m | plot no20 | plot no18 | s.no.39/2b | 9m road |
| 20 | 20 | uneven | 9*odd | 105.3 sq mt | Phase 20 | NA | odd | odd | 9m | 9m | plot no 21 | plot no19 | s.no.39/2b | 9m road |
| 21 | 21 | uneven | 9*odd | 105.3 sq mt | Phase 21 | NA | odd | odd | 9m | 9m | plot no22 | plot no20 | s.no.39/2b | 9m road |
| 22 | 22 | odd | odd | 80.467 sq mt | Phase 22 | NA | odd | odd | odd | odd | 9m road | plot no21 | s.no.39/2b | 9m road |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 10-10-2018 | 22-06-2019 |
| 2 | Formation Of Road, Footpath | Yes | 16-02-2019 | 12-04-2019 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 28-02-2019 | 14-03-2019 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 15-01-2019 | 28-02-2019 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 02-03-2019 | 07-09-2019 |
| 6 | Construction Of Storm Water Drainage | Yes | 02-11-2018 | 10-01-2019 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | Yes | 10-05-2019 | 17-08-2019 |
| 9 | Street Lighting | Yes | 02-09-2019 | 07-09-2019 |
| 10 | Other Miscellaneous Work | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | No |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning and incarnation | No |
| Total number of Plots | 22 |
| No. of Public and Semi Pubic Sites | 0 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 0 |
| No. of Parks and Open Spaces | 0 |
| Area of Parks and Open Spaces(in Sq.m) | 0 |
| Area of Road/Transportation(in Sq.m) | 922 |
| Project Start Date | 01-12-2018 |
| Project End Date | 31-03-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 3732750 |
| Cost of construction | 2450000 |
| Total cost | 6182750 |
| Total amount collected From buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 2797814 |
| Total No of sites of Project | 22 |
| Total No of sites sold | 0 |
| Total No of sites unsold | 22 |
| Whether there is any changes in inventory details | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |