Builtech Developers
CTS No.8471, Plot No. 691, Sector No.5, MM Extention, Shree Nagar
Approved
15th Oct 2019
Completed
22nd Feb 2022
Registration No.
PRM/KA/RERA/1249/447/PR/191015/002917
Acknowledgement No.
ACK/KA/RERA/1249/447/PR/190813/003491
Project Type
Residential/Group Housing
Approving Authority
Commissioner, City Corporation, Belagavi
District
Belagavi
Taluka
Belagavi
State
Karnataka
| Project Name | BUILTECH's RAMA RESIDNECY |
| Project Description | Residential Apartment having G+4 storey building with basement car parking. Total no of 2 BHK Flats are 14. |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-09-2019 |
| Proposed Project Completion Date | 22-02-2022 |
| Total Area Of Land (Sq Mtr) | 371 |
| Total Coverd Area (Sq Mtr) | 1058 |
| Total Open Area (Sq Mtr) | 144 |
| Estimated Cost of Construction (INR) | 12700000 |
| Cost of Land (INR) | 6800000 |
| Total Project Cost (INR) | 19500000 |
| Project Address | CTS No.8471, Plot No. 691, Sector No.5, MM Extention, Shree Nagar |
| District | Belagavi |
| Taluk | Belagavi |
| Approving Authority | Commissioner, City Corporation, Belagavi |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 2 BHK Flats |
| No of Inventory | 14 |
| Carpet Area (Sq Mtr) | 830SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1058SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 44SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | Main Branch |
| ifscCode | HDFC0000253 |
| Account No.(70% Account) | 50200042634748 |
| State | Karnataka |
| Name | SAGAR HUDDAR |
| Address | Near Vinayak Housing Society,Shahu Nagar |
| Pin Code | 590010 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 20 |
| Reg. Of COA No. | CA/2009/46077 |
| Local Authority Licence Number | 100 |
| Promoter Type | Other |
| Name | Veeresh Shattennavar |
| PAN Number | BIOPS6105B |
| Address | No.76,APMC Road , Sangameshwara Nagar |
| District | Belagavi |
| State/UT | Karnataka |
| PIN Code | 590016 |
| Company Registration No. | 29BIOPS6105B2Z4 |
| Type of Inventory | 2 BHK Flats |
| No of Inventory | 14 |
| Carpet Area (Sq Mtr) | 830 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1058 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 44 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-10-2019 | 21-10-2019 |
| 2 | Foundation footing work | Yes | 22-10-2019 | 30-10-2019 |
| 3 | Retaining wall (All types) | Yes | 22-10-2019 | 31-10-2019 |
| 4 | Plinth level Beam | Yes | 01-11-2019 | 04-11-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 05-11-2019 | 06-11-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 2.24 |
| Number of Towers | 1 |
| 0 | 2 |
| 1 | 3 |
| 2 | 3 |
| 3 | 3 |
| 4 | 3 |
| 5 | 0 |
| Total No of Units | 14 |
| Project Start Date | 01-09-2019 |
| Project End Date | 22-02-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 6800000 |
| Cost of construction | 12700000 |
| Total project cost | 19500000 |
| Total amount collected from buyers | 21493900 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 18163076 |
| Balance amount with the promoter | 3330821 |
| Total number of Flats/Apartments of the Project | 14 |
| Total number of Flats/Apartments sold | 14 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |