Vinayaka Builders and Developers
Sy 62, Pattangere village, Kengeri Hobli, Bangalore south taluk
Approved
5th Sept 2017
Completed
31st Dec 2019
Registration No.
PRM/KA/RERA/1251/310/PR/170905/000135
Acknowledgement No.
PR/KN/170728/000135
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Century Indus Phase 2 |
| Project Description | Residential Apartment with 2 towers comprising Block A and B. Block C and D were built in phase 1 OC received. Total Land Area is 23747 sq.mt. Total covered area for Phase 1 and 2 is 3202 sq.mt. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 30-10-2015 |
| Proposed Project Completion Date | 31-12-2019 |
| Total Area Of Land (Sq Mtr) | 23747 |
| Total Coverd Area (Sq Mtr) | 3202 |
| Total Open Area (Sq Mtr) | 20545 |
| Estimated Cost of Construction (INR) | 1008000000 |
| Cost of Land (INR) | 203650000 |
| Total Project Cost (INR) | 1211650000 |
| Project Address | Sy 62, Pattangere village, Kengeri Hobli, Bangalore south taluk |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 1 |
| Area of Garage for Sale (Sq Mtr) | 2257 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 40 % |
| Extent of development pending | 40 % |
| Total amount of money collected from allottee | 545300000 |
| Total amount of money used for development of project | 570900000 |
| Total amount of balance maney lying with promoter | 20600000 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Bank Name | HDFC |
| Branch | Richmond Road |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 5230350007432 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | Neelakantha Patil |
| PAN Number | AAEFV2229C |
| Address | Sy 62, Pattangere village, Kengeri Hobli, Bangalore south taluk - 560098 |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560052 |
| Company Registration No. | 581 |
| Type | Others |
| Pin Code | 560098 |
| Project Name | Century Indus - Phase 1 |
| Project Description | Residential Apartment consisting of 2 towers with an constructed area of 21362 sq.mt and a larger land extent of 6 acres for the entire phase 1 and phase 2 with amenities such as club house. Partial Occupancy Certificate already received with Ref JDTP(S)/ADTP/OC/31/15-16 on 21-01-16 for C and D Block(Phase 1). |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 28-07-2017 |
| Extension Applied On | 19-01-2019 |
| Extension Approved On | 15-03-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/220315/000135 |
| Proposed Project End Date at the time of registration | 31-12-2018 |
| Project End Date provided under Section 6 | 31-12-2019 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | affidavit or abiding in respect of compensation event under Section 18(1) of RERA Act |
| 1 | Shortage of Labour |
| Document Name_1 | |
| Document Name_2 | |
| Document Name_3 | |
| Document Name_4 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-02-2015 | 25-02-2015 |
| 2 | Foundation footing work | Yes | 02-03-2015 | 09-04-2015 |
| 3 | Retaining wall (All types) | Yes | 05-05-2015 | 05-06-2015 |
| 4 | Plinth level Beam | Yes | 02-04-2015 | 02-07-2015 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-03-2015 | 15-04-2015 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | www.centuryrealestate.in/project/residential/century-indus |
| FAR Sanctioned | 1.9934 |
| Number of Towers | 2 |
| 0 | 7 |
| 1 | 7 |
| 2 | 7 |
| 3 | 7 |
| 4 | 7 |
| 5 | 7 |
| 6 | 7 |
| 7 | 7 |
| 8 | 7 |
| 9 | 7 |
| 10 | 7 |
| 11 | 7 |
| 12 | 7 |
| 13 | 7 |
| Total No of Units | 196 |
| Name | Registered conveyance deed for an individual unit |
| Approval Date | 19-12-2019 |
| Appeals / FNH | NO APPEALS / FNH |