MOHAMMADHANIF SHABASKHAN
NEAR BHAGYANAGAR BHADAVANE,GOGAK, R BHAGYANAGAR BHADAVANE,GOGAK
Approved
22nd Oct 2018
Completed
30th Mar 2019
Registration No.
PRM/KA/RERA/1249/365/PR/181022/002092
Acknowledgement No.
ACK/KA/RERA/1249/365/PR/180704/002427
Project Type
Plotted Development
Approving Authority
Belagavi Urban Development Authority
District
Belagavi
Taluka
Gokak
State
Karnataka
| Project Name | BHAGYANAGAR BHADAVANE |
| Project Description | RESIDENTIAL SITE |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 09-04-2018 |
| Proposed Project Completion Date | 30-03-2019 |
| Total Area Of Land (Sq Mtr) | 9004 |
| Total Coverd Area (Sq Mtr) | 9004 |
| Total Open Area (Sq Mtr) | 1022 |
| Estimated Cost of Construction (INR) | 4150000 |
| Cost of Land (INR) | 2450000 |
| Total Project Cost (INR) | 6600000 |
| Project Address | NEAR BHAGYANAGAR BHADAVANE,GOGAK, R BHAGYANAGAR BHADAVANE,GOGAK |
| District | Belagavi |
| Taluk | Gokak |
| Approving Authority | Belagavi Urban Development Authority |
| No of Garage for Sale | 58 |
| Area of Garage for Sale (Sq Mtr) | 9004 |
| No of Parking for Sale | 1022 |
| Area of Parking for Sale (Sq Mtr) | 1022 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| RESIDENTIAL SITES | Self Development |
| Bank Name | Canara Bank |
| Branch | GOKAK |
| ifscCode | CNRB0002763 |
| Account No.(70% Account) | 2763101004106 |
| State | Karnataka |
| Name | MOHAMMADHANIF D SHABASHKHAN |
| Address | R BHAGYANAGAR BHADAVANE,GOGAK,R BHAGYANAGAR BHADAVANE,GOGAK |
| Pin Code | 591307 |
| Year Of Establishment | 2018 |
| Number Of Project Completed | 0 |
| Firm Type | Individual |
| Name | MOHAMMADHANIF SHABASKHAN |
| Father's Name | DASTAGIRSAB |
| PAN Number | BKBPS5179J |
| Address | MALDAR GALLI,GURUVAR PET,GOKAKA |
| State/UT | Karnataka |
| PIN Code | 591307 |
| Project Name | RESIDENTIAL LAY OUT |
| Project Description | Residential site |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 01-07-2019 |
| District | Belagavi |
| Pin Code | 591307 |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | OPAN SPACE | 182.29 | 182.29 | NA | NA | 12.15 | 12.15 | 25 | 25 | 168/1+2A | 168/16 | ROAD | OPEN SPACE |
| 2 | 2 | RASIDENTAL | 102 | 102 | SOUTH | Completed | 10.4 | 10 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 3 | ROAD |
| 3 | 3 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 4 | PAOT NO 2 |
| 4 | 4 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 5 | PLOT NO 3 |
| 5 | 5 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 6 | PLOT NO 4 |
| 6 | 6 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 7 | PLOT NO 5 |
| 7 | 7 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 8 | PLOT NO 6 |
| 8 | 8 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 9 | PLOT NO 7 |
| 9 | 9 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 10 | PLOT NO 8 |
| 10 | 10 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 11 | PLOT NO 9 |
| 11 | 11 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 12 | PLOT NO 10 |
| 12 | 12 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 13 | PLOT NO 11 |
| 13 | 13 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 14 | PLOT NO 12 |
| 14 | 14 | RASIDENTAL | 60 | 60 | SOUTH | Completed | 6 | 6 | 9 | 9 | 168/1+2A | ROAD | PLOT NO 15 | PLOT NO 13 |
| 15 | 15 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | ROAD | PLOT NO 14 |
| 16 | 16 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 17 | ROAD |
| 17 | 17 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 18 | PLOT NO 16 |
| 18 | 18 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 19 | PLOT NO 17 |
| 19 | 19 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 20 | PLOT NO 18 |
| 20 | 20 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 21 | PLOT NO 19 |
| 21 | 21 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 22 | PLOT NO 20 |
| 22 | 22 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 23 | PLOT NO 21 |
| 23 | 23 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 24 | PLOT NO 22 |
| 24 | 24 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | ROAD | PLOT NO 23 |
| 25 | 25 | RASIDENTAL | 124 | 124 | SOUTH | Completed | 12.34 | 12.34 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 26 | ROAD |
| 26 | 26 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 27 | PLOT NO 25 |
| 27 | 27 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 28 | PLOT NO 26 |
| 28 | 28 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 29 | PLOT NO 27 |
| 29 | 29 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | PLOT NO 30 | PLOT NO 28 |
| 30 | 30 | RASIDENTAL | 90 | 90 | SOUTH | Completed | 9 | 9 | 10 | 10 | 168/1+2A | ROAD | ROAD | PLOT NO 29 |
| 31 | 31 | OPAN SPACE | 337.5 | 337.5 | SOUTH | NA | 34.8 | 32.7 | 10 | 10 | 168/1+2A | ROAD | R S NO | ROAD |
| 32 | 32 | OPAN SPACE | 320 | 320 | NORTH | Na | 34 | 30 | 11 | 11 | ROAD | 168/16 | R S NO | ROAD |
| 33 | 33 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | ROAD | PLOT NO 34 |
| 34 | 34 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 34 | PLOT NO 35 |
| 35 | 35 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 35 | PLOT NO 36 |
| 36 | 36 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 36 | PLOT NO 37 |
| 37 | 37 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 37 | PLOT NO 38 |
| 38 | 38 | RASIDENTAL | 99 | 99 | NORTH | Completed | 12.34 | 12.34 | 11 | 11 | ROAD | 168/16 | PLOT NO 37 | ROAD |
| 39 | 39 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | ROAD | PLOT NO 40 |
| 40 | 40 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 39 | PLOT NO 41 |
| 41 | 41 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 40 | PLOT NO 42 |
| 42 | 42 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 41 | PLOT NO 43 |
| 43 | 43 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 42 | PLOT NO 44 |
| 44 | 44 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 43 | PLOT NO 45 |
| 45 | 45 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 44 | PLOT NO 46 |
| 46 | 46 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 45 | PLOT NO 47 |
| 47 | 47 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | PLOT NO 46 | ROAD |
| 48 | 48 | RASIDENTAL | 99 | 99 | NORTH | Completed | 9 | 9 | 11 | 11 | ROAD | 168/16 | ROAD | PLOT NO 49 |
| 49 | 49 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 48 | PLOT NO 50 |
| 50 | 50 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 49 | PLOT NO 51 |
| 51 | 51 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 50 | PLOT NO 52 |
| 52 | 52 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 51 | PLOT NO 53 |
| 53 | 53 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 52 | PLOT NO 54 |
| 54 | 54 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 53 | PLOT NO 55 |
| 55 | 55 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 54 | PLOT NO 56 |
| 56 | 56 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 55 | PLOT NO 57 |
| 57 | 57 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 56 | PLOT NO 58 |
| 58 | 58 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 57 | PLOT NO 59 |
| 59 | 59 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 58 | PLOT NO 60 |
| 60 | 60 | RASIDENTAL | 66 | 66 | NORTH | Completed | 6 | 6 | 11 | 11 | ROAD | 168/16 | PLOT NO 59 | PLOT NO 61 |
| 61 | 61 | RASIDENTAL | 110 | 110 | NORTH | Completed | 10 | 10 | 11 | 11 | ROAD | 168/16 | PLOT NO 60 | ROAD |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-04-2018 | 30-03-2019 |
| 2 | Formation Of Road, Footpath | Yes | 01-04-2018 | 30-03-2019 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 01-04-2018 | 30-03-2019 |
| 4 | Construction Of Sewage System Infrastucture | No | ||
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 01-04-2018 | 30-03-2019 |
| 6 | Construction Of Storm Water Drainage | No | ||
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | No | ||
| 9 | Street Lighting | Yes | 01-04-2018 | 30-03-2019 |
| 10 | Other Miscellaneous Work | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | No |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | No |
| 14 | Air conditioning and incarnation | No |
| Total number of Plots | 61 |
| No. of Public and Semi Pubic Sites | 3 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 1021 |
| No. of Parks and Open Spaces | 0 |
| Area of Parks and Open Spaces(in Sq.m) | 0 |
| Area of Road/Transportation(in Sq.m) | 3030 |
| Project Start Date | 09-04-2018 |
| Project End Date | 30-03-2019 |
| If any extension of time has been granted | NO |
| Cost of land | 2450000 |
| Cost of construction | 4150000 |
| Total cost | 6600000 |
| Total amount collected From buyers | 16033000 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 7226379 |
| Total No of sites of Project | 61 |
| Total No of sites sold | 53 |
| Total No of sites unsold | 8 |
| Whether there is any changes in inventory details | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate