BOLLINENI NESTOR
BOLLINENI DEVELOPERS LTD
sy no 47/1 48/1, YELLUPURA VILLAGE
Approved
26th Oct 2017
Completed
31st Jan 2025
Registration No.
PRM/KA/RERA/1250/301/PR/171026/000612
Acknowledgement No.
PR/KN/170731/000612
Project Type
Residential/Group Housing
Approving Authority
BIAPPA - Bangalore Airport Area Planning Authority
District
Bengaluru Rural
Taluka
Doddaballapura
State
Karnataka
Project Details
| Project Name | BOLLINENI NESTOR |
| Project Description | HIGH RISE APPARTMENTS |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 16-03-2015 |
| Proposed Project Completion Date | 30-09-2022 |
| Further Extension Date | 31-01-2025 |
| Total Area Of Land (Sq Mtr) | 8650 |
| Total Coverd Area (Sq Mtr) | 1534 |
| Total Open Area (Sq Mtr) | 1133 |
| Estimated Cost of Construction (INR) | 410000000 |
| Cost of Land (INR) | 125100000 |
| Total Project Cost (INR) | 535100000 |
| Project Address | sy no 47/1 48/1, YELLUPURA VILLAGE |
| District | Bengaluru Urban |
| Taluk | Doddaballapura |
| Approving Authority | BIAPPA - Bangalore Airport Area Planning Authority |
| No of Garage for Sale | 1 |
| Area of Garage for Sale (Sq Mtr) | 2702 |
| No of Parking for Sale | 81 |
| Area of Parking for Sale (Sq Mtr) | 1114 |
| Extent of development carried till date | 20 % |
| Extent of development pending | 20 % |
| Total amount of money collected from allottee | 0 |
| Total amount of money used for development of project | 60000000 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Axis Bank |
| Branch | SADASHIVANAGAR |
| ifscCode | UTIB0001887 |
| Account No.(70% Account) | 913020035609244 |
| State | Karnataka |
| Name | BSCPL INFRASTRUCTURE LTD |
| Address | sadashivanagar,BANGALORE |
| Pin Code | 560003 |
| Year Of Establishment | 1998 |
| Number Of Project Completed | 1 |
Promoter Details
| Promoter Type | Company |
| Name | BOLLINENI KRISHNAIAH |
| PAN Number | AAA******* |
| Address | H NO 8-2-546/2 ROAD NO -07 , BANJARA HIILS |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560003 |
| Company Registration No. | U65990AP1996PLC024371 |
Extension Details
| Extension Applied On | 31-03-2022 |
| Extension Approved On | 28-10-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1250/301/PR/221028/000612 |
| Proposed Project End Date at the time of registration | 30-09-2021 |
| Project End Date provided under Section 6 | 30-09-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | others |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 12-12-2015 | 15-06-2016 |
| 2 | Foundation footing work | Yes | 01-03-2016 | 01-06-2016 |
| 3 | Retaining wall (All types) | Yes | 01-01-2016 | 30-03-2016 |
| 4 | Plinth level Beam | Yes | 30-03-2016 | 30-05-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-06-2016 | 01-08-2016 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| WebSite Link 1 | www.bscplre.com |
| FAR Sanctioned | 1.46 |
| Number of Towers | 1 |
| 0 | 14 |
| 1 | 18 |
| 2 | 18 |
| 3 | 18 |
| 4 | 18 |
| 5 | 18 |
| 6 | 18 |
| 7 | 18 |
| Total No of Units | 140 |
Completion Details
| Project Start Date | 16-03-2015 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2021 |
| Extended End Date | 30-09-2022 |
| Cost of land | 125100000 |
| Cost of construction | 410000000 |
| Total project cost | 535100000 |
| Total amount collected from buyers | 142101514 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 273320828 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 140 |
| Total number of Flats/Apartments sold | 140 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 28-10-2024 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in