DS MAX PROPERTIES PVT LTD
situated at Chikkasandra Village, Yeshwanthpur Hobli, Bangalore North Taluk, situated at Chikkasandra Village, Yeshwanthpur Hobli, Bangalore North Taluk
Approved
20th Jan 2018
Completed
30th Sept 2021
Registration No.
PRM/KA/RERA/1251/309/PR/180120/001403
Acknowledgement No.
PR/KN/170822/001403
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
| Project Name | DS MAX SONATA |
| Project Description | converted land property bearing Sy. No. 32/1, which measuring 1 acre 20 guntas, situated at Chikkasandra Village, Yeshwanthpur Hobli, Bangalore North Taluk, Total 180 Flats |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 20-08-2017 |
| Proposed Project Completion Date | 30-09-2021 |
| Total Area Of Land (Sq Mtr) | 5911 |
| Total Coverd Area (Sq Mtr) | 13323 |
| Total Open Area (Sq Mtr) | 0 |
| Estimated Cost of Construction (INR) | 198500000 |
| Cost of Land (INR) | 163350000 |
| Total Project Cost (INR) | 256200000 |
| Project Address | situated at Chikkasandra Village, Yeshwanthpur Hobli, Bangalore North Taluk, situated at Chikkasandra Village, Yeshwanthpur Hobli, Bangalore North Taluk |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 180 |
| Area of Garage for Sale (Sq Mtr) | 2580 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 2 & 3bhk |
| No of Inventory | 119 |
| Carpet Area (Sq Mtr) | 12135SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 11525SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | ANDHRA BANK |
| Branch | BANASWADI |
| ifscCode | ANDB0001432 |
| Account No.(70% Account) | 143211100003934 |
| State | Karnataka |
| Promoter Type | Company |
| Name | KV SATISH |
| PAN Number | AACCD6168M |
| Address | converted land property bearing Sy.No.60, measuring to an extent of 2 acres, situated at Gollahalli Village, Uttarahalli Hobli, Bangalore South Taluk, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560043 |
| Company Registration No. | U70102KA2007PTC041508 |
| Project Name | DS MAX STONE HILL |
| Project Description | converted land property bearing Sy.No.60, measuring to an extent of 2 acres, situated at Gollahalli Village, Uttarahalli Hobli, Bangalore South Taluk, Total 256 Flats |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 22-08-2017 |
| Pin Code | 560018 |
| Type of Inventory | 2 & 3bhk |
| No of Inventory | 119 |
| Carpet Area (Sq Mtr) | 12135 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 11525 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 22-08-2017 | 06-09-2017 |
| 2 | Foundation footing work | Yes | 11-09-2017 | 20-12-2017 |
| 3 | Retaining wall (All types) | Yes | 21-10-2017 | 20-12-2017 |
| 4 | Plinth level Beam | Yes | 29-01-2018 | 30-03-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 21-10-2017 | 20-12-2017 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.dsmaxproperties.com |
| FAR Sanctioned | 1.65 |
| Number of Towers | 1 |
| 0 | 45 |
| 1 | 45 |
| 2 | 45 |
| 3 | 45 |
| Total No of Units | 180 |
| Project Start Date | 20-08-2017 |
| Project End Date | 30-09-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 163350000 |
| Cost of construction | 198500000 |
| Total project cost | 256200000 |
| Total amount collected from buyers | 274944725 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 227940922 |
| Balance amount with the promoter | 47003803 |
| Total number of Flats/Apartments of the Project | 180 |
| Total number of Flats/Apartments sold | 118 |
| Total number of Flats/Apartments Unsold | 62 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 02-06-2021 |
| Appeals / FNH | NO APPEALS / FNH |