SHEIK SIRAJUDDIN
Sanduru
Approved
14th Sept 2023
Completed
31st Dec 2024
Registration No.
PRM/KA/RERA/1248/444/PR/140923/006260
Acknowledgement No.
ACK/KA/RERA/1248/444/PR/080623/007178
Project Type
Plotted Development
District
Ballari
Taluka
Sanduru
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Proprietorship |
| Promoter Name | SHEIK SIRAJUDDIN |
| Main Objectives | Development of real estate |
| Trade Name | SHEIK SIRAJUDDIN |
| Registration Number | UDYAM-KR-05-0024780 |
| PAN | APLPS0617K |
| GSTIN | NA |
| Promoter Address | Aashiyana, KHB Colony,14th Ward Sandur Bellary District, Karnataka 583119 ,Sanduru ,Ballari-583119 |
| District | Ballari |
| Taluk | Sanduru |
| PIN Code | 583119 |
| Name of Authorized Signatory | SHEIK SIRAJUDDIN |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | NO |
| Present Address | Aashiyana, KHB Colony, 14th Ward Sandur Bellary District, Karnataka 583119 , Ballari , Karnataka - 583119 |
| Permanent Address | Aashiyana, KHB Colony, 14th Ward Sandur Bellary District, Karnataka 583119 , Ballari , Karnataka - 583119 |
| Official Address | Aashiyana, KHB Colony, 14th Ward Sandur Bellary District, Karnataka 583119 , Ballari , Karnataka - 583119 |
| Sl No. |
| Type of Inventory | 9 X 15 M |
| No of Inventory | 20 |
| Carpet Area (Sq Mtr) | 2700 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Residencial | ODD | 525 | 1 | 1 | 17.1 | 17.6 | 33.02 | 28.45 | 9 M road | 6 M road | 3 M way | 9 M road |
| 2 | 2 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | Site No 7 | 9 M road | Empty | Site No 3 |
| 3 | 3 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | Site No 6 | 9 M road | Site No 2 | Site No 4 |
| 4 | 4 | Residencial | ODD | 209 | 1 | 1 | 13.75 | 14.08 | 15 | 14.9 | Site No 5 | 9 M road | Site No 3 | 9 M road |
| 5 | 5 | Residencial | ODD | 204 | 1 | 1 | 13.43 | 13.75 | 14.9 | 15 | 9 M road | Site No 4 | Site No 6 | 9 M road |
| 6 | 6 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | 9 M road | Site No 3 | Site No 7 | Site No 5 |
| 7 | 7 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | 9 M road | Site No 2 | Empty | Site No 6 |
| 8 | 8 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | Site No 13 | 9 M road | Empty | Site No 9 |
| 9 | 9 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | Site No 12 | 9 M road | Site No 8 | Site No 10 |
| 10 | 10 | Residencial | ODD | 196 | 1 | 1 | 12.91 | 13.23 | 15 | 14.8 | Site No 11 | 9 M road | Site No 9 | 9 M road |
| 11 | 11 | Residencial | ODD | 191 | 1 | 1 | 12.58 | 12.91 | 14.8 | 15 | 9 M road | Site No 10 | Site No 12 | 9 M road |
| 12 | 12 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | 9 M road | Site No 9 | Site No 13 | Site No 11 |
| 13 | 13 | Residencial | 9 X 15 | 135 | 1 | 1 | 9 | 9 | 15 | 15 | 9 M road | Site No 8 | Empty | Site No 12 |
| 14 | 14 | Residencial | ODD | 199 | 1 | 1 | 15.04 | 15 | 13.74 | 12.74 | Sy No 135/3 | Site No 15 | 9 M road | Empty |
| 15 | 15 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 14 | Site No 16 | 9 M road | Empty |
| 16 | 16 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 15 | Site No 17 | 9 M road | Empty |
| 17 | 17 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 16 | Site No 18 | 9 M road | Empty |
| 18 | 18 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 17 | Site No 19 | 9 M road | Sy No 135/5 |
| 19 | 19 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 18 | Site No 20 | 9 M road | Sy No 135/5 |
| 20 | 20 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 19 | Site No 21 | 9 M road | Sy No 135/5 |
| 21 | 21 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 20 | Site No 22 | 9 M road | Sy No 135/5 |
| 22 | 22 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 21 | Site No 23 | 9 M road | Empty |
| 23 | 23 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 22 | Site No 24 | 9 M road | Empty |
| 24 | 24 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 23 | Site No 25 | 9 M road | Empty |
| 25 | 25 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 24 | Site No 26 | 9 M road | Empty |
| 26 | 26 | Residencial | 9 X 15 | 135 | 1 | 1 | 15 | 15 | 9 | 9 | Site No 25 | Site No 27 | 9 M road | Empty |
| 27 | 27 | Residencial | ODD | 228 | 1 | 1 | 15 | 15.45 | 17.05 | 13.3 | Site No 26 | Site No 28 | 9 M road | Empty |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-04-2023 | 30-06-2023 |
| 2 | Formation Of Road, Footpath | Yes | 01-07-2023 | 30-10-2024 |
| 3 | Construction Of Water Supply Infrastucture | Yes | 01-07-2023 | 30-10-2024 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-07-2023 | 30-10-2024 |
| 5 | Power Supply Work(Transformer & Substation) | Yes | 01-07-2023 | 30-10-2024 |
| 6 | Construction Of Storm Water Drainage | Yes | 01-07-2023 | 30-10-2024 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | Yes | 01-07-2023 | 30-10-2024 |
| 9 | Street Lighting | No | ||
| 10 | Sewage Treatment Plant (STP) | Yes | 01-07-2023 | 30-10-2024 |
| 11 | Other Miscellaneous Work | Yes | 30-10-2024 | 31-12-2024 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Piped Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning | No |
| Total number of Plots | 27 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 438 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 809 |
| Area of Road/Transportation(in Sq.m) | 2395 |
| Project Start Date | 01-04-2023 |
| Project End Date | 31-12-2024 |
| If any extension of time has been granted | NO |
| Cost of land | 1946833 |
| Cost of construction | 6350000 |
| Total cost | 8296833 |
| Total amount collected From buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 8612348 |
| Total No of sites of Project | 27 |
| Total No of sites sold | 0 |
| Total No of sites unsold | 27 |
| Whether there is any changes in inventory details | NO |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |