Century Real Estate Holdings Private Limited
Century Ethos, Amruthahalli, Yelahanka Hobli, Bangalore North
Approved
14th Oct 2017
Completed
30th Sept 2022
Registration No.
PRM/KA/RERA/1251/309/PR/171014/000283
Acknowledgement No.
PR/KN/170729/000283
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
| Project Name | Century Ethos |
| Project Description | Residential Apartment comprising of 4 residential towers with garages and amenities. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 18-01-2016 |
| Proposed Project Completion Date | 30-09-2022 |
| Total Area Of Land (Sq Mtr) | 29574 |
| Total Coverd Area (Sq Mtr) | 5912 |
| Total Open Area (Sq Mtr) | 23662 |
| Estimated Cost of Construction (INR) | 4529800000 |
| Cost of Land (INR) | 3844669400 |
| Total Project Cost (INR) | 8374469400 |
| Project Address | Century Ethos, Amruthahalli, Yelahanka Hobli, Bangalore North |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 746 |
| Area of Garage for Sale (Sq Mtr) | 9325 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 26 % |
| Extent of development pending | 26 % |
| Total amount of money collected from allottee | 1364300000 |
| Total amount of money used for development of project | 1499400000 |
| Total amount of balance maney lying with promoter | 38000000 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Bank Name | HDFC |
| Branch | Richmond Road |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 05230350006578 |
| State | Karnataka |
| Promoter Type | Company |
| Name | Neelakantha Patil |
| PAN Number | AADCC0651M |
| Address | Hosahudya village, kasaba hobli, Bangalore rural district. |
| District | Bengaluru Rural |
| State/UT | Karnataka |
| PIN Code | 560052 |
| Company Registration No. | U70101KA2007PTC042078 |
| Type | Others |
| Pin Code | 562157 |
| Project Name | Century Eden |
| Project Description | Plotted development |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 29-07-2017 |
| Extension Applied On | 04-10-2021 |
| Extension Approved On | 21-11-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/309/PR/221121/000283 |
| Proposed Project End Date at the time of registration | 30-09-2021 |
| Project End Date provided under Section 6 | 30-09-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | Force Majeure |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 22-09-2014 | 15-02-2015 |
| 2 | Foundation footing work | Yes | 20-01-2015 | 18-07-2018 |
| 3 | Retaining wall (All types) | Yes | 30-03-2015 | 30-12-2017 |
| 4 | Plinth level Beam | Yes | 01-03-2015 | 15-05-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-02-2014 | 15-04-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.centuryrealestate.in/project/residential/century-indus |
| FAR Sanctioned | 3.204 |
| Number of Towers | 5 |
| 0 | 2 |
| 1 | 2 |
| 2 | 2 |
| 3 | 2 |
| 4 | 2 |
| 5 | 2 |
| 6 | 2 |
| 7 | 2 |
| 8 | 2 |
| 9 | 2 |
| 10 | 2 |
| 11 | 2 |
| 12 | 2 |
| 13 | 2 |
| 14 | 2 |
| 15 | 2 |
| 16 | 2 |
| 17 | 2 |
| 18 | 2 |
| 19 | 2 |
| 20 | 2 |
| 21 | 2 |
| Total No of Units | 373 |
| Appeals / FNH | NO APPEALS / FNH |