BALDOTA BUILDERS AND DEVELOPERS
SY 89/4 RACHENAHALLI VILLAGE , K R PURAM HOBLI
Approved
23rd Jan 2020
Completed
11th Jan 2024
Registration No.
PRM/KA/RERA/1251/446/PR/200123/003223
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/191104/003660
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | BALDOTA SIGNATURE |
| Project Description | BBMP APPROVED, BASEMENT GROUND PLUS UPPER FOUR FLOORS , OC CC PROJECT, |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 11-09-2019 |
| Proposed Project Completion Date | 11-01-2024 |
| Total Area Of Land (Sq Mtr) | 6445 |
| Total Coverd Area (Sq Mtr) | 2950 |
| Total Open Area (Sq Mtr) | 3495 |
| Estimated Cost of Construction (INR) | 255000000 |
| Cost of Land (INR) | 137642500 |
| Total Project Cost (INR) | 392642500 |
| Project Address | SY 89/4 RACHENAHALLI VILLAGE , K R PURAM HOBLI |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 5 % |
| Extent of development pending | 95 % |
| Total amount of money collected from allottee | 0 |
| Total amount of money used for development of project | 15158760 |
| Total amount of balance maney lying with promoter | 2646640 |
| Reason For Delay | NO |
| No of Month Delay | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | gandhinagar |
| ifscCode | hdfc0004697 |
| Account No.(70% Account) | 50200036699142 |
| State | Karnataka |
| Name | SHRINIVASA RAO BOLIMUTA |
| Address | 101 1ST MAIN ,SESHADRIPURAM |
| Pin Code | 560020 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 125 |
| Reg. Of COA No. | BCC/BL-3.6/E-4205/2016-17 |
| Local Authority Licence Number | BCC/BL-3.6/SE-211/2016-17 |
| Promoter Type | Partnership Firm |
| Name | MUDITH CHAJJER |
| PAN Number | AAUFB4327K |
| Address | no 9 bikshu kripa , 4th cross .gandhinagar |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560009 |
| Company Registration No. | NOT APPLICABLE |
| Type | Others |
| Pin Code | 560009 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-08-2019 | 15-08-2019 |
| 2 | Foundation footing work | Yes | 16-08-2019 | 30-10-2019 |
| 3 | Retaining wall (All types) | Yes | 21-08-2019 | 18-09-2019 |
| 4 | Plinth level Beam | Yes | 01-11-2019 | 29-11-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-12-2019 | 15-12-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.baldotadevelopers.com |
| FAR Sanctioned | 2.25 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 17 |
| 2 | 17 |
| 3 | 17 |
| 4 | 17 |
| 5 | 17 |
| Total No of Units | 135 |
| Project Start Date | 11-09-2019 |
| Project End Date | 11-01-2024 |
| If any extension of time has been granted | NO |
| Cost of land | 137642500 |
| Cost of construction | 255000000 |
| Total project cost | 392642500 |
| Total amount collected from buyers | 781917438 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 675791987 |
| Balance amount with the promoter | 106125451 |
| Total number of Flats/Apartments of the Project | 135 |
| Total number of Flats/Apartments sold | 114 |
| Total number of Flats/Apartments Unsold | 21 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 29-12-2022 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |