M/s.CHAITHANYA PROJECTS (P) LTD.,
Mandur Village, Bidarahalli Hobli, , Bangalore East Taluk
Approved
19th Jan 2018
Completed
21st Mar 2024
Registration No.
PRM/KA/RERA/1251/446/PR/180119/000936
Acknowledgement No.
PR/KN/170801/000936
Project Type
Residential/Group Housing
Approving Authority
Local Planing Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | Chaithanya SAMARTH |
| Project Description | Chaithanya Samarth is being conceived in a 33 acres 35 Guntas land featuring 163, three and four bedroom villas. Samarth is a perfect getaway where every detail is thought over meticulously. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 22-06-2017 |
| Proposed Project Completion Date | 21-03-2024 |
| Total Area Of Land (Sq Mtr) | 137086 |
| Total Coverd Area (Sq Mtr) | 38864 |
| Total Open Area (Sq Mtr) | 98221 |
| Estimated Cost of Construction (INR) | 3640000000 |
| Cost of Land (INR) | 1190000000 |
| Total Project Cost (INR) | 4830000000 |
| Project Address | Mandur Village, Bidarahalli Hobli, , Bangalore East Taluk |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 137 |
| Area of Parking for Sale (Sq Mtr) | 6855 |
| Extent of development carried till date | 4 % |
| Extent of development pending | 4 % |
| Total amount of money collected from allottee | 608100000 |
| Total amount of money used for development of project | 428900000 |
| Total amount of balance maney lying with promoter | 179200000 |
| Is Any Subsequent Modification in Plan | Yes |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | Type 1W |
| No of Inventory | 21 |
| Carpet Area (Sq Mtr) | 4576SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 701SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 762SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Bank Name | HDFC |
| Branch | IT Park |
| ifscCode | HDFC 0000077 |
| Account No.(70% Account) | 50200001291702 |
| State | Karnataka |
| Name | Chaithanya Infra Projects (India) Pvt.Ltd,. |
| Address | ‘Prestige Omega’, No.104, 3rd Floor,EPIP Zone, Whitefield |
| Pin Code | 560066 |
| Year Of Establishment | 2009 |
| Number of Project Completed | 110 |
| Reg. Of COA No. | CA/2006/38115 |
| Local Authority Licence Number | BCC/BL/3.6/STRL.E:52:09-10 |
| Number Of Project Completed | 2 |
| Promoter Type | Company |
| Name | Rajesh Jayaprakash |
| PAN Number | AABCC4930H |
| Address | Pattandur Agarahara Village, K.R.Puram Hobli, Bangalore East Taluk |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560066 |
| Company Registration No. | U45209KA2000PTC026241 |
| Project Name | Chaithanya RAKUEN |
| Project Description | Chaithanya Rakuen is a villa project which features 13 villas, set in 3 acre land in Whitefield, Bangalore. The architectural design of the Rakuen villas is inspired by the Zen school of thought. |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 01-08-2017 |
| Pin Code | 560066 |
| Modification Applied On | 24-05-2023 |
| Modification Approved On | 21-09-2024 |
| Type of Inventory | Type 1W |
| No of Inventory | 21 |
| Carpet Area (Sq Mtr) | 4576 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 701 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 762 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Change in Park Area, Master Plan Road as Per CDP |
| Modified plan applied date | 24/02/2018 |
| Modified plan approved date | 02/05/2023 |
| Extend of the work carried out till date of registered project ( % ) | 67.0 |
| Extend of the work pending of registered project ( % ) | 33.0 |
| Total amount collected in respect of registered project ( INR ) | 3826182394 |
| Total amount spent for the project ( INR ) | 3132655127 |
| Total balance amount lying with the promoter ( INR ) | 482789987 |
| NOC | BESCOM NOC 21082014 |
| SlNo. |
| Extension Applied On | 21-03-2023 |
| Extension Approved On | 19-04-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/446/PR/230419/000936 |
| Proposed Project End Date at the time of registration | 21-03-2023 |
| Project End Date provided under Section 6 | 21-03-2024 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Checklist for extension - 24 points |
| 1 | Shortage of Building Materials, Concrete, Jalli etc |
| 2 | others |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-04-2017 | 19-06-2018 |
| 2 | Foundation footing work | Yes | 28-04-2017 | 06-07-2018 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 06-07-2018 | 25-07-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.chaithanya.com |
| WebSite Link 2 | http://chaithanyaprojects.in/budigere/chaithanyasamarth/ |
| FAR Sanctioned | 0.463 |
| Number of Towers | 1 |
| 0 | 163 |
| 1 | 0 |
| Total No of Units | 163 |
| Project Start Date | 22-06-2017 |
| Project End Date | 21-03-2024 |
| If any extension of time has been granted | YES |
| Extended From Date | 21-03-2023 |
| Extended End Date | 21-03-2024 |
| Cost of land | 1190000000 |
| Cost of construction | 3640000000 |
| Total project cost | 4830000000 |
| Total amount collected from buyers | 4969980637 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 4236786688 |
| Balance amount with the promoter | 733193949 |
| Total number of Flats/Apartments of the Project | 163 |
| Total number of Flats/Apartments sold | 133 |
| Total number of Flats/Apartments Unsold | 30 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 15-09-2023 |
| Appeals / FNH | NO APPEALS / FNH |