NAVCHAITANYA DEVELOPERS
Belagavi
Approved
1st Jul 2022
Completed
10th Jan 2025
Registration No.
PRM/KA/RERA/1249/447/PR/010722/005034
Acknowledgement No.
ACK/KA/RERA/1249/447/PR/190422/005865
Project Type
Mixed Development
District
Belagavi
Taluka
Belagavi
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Partnership Firm |
| Promoter Name | NAVCHAITANYA DEVELOPERS |
| Main Objectives | BUILDING CONSTURCTION |
| Registration Number | BELF179201718 |
| PAN | AOMPN4949K |
| GSTIN | 29AAOFN5131D1Z9 |
| Promoter Address | P.NO.449/1, DATTA GALLI,M.VADGAON, BELAGAVI ,Belagavi ,Belagavi-590005 |
| District | Belagavi |
| Taluk | Belagavi |
| PIN Code | 590005 |
| Name of Authorized Signatory | SWAPNIL KALLAPPA NILAJKAR |
| Number of Partners | 6 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | BHANDARE RESIDENCY |
| Project Description | BHANDARE RESIDENCY, STILT PARKING + GF + FF + SF + TF + PENT HOUSES FOR RESIDENTIAL PURPOSE ONLY |
| Type of Project | Residential |
| Current Status | Completed |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | CTS.NO.450, CCB NO.558/A, DATTA GALLI, M.VADGAON |
| State/UT | Karnataka |
| Pin Code | 590005 |
| Present Address | CHANDGAD , KHANGAON POST , Belagavi , Karnataka - 590016 |
| Permanent Address | CHANDGAD, KHANGAON POST , Belagavi , Karnataka - 590016 |
| Official Address | P.NO.449/1, DATTA GALLI, M.VADGAON , Belagavi , Karnataka - 590005 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 |
| Type of Inventory | RESIDENTIAL FLATS+ PENT HOUSE 6 |
| No of Inventory | 34 |
| Carpet Area (Sq Mtr) | 1826 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 325 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-01-2022 | 20-02-2022 |
| 2 | Foundation footing work | Yes | 20-02-2022 | 22-03-2022 |
| 3 | Upto Plinth Level | Yes | 22-03-2022 | 10-04-2022 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-05-2023 | 01-06-2023 |
| 5 | Retaining wall (All types) | Yes | 22-02-2022 | 23-04-2022 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | Yes |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | No |
| 5 | Fire protection and fire safety requirements | No |
| 6 | Solid waste management and disposal | Yes |
| 7 | Emergency Evacuation services | No |
| FAR Sanctioned | 3.0 |
| Number of Towers | 1 |
| 0 | 6 |
| 1 | 6 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| 5 | 6 |
| Total No of Units | 36 |
| Project Start Date | 10-01-2022 |
| Project End Date | 10-01-2025 |
| If any extension of time has been granted | NO |
| Cost of land | 32500000 |
| Cost of construction | 69450168 |
| Total project cost | 101950168 |
| Total amount collected from buyers | 38814535 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 109828531 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 33 |
| Total number of Flats/Apartments sold | 18 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 24-05-2024 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate