Jairaj Constructions
CTS NO.780 defence colony hindalga belgaum, CTS NO.780 defence colony hindalga belgaum
Approved
11th Aug 2020
Completed
30th Sept 2023
Registration No.
PRM/KA/RERA/1249/447/PR/200811/003514
Acknowledgement No.
ACK/KA/RERA/1249/447/PR/200305/003944
Project Type
Residential/Group Housing
Approving Authority
Commissioner, City Corporation, Belagavi
District
Belagavi
Taluka
Belagavi
State
Karnataka
| Project Name | Jairaj Enclave |
| Project Description | B+G+4+PENTHOUSE |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 10-02-2020 |
| Proposed Project Completion Date | 30-09-2023 |
| Total Area Of Land (Sq Mtr) | 838 |
| Total Coverd Area (Sq Mtr) | 508 |
| Total Open Area (Sq Mtr) | 330 |
| Estimated Cost of Construction (INR) | 45600000 |
| Cost of Land (INR) | 13577055 |
| Total Project Cost (INR) | 60256000 |
| Project Address | CTS NO.780 defence colony hindalga belgaum, CTS NO.780 defence colony hindalga belgaum |
| District | Belagavi |
| Taluk | Belagavi |
| Approving Authority | Commissioner, City Corporation, Belagavi |
| No of Garage for Sale | 19 |
| Area of Garage for Sale (Sq Mtr) | 452 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | Union Bank of India |
| Branch | samadevi galli belgaum |
| ifscCode | UBIN0547158 |
| Account No.(70% Account) | 471501010043519 |
| State | Karnataka |
| Name | Sagar V. Huddar |
| Address | Vinayak housing society shahunagr Belgaum,Vinayak housing society shahunagr Belgaum |
| Pin Code | 590001 |
| Year Of Establishment | 2004 |
| Number of Project Completed | 1500 |
| Reg. Of COA No. | CA/2006/37541 |
| Local Authority Licence Number | BGM/BL/10242/18-19 |
| Promoter Type | Partnership Firm |
| Name | Yuvaraj K. Hulji |
| PAN Number | AAOFJ1431C |
| Address | 3rd cross ,laxmi nagar kakati, Blgaum.3rd cross ,laxmi nagar kakati, Blgaum |
| District | Belagavi |
| State/UT | Karnataka |
| PIN Code | 590001 |
| Company Registration No. | BELF1 |
| Type | Others |
| Pin Code | 591113 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-02-2020 | 20-03-2020 |
| 2 | Foundation footing work | Yes | 05-05-2020 | 10-06-2020 |
| 3 | Retaining wall (All types) | Yes | 04-05-2020 | 15-06-2020 |
| 4 | Plinth level Beam | Yes | 05-05-2020 | 12-06-2020 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 13-06-2020 | 20-06-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 2.67 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 8 |
| 2 | 8 |
| 3 | 8 |
| 4 | 8 |
| 5 | 6 |
| Total No of Units | 38 |
| Project Start Date | 10-02-2020 |
| Project End Date | 30-09-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 13577055 |
| Cost of construction | 45600000 |
| Total project cost | 60256000 |
| Total amount collected from buyers | 59632000 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 61639133 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 38 |
| Total number of Flats/Apartments sold | 23 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |