Dharani Homes
DharaniConstructions
Site no C45 Ramanshree California Gardesns, Doddaballapur Main Road, Yelahanka
Approved
7th May 2018
Completed
30th Sept 2021
Registration No.
PRM/KA/RERA/1251/472/PR/180507/001645
Acknowledgement No.
PR/KN/180330/002929
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Yelahanka
State
Karnataka
Project Details
| Project Name | Dharani Homes |
| Project Description | Its s small residential building have 19 flats with 2 and 3 BHK having Ground plus three floors |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-12-2017 |
| Proposed Project Completion Date | 30-09-2021 |
| Total Area Of Land (Sq Mtr) | 833 |
| Total Coverd Area (Sq Mtr) | 528 |
| Total Open Area (Sq Mtr) | 305 |
| Estimated Cost of Construction (INR) | 70000000 |
| Cost of Land (INR) | 50000000 |
| Total Project Cost (INR) | 110000000 |
| Project Address | Site no C45 Ramanshree California Gardesns, Doddaballapur Main Road, Yelahanka |
| District | Bengaluru Urban |
| Taluk | Yelahanka |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 20 |
| Area of Garage for Sale (Sq Mtr) | 575 |
| No of Parking for Sale | 1 |
| Area of Parking for Sale (Sq Mtr) | 1 |
| Type of Inventory | Residential |
| No of Inventory | 19 |
| Carpet Area (Sq Mtr) | 1570SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 257SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 15SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | CORPORATION BANK |
| Branch | Yelahanka new town |
| ifscCode | CORP0000703 |
| Account No.(70% Account) | 0703011601000808 |
| State | Karnataka |
| Name | Babu |
| Address | 2nd cross Devarachikkana halli,vijayabank layout |
| Pin Code | 560076 |
| Year Of Establishment | 2012 |
| Number of Project Completed | 125 |
| Reg. Of COA No. | BCC/BL-3.6/E-4205/2016-17 |
| Local Authority Licence Number | BCC/BL-3.6 SE-211/2016-17 |
| Number Of Project Completed | 5 |
Promoter Details
| Promoter Type | Partnership Firm |
| Name | Jayachandra Naidu |
| PAN Number | AAN******* |
| Address | 501 4th cross shanthiniketan layout.BG Road |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560064 |
| Company Registration No. | NOT APPLICABLE |
| Type | Others |
| Pin Code | 560076 |
Modification Plan Details
| Type of Inventory | Residential |
| No of Inventory | 19 |
| Carpet Area (Sq Mtr) | 1570 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 257 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 15 Sq Mtr |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 20-10-2017 | 28-10-2017 |
| 2 | Foundation footing work | Yes | 02-11-2017 | 09-11-2017 |
| 3 | Retaining wall (All types) | Yes | 10-12-2017 | 24-12-2017 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 02-01-2018 | 02-02-2018 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| FAR Sanctioned | 2.0 |
| Number of Towers | 1 |
| 0 | 4 |
| 1 | 5 |
| 2 | 5 |
| 3 | 5 |
| Total No of Units | 19 |
Completion Details
| Project Start Date | 01-12-2017 |
| Project End Date | 30-09-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 50000000 |
| Cost of construction | 70000000 |
| Total project cost | 110000000 |
| Total amount collected from buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 0 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 19 |
| Total number of Flats/Apartments sold | 0 |
| Total number of Flats/Apartments Unsold | 19 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 06-08-2019 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Mangalore


Ask Pulse Ai anything about real estate





