M1 PROPERTIES
Sy no 26,27,29 , Shankinipura Village, Kasaba Hobli, Hoskote
Approved
8th Dec 2017
Completed
28th Sept 2021
Registration No.
PRM/KA/RERA/1250/304/PR/171208/001069
Acknowledgement No.
PR/KN/170803/001069
Project Type
Residential/Group Housing
Approving Authority
BMRDA - Bangalore Metropolitan Region Development Authority
District
Bengaluru Rural
Taluka
Hosakote
State
Karnataka
| Project Name | M1 PROPERTIES TERRA ALEGRIA |
| Project Description | Group housing villa project in Shankinipura , Hoskote |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 28-10-2016 |
| Proposed Project Completion Date | 28-09-2021 |
| Total Area Of Land (Sq Mtr) | 30705 |
| Total Coverd Area (Sq Mtr) | 8698 |
| Total Open Area (Sq Mtr) | 10100 |
| Estimated Cost of Construction (INR) | 380000000 |
| Cost of Land (INR) | 95000000 |
| Total Project Cost (INR) | 605300000 |
| Project Address | Sy no 26,27,29 , Shankinipura Village, Kasaba Hobli, Hoskote |
| District | Bengaluru Urban |
| Taluk | Hosakote |
| Approving Authority | BMRDA - Bangalore Metropolitan Region Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 2 |
| Area of Parking for Sale (Sq Mtr) | 1533 |
| Type of Inventory | VILLAS |
| No of Inventory | 103 |
| Carpet Area (Sq Mtr) | 17733SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 14489SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 1160SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Canara Bank |
| Branch | HSR LAYOUT, BANGALORE |
| ifscCode | CNRB0002673 |
| Account No.(70% Account) | 2673201003949 |
| State | Karnataka |
| Name | C S CONSTRUCTIONS |
| Address | No 1 , SNS Nilaya ,Vidyaranyapura |
| Pin Code | 560057 |
| Year Of Establishment | 2015 |
| Number of Project Completed | 475 |
| Reg. Of COA No. | CA/86/10254 |
| Local Authority Licence Number | 80/STRLENGINEER/TP10/GHMC |
| Number Of Project Completed | 3 |
| Promoter Type | Other |
| Name | SIVA RAMA KRISHNA PRASAD MUSUNURI |
| PAN Number | AHFPM3111J |
| Address | C 902 , Mantri Espana , Bellandur , Kariyammana Agrahara |
| District | Bengaluru Rural |
| State/UT | Karnataka |
| PIN Code | 562114 |
| Company Registration No. | 22174S4722013 |
| Type of Inventory | VILLAS |
| No of Inventory | 103 |
| Carpet Area (Sq Mtr) | 17733 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 14489 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 1160 Sq Mtr |
| Extension Applied On | 30-12-2019 |
| Extension Approved On | 26-05-2020 |
| Extension Registration Number | EX/PRM/KA/RERA/1250/304/PR/200526/001069 |
| Proposed Project End Date at the time of registration | 28-12-2019 |
| Project End Date provided under Section 6 | 28-12-2020 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | HPA COMMENCEMENT CERTIFICATE |
| 1 | Shortage of Labour |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-03-2018 | 27-12-2018 |
| 2 | Foundation footing work | No | ||
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.m1homes.com |
| FAR Sanctioned | 1.5 |
| Number of Towers | 103 |
| 0 | 1 |
| 1 | 0 |
| 2 | 0 |
| Total No of Units | 103 |
| Project Start Date | 28-10-2016 |
| Project End Date | 28-09-2021 |
| If any extension of time has been granted | YES |
| Extended From Date | 28-12-2019 |
| Extended End Date | 28-12-2020 |
| Cost of land | 95000000 |
| Cost of construction | 380000000 |
| Total project cost | 605300000 |
| Total amount collected from buyers | 654329129 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 668875400 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 103 |
| Total number of Flats/Apartments sold | 88 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 21-03-2020 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |