SHRIVISION TOWERS PRIVATE LIMITED
Sy.No- 73/1,73/2A,74(P) & 81,, Bammenahalli Village,Bidarahalli Hobli,Bangalore East Taluk
Approved
14th Oct 2017
Completed
30th Dec 2023
Registration No.
PRM/KA/RERA/1250/304/PR/171014/001220
Acknowledgement No.
PR/KN/170810/001220
Project Type
Residential/Group Housing
Approving Authority
BMRDA - Bangalore Metropolitan Region Development Authority
District
Bengaluru Rural
Taluka
Hosakote
State
Karnataka
| Project Name | SHRIRAM GREEN FIELD PHASE 2 |
| Project Description | Residential Apartments with 9 Blocks, PH-2: Block-G,H&J- 2B+G+19 Floors/710 Units, PH-1 registered separately, Block-A to F- 2B+G+19 Floors/935 Units. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 03-10-2017 |
| Proposed Project Completion Date | 30-12-2022 |
| Further Extension Date | 30-12-2023 |
| Total Area Of Land (Sq Mtr) | 23344 |
| Total Coverd Area (Sq Mtr) | 8243 |
| Total Open Area (Sq Mtr) | 14297 |
| Estimated Cost of Construction (INR) | 2435280635 |
| Cost of Land (INR) | 175034965 |
| Total Project Cost (INR) | 2610315600 |
| Project Address | Sy.No- 73/1,73/2A,74(P) & 81,, Bammenahalli Village,Bidarahalli Hobli,Bangalore East Taluk |
| District | Bengaluru Urban |
| Taluk | Hosakote |
| Approving Authority | BMRDA - Bangalore Metropolitan Region Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 4 % |
| Extent of development pending | 4 % |
| Total amount of money collected from allottee | 22983298 |
| Total amount of money used for development of project | 358339401 |
| Total amount of balance maney lying with promoter | -335356103 |
| Is Any Subsequent Modification in Plan | Yes |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | APARTMENTS |
| No of Inventory | 710 |
| Carpet Area (Sq Mtr) | 49989SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 2537SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| MUNICIPAL WATER CONNECTION AND POWER CONNECTION | Local Authority |
| Bank Name | RATNAKAR BANK |
| Branch | PRESTIGE TOWERS |
| ifscCode | RATN0000156 |
| Account No.(70% Account) | 409000948740 |
| State | Karnataka |
| Name | ICONICA CONSTRUCTIONS |
| Address | #845,5th Cross.10th Main,,Indiranagar 2nd Stage,Bangalore |
| Pin Code | 560038 |
| Year Of Establishment | 2015 |
| Number of Project Completed | 66 |
| Reg. Of COA No. | CA/2002/29793 |
| Local Authority Licence Number | BCC/BL-3.6/STRL:E:67:09-10 |
| Number Of Project Completed | 3 |
| Promoter Type | Company |
| Name | MALLIKARJUN.M |
| PAN Number | AAMCS2161D |
| Address | Sy.No- 80/1, 2, 3, 4, 84/6 & 7, 85/2, 87/2, 89/1 & 2, 121/1, 2, 3, Veerasandra Village & Hebbagodi Village, Anekal Taluk, Attibele, Bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560080 |
| Company Registration No. | U70102KA2008PTC047227 |
| Type | Others |
| Pin Code | 562107 |
| Project Name | SHRIRAM SUMMIT |
| Project Description | High rise Residential Apartments with 3 Blocks 2B+G+13 Floors ,Block-01 10Towers,Block-02 7Towers,Block-03 4Towers,Total Towers -21.Block- 1= 520 Flats,Block-02 = 392 Flats,Block-03 = 216Flats.Total Flats =1128 |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 10-08-2017 |
| Type of Inventory | APARTMENTS |
| No of Inventory | 710 |
| Carpet Area (Sq Mtr) | 49989 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 2537 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Extension Applied On | 27-11-2021 |
| Extension Approved On | 07-05-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1250/304/PR/220507/001220 |
| Proposed Project End Date at the time of registration | 30-12-2021 |
| Project End Date provided under Section 6 | 30-12-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Note: By mistakely we have uploaded architect certificate in the Reason for delay docs |
| 1 | Force Majeure |
| 2 | Shortage of Building Materials, Concrete, Jalli etc |
| Document Name_1 | |
| Document Name_2 | |
| Document Name_3 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 20-05-2016 | 22-06-2017 |
| 2 | Foundation footing work | Yes | 23-06-2017 | 31-01-2019 |
| 3 | Retaining wall (All types) | Yes | 16-05-2018 | 02-03-2019 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 28-10-2018 | 04-05-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | https://www.shriramproperties.com/greenfield/ |
| FAR Sanctioned | 168437.0 |
| Number of Towers | 3 |
| 0 | 0 |
| 1 | 11 |
| 2 | 12 |
| 3 | 12 |
| 4 | 12 |
| 5 | 12 |
| 6 | 12 |
| 7 | 12 |
| 8 | 12 |
| 9 | 12 |
| 10 | 12 |
| 11 | 12 |
| 12 | 12 |
| 13 | 12 |
| 14 | 12 |
| 15 | 12 |
| 16 | 12 |
| 17 | 12 |
| 18 | 10 |
| Total No of Units | 653 |
| Project Start Date | 03-10-2017 |
| Project End Date | 30-12-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-12-2021 |
| Extended End Date | 30-12-2022 |
| Cost of land | 175034965 |
| Cost of construction | 2435280635 |
| Total project cost | 2610315600 |
| Total amount collected from buyers | 1958870305 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 2610315600 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 653 |
| Total number of Flats/Apartments sold | 644 |
| Total number of Flats/Apartments Unsold | 9 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 30-12-2023 |
| Appeals / FNH | NO APPEALS / FNH |