SOWPARNIKA PROJECTS AND INFRASTRUCTURE PVT. LTD.
Sy Nos. 185, 186/1, 186/2, Naduvatti Village,, Kasaba Hobli, Hosakote Taluk,
Approved
24th Oct 2017
Completed
15th Dec 2023
Registration No.
PRM/KA/RERA/1250/304/PR/171024/000764
Acknowledgement No.
PR/KN/170731/000764
Project Type
Residential/Group Housing
Approving Authority
BMRDA - Bangalore Metropolitan Region Development Authority
District
Bengaluru Rural
Taluka
Hosakote
State
Karnataka
| Project Name | SOWPARNIKA COLUMNS |
| Project Description | The aesthetic architecture houses with 216 spacious 1, 2 & 3 BHK apartments in various dimensions and complements your lifestyle with luxury amenities and premium specifications |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 01-07-2017 |
| Proposed Project Completion Date | 30-09-2022 |
| Further Extension Date | 15-12-2023 |
| Total Area Of Land (Sq Mtr) | 12687 |
| Total Coverd Area (Sq Mtr) | 2643 |
| Total Open Area (Sq Mtr) | 10044 |
| Estimated Cost of Construction (INR) | 524309500 |
| Cost of Land (INR) | 48020429 |
| Total Project Cost (INR) | 920334714 |
| Project Address | Sy Nos. 185, 186/1, 186/2, Naduvatti Village,, Kasaba Hobli, Hosakote Taluk, |
| District | Bengaluru Urban |
| Taluk | Hosakote |
| Approving Authority | BMRDA - Bangalore Metropolitan Region Development Authority |
| No of Garage for Sale | 360 |
| Area of Garage for Sale (Sq Mtr) | 10694 |
| No of Parking for Sale | 65 |
| Area of Parking for Sale (Sq Mtr) | 838 |
| Extent of development carried till date | 4 % |
| Extent of development pending | 4 % |
| Total amount of money collected from allottee | 1931873 |
| Total amount of money used for development of project | 26900843 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | Residential |
| No of Inventory | 390 |
| Carpet Area (Sq Mtr) | 22309SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 2045SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Bank Name | HDFC |
| Branch | OLD AIRPORT ROAD |
| ifscCode | HDFC0000075 |
| Account No.(70% Account) | 00750350000222 |
| State | Karnataka |
| Promoter Type | Company |
| Name | MOHAMAD ZEAULLA |
| PAN Number | AAKCS9641L |
| Address | NO. 750, 'C' BLOCK, 1ST MAIN ROAD,.AECS LAYOUT, KUNDALAHALLI, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560037 |
| Company Registration No. | U45201KA2007PTC043166 |
| Type | Others |
| Pin Code | 560037 |
| Modification Applied On | 09-09-2020 |
| Modification Approved On | 19-02-2021 |
| Type of Inventory | Residential |
| No of Inventory | 390 |
| Carpet Area (Sq Mtr) | 22309 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 2045 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Initially plans were approved for 2 Basements + Ground + 8 Floors with 216 units by Hoskote Planning Authority (HPA), Hoskote. Later the subject project land has come under the jurisdiction of Satellite Town Ring Road (STRR) Authority and we were hoping of getting higher FSI under STRR Authority. Subsequently we have applied for and obtained revised sanction from STRR Authority for higher FSI with 2 Basement + Ground + 14 Floors with 390 units which we got in the month of Nov 2018. Also, as per the guidelines of HPA, under group housing, we were supposed to make a provision for civic amenities of 5% only which was considered while getting approval from HPA. Once the jurisdictional authority changed to STRR, as per their bylaws, we were forced to make additional reservation for STRR buffer of another 5%. Hence we had to rework on our entire drawings to accommodate this additional reservation. Thus the plans of Sowparnika Columns are modified from 2B+G+8 Floors with 216 units 2B+G+14 Floors with 390 units. |
| Modified plan applied date | 13/11/2018 |
| Modified plan approved date | 13/11/2018 |
| Extend of the work carried out till date of registered project ( % ) | 36.0 |
| Extend of the work pending of registered project ( % ) | 64.0 |
| Total amount collected in respect of registered project ( INR ) | 542593916 |
| Total amount spent for the project ( INR ) | 449765066 |
| Total balance amount lying with the promoter ( INR ) | 50000 |
| NOC | SEIAA |
| SlNo. |
| Extension Applied On | 05-04-2019 |
| Extension Approved On | 01-04-2021 |
| Extension Registration Number | EX/PRM/KA/RERA/1250/304/PR/210401/000764 |
| Proposed Project End Date at the time of registration | 31-12-2020 |
| Project End Date provided under Section 6 | 31-12-2021 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Clarification Undertaking letter |
| 1 | Applied for modification |
| Document Name_1 | |
| Document Name_2 | |
| Document Name_3 | |
| Document Name_4 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-10-2017 | 09-03-2018 |
| 2 | Foundation footing work | Yes | 09-12-2017 | 07-06-2018 |
| 3 | Retaining wall (All types) | Yes | 08-01-2018 | 21-08-2018 |
| 4 | Plinth level Beam | Yes | 20-09-2018 | 19-11-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 19-12-2018 | 17-02-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | https://www.sowparnika.com/ |
| Agent Registration No 1 | PRM/KA/RERA/1251/310/AG/170927/000121 |
| Agent Registration No 2 | AG001936 |
| Agent Registration No 3 | AG/KN/171025/001410 |
| Agent Registration No 4 | PRM/KA/RERA/1251/308/AG/180709/001022 |
| Agent Registration No 5 | PRM/KA/RERA/1251/310/AG/170824/000092 |
| Agent Registration No 6 | PRM/KA/RERA/1251/446/AG/171007/000774 |
| Agent Registration No 7 | PRM/KA/RERA/1250/305/AG/180606/000948 |
| Agent Registration No 8 | PRM/KA/RERA/1251/310/AG/180626/000997 |
| Agent Registration No 9 | PRM/KA/RERA/1251/446/AG/180612/000980 |
| Agent Registration No 10 | PRM/KA/RERA/1251/310/AG/171114/000400 |
| Agent Registration No 11 | PRM/KA/RERA/1251/310/AG/170823/000047 |
| FAR Sanctioned | 2.49 |
| Number of Towers | 1 |
| 0 | 26 |
| 1 | 26 |
| 2 | 26 |
| 3 | 26 |
| 4 | 26 |
| 5 | 26 |
| 6 | 26 |
| 7 | 26 |
| 8 | 26 |
| 9 | 26 |
| 10 | 26 |
| 11 | 26 |
| 12 | 26 |
| 13 | 26 |
| 14 | 26 |
| Total No of Units | 390 |
| Project Start Date | 01-07-2017 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 31-12-2020 |
| Extended End Date | 31-12-2021 |
| Cost of land | 48020429 |
| Cost of construction | 524309500 |
| Total project cost | 920334714 |
| Total amount collected from buyers | 1512281457 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 1512281457 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 390 |
| Total number of Flats/Apartments sold | 387 |
| Total number of Flats/Apartments Unsold | 3 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 13-04-2023 |
| Appeals / FNH | NO APPEALS / FNH |