Earth & Essence - Plotted Development - Phase 2
Assetz Premium Holdings Private Limited
Sy No 17 HOSAHALLI VILLAGE, JALA HOBLI YELAHANKA TALUK, BANGALORE URBAN DISTRICT
Approved
27th Oct 2021
Completed
30th Mar 2024
Registration No.
PRM/KA/RERA/1251/309/PR/211027/004375
Acknowledgement No.
ACK/KA/RERA/1251/309/PR/210824/005174
Project Type
Plotted Development
Approving Authority
BIAPPA - Bangalore Airport Area Planning Authority
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
Project Details
| Project Name | Earth & Essence - Plotted Development - Phase 2 |
| Project Description | Plotted Development Project |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 01-10-2021 |
| Proposed Project Completion Date | 30-03-2024 |
| Total Area Of Land (Sq Mtr) | 23067 |
| Total Coverd Area (Sq Mtr) | 10527 |
| Total Open Area (Sq Mtr) | 12540 |
| Estimated Cost of Construction (INR) | 317959965 |
| Cost of Land (INR) | 462496750 |
| Total Project Cost (INR) | 780456715 |
| Project Address | Sy No 17 HOSAHALLI VILLAGE, JALA HOBLI YELAHANKA TALUK, BANGALORE URBAN DISTRICT |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BIAPPA - Bangalore Airport Area Planning Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | ODD Site |
| No of Inventory | 1 |
| Carpet Area (Sq Mtr) | 309SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | Richmond Road |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 57500000718421 |
| State | Karnataka |
| Name | Rajesh S Shirakol |
| Address | RREN Consultants & Contractors Pvt Ltd 470 Muneesh Legacy 1st floor,13th Cross 3rd Main Indiranagar 2nd stage Bengaluru |
| Pin Code | 560038 |
| Year Of Establishment | 2018 |
| Number of Project Completed | 10 |
| Reg. Of COA No. | CA/2004/33004 |
| Local Authority Licence Number | M-137173-2 |
Promoter Details
| Promoter Type | Company |
| Name | Somasundaram Thiruppathi |
| PAN Number | AAN******* |
| Address | Assetz House No 30 .Crescent Road |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560001 |
| Company Registration No. | U45205KA2015PTC079422 |
| Type | Director |
| Pin Code | 560001 |
| Sl No. |
Modification Plan Details
| Type of Inventory | ODD Site |
| No of Inventory | 1 |
| Carpet Area (Sq Mtr) | 309 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
Extension Details
| Extension Applied On | 24-02-2023 |
| Extension Approved On | 25-04-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/309/PR/230425/004375 |
| Proposed Project End Date at the time of registration | 31-03-2023 |
| Project End Date provided under Section 6 | 30-03-2024 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | YES |
| Document Name | Form B |
| 1 | others |
Residential Plot Details
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Residential | MID SIZE PLOT | 242.30 | Phase 2 | Infrastructure work in Progress | 19.77 | 18.3 | 9.5 | 16.98 | Road | Site 2 | Site 24 | Road |
| 2 | 2 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 1 | Site 3 | Site 23,24 | Road |
| 3 | 3 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 2 | Site 4 | Site 23 | Road |
| 4 | 4 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 3 | Site 5 | Site 22 | Road |
| 5 | 5 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 4 | Site 6 | Site 21 | Road |
| 6 | 6 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 5 | Site 7 | Site 20 | Road |
| 7 | 7 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 6 | Site 8 | Site 19 | Road |
| 8 | 8 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 7 | Site 9 | Site 18 | Road |
| 9 | 9 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 8 | Site 10 | Site 17 | Road |
| 10 | 10 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 9 | Site 11 | Site 16 | Road |
| 11 | 11 | Residential | 13.63 M X 18.30 M | 249.43 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 13.63 | 13.63 | Site 10 | Site 12 | Site 15 | Road |
| 12 | 12 | Residential | 13.63 M X 18.30 M | 249.43 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 13.63 | 13.63 | Site 11 | Site 13 | Site 14 | Road |
| 13 | 13 | Residential | MID SIZE PLOT | 251.18 | Phase 2 | Infrastructure work in Progress | 18.3 | 20.72 | 11 | 12.64 | Site 12 | Road | Public Utility | Road |
| 14 | 14 | Residential | 13.63 M X 18.30 M | 249.43 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 13.63 | 13.63 | Site 15 | Public Utility | Road | Site 12 |
| 15 | 15 | Residential | 13.63 M X 18.30 M | 249.43 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 13.63 | 13.63 | Site 16 | Site 14 | Road | Site 11 |
| 16 | 16 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 17 | Site 15 | Road | Site 10 |
| 17 | 17 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 18 | Site 16 | Road | Site 9 |
| 18 | 18 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 19 | Site 17 | Road | Site 8 |
| 19 | 19 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 20 | Site 18 | Road | Site 7 |
| 20 | 20 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 21 | Site 19 | Road | Site 6 |
| 21 | 21 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 22 | Site 20 | Road | Site 5 |
| 22 | 22 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 23 | Site 21 | Road | Site 4 |
| 23 | 23 | Residential | 15.24 M X 18.30 M | 278.89 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 15.24 | 15.24 | Site 24 | Site 22 | Road | Site 3, 2 |
| 24 | 24 | Residential | LARGER SIZE PLOT | 273.17 | Phase 2 | Infrastructure work in Progress | 19.77 | 18.3 | 11.19 | 18.66 | Road | Site 23 | Road | Site 2,1 |
| 25 | 25 | Residential | LARGER SIZE PLOT | 289.60 | Phase 2 | Infrastructure work in Progress | 20.06 | 18.3 | 11.75 | 19.85 | Private Property | Site 26 | Site 44 | Road |
| 26 | 26 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 25 | Site 27 | Site 44,43 | Road |
| 27 | 27 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 26 | Site 28 | Site 43 | Road |
| 28 | 28 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 27 | Site 29 | Site 42 | Road |
| 29 | 29 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 28 | Site 30 | Site 41 | Road |
| 30 | 30 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 29 | Site 31 | Site 40 | Road |
| 31 | 31 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 30 | Site 32 | Site 39 | Road |
| 32 | 32 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 31 | Site 33 | Site 38 | Road |
| 33 | 33 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 32 | Site 34 | Site 37 | Road |
| 34 | 34 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 33 | Site 35 | Site 36 | Road |
| 35 | 35 | Residential | LARGER SIZE PLOT | 284.19 | Phase 2 | Infrastructure work in Progress | 18.3 | 20.6 | 13.08 | 14.38 | Site 34 | Road | Site 36, Public Utility | Road |
| 36 | 36 | Residential | 15.24 M X 18.30 M | 278.89 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 15.24 | 15.24 | Site 37 | Public Utility | Road | Site 35, 34 |
| 37 | 37 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 38 | Site 36 | Road | Site 33 |
| 38 | 38 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 39 | Site 37 | Road | Site 32 |
| 39 | 39 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 40 | Site 38 | Road | Site 31 |
| 40 | 40 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 41 | Site 39 | Road | Site 30 |
| 41 | 41 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 42 | Site 40 | Road | Site 29 |
| 42 | 42 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 43 | Site 41 | Road | Site 28 |
| 43 | 43 | Residential | 15.24 M X 18.30 M | 278.89 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 15.24 | 15.24 | Site 44 | Site 42 | Road | Site 26, 27 |
| 44 | 44 | Residential | LARGER SIZE PLOT | 308.60 | Phase 2 | Infrastructure work in Progress | 19.94 | 18.3 | 12.85 | 20.88 | Private Property | Site 43 | Road | Site 25, 26 |
| 45 | 45 | Residential | LARGER SIZE PLOT | 294.55 | Phase 2 | Infrastructure work in Progress | 20.07 | 18.3 | 12.06 | 20.16 | Private Property | Site 46 | Kharab, private property | Road |
| 46 | 46 | Residential | 15.24 M X 18.30 M | 278.89 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 15.24 | 15.24 | Site 45 | Site 47 | Kharab, private property | Road |
| 47 | 47 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 46 | Site 48 | Kharab, private property | Road |
| 48 | 48 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 47 | Site 49 | Kharab, private property | Road |
| 49 | 49 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 48 | Site 50 | Kharab, private property | Road |
| 50 | 50 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 49 | Site 51 | Kharab, private property | Road |
| 51 | 51 | Residential | 12.20M X 18.30M | 223.26 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 12.2 | 12.2 | Site 50 | Site 52 | Kharab, private property | Road |
| 52 | 52 | Residential | 15.24 M X 18.30 M | 278.89 | Phase 2 | Infrastructure work in Progress | 18.3 | 18.3 | 15.24 | 15.24 | Site 51 | Public Utility | Kharab, private property | Road |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-01-2022 | 15-02-2022 |
| 2 | Formation Of Road, Footpath | Yes | 01-02-2022 | 31-12-2022 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 15-03-2022 | 31-07-2022 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 14-04-2022 | 31-08-2022 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 01-10-2022 | 31-01-2023 |
| 6 | Construction Of Storm Water Drainage | Yes | 29-04-2022 | 30-09-2022 |
| 7 | Solid Waste Management and Disposal | Yes | 01-11-2022 | 30-01-2023 |
| 8 | Tree Plantation And LandScape Work | Yes | 01-01-2023 | 31-03-2023 |
| 9 | Street Lighting | Yes | 01-02-2023 | 31-03-2023 |
| 10 | Other Miscellaneous Work | No |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | Yes |
| 4 | Club House | Yes |
| 5 | Community Hall | Yes |
| 6 | Outdoor Sports facility | Yes |
| 7 | Indoor sports facility | Yes |
| 8 | Swimming Pools | Yes |
| 9 | Gym | Yes |
| 10 | Parks | Yes |
| 11 | Power Backup | Yes |
| 12 | Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning and incarnation | No |
Post Registration Details
| WebSite Link 1 | www.assetzproperty.com |
| Agent Registration No 1 | undefined |
| Agent Registration No 2 | PRM/KA/RERA/1251/310/AG/190711/001527 |
| Agent Registration No 3 | PRM/KA/RERA/1251/310/AG/170823/000047 |
| Agent Registration No 4 | PRM/KA/RERA/1251/309/1G/180228/001934 |
| Agent Registration No 5 | PRM/KA/RERA/1251/446/AG/180430/000897 |
| Agent Registration No 6 | PRM/KA/RERA/1251/446/AG/171021/001317 |
| Agent Registration No 7 | PRM/KA/RERA/1251/309/AG/180804/001069 |
| Agent Registration No 8 | PRM/KA/RERA/1251/446/AG/210225/002303 |
| Agent Registration No 9 | PRM/KA/RERA/1251/310/AG/200826/001951 |
| Agent Registration No 10 | PRM/KA/RERA/1251/309/AG/171113/000713 |
| Agent Registration No 11 | PRM/KA/RERA/1251/310/AG/191023/001624 |
| Agent Registration No 12 | PRM/KA/RERA/1251/309/AG/180221/001740 |
| Agent Registration No 13 | ACK/KA/RERA/1251/310/AG/201226/002472 |
| Total number of Plots | 52 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 166 |
| No. of Parks and Open Spaces | 2 |
| Area of Parks and Open Spaces(in Sq.m) | 2321 |
| Area of Road/Transportation(in Sq.m) | 6625 |
Completion Details
| Project Start Date | 01-10-2021 |
| Project End Date | 30-03-2024 |
| If any extension of time has been granted | YES |
| Extended From Date | 31-03-2023 |
| Extended End Date | 30-03-2024 |
| Cost of land | 462496750 |
| Cost of construction | 317959965 |
| Total cost | 780456715 |
| Total amount collected From buyers | 538345817 |
| Whether any loan has been raised | YES |
| Total amount spent on Project for completion of the project | 776825957 |
| Total No of sites of Project | 52 |
| Total No of sites sold | 42 |
| Total No of sites unsold | 10 |
| Whether there is any changes in inventory details | NO |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Udupi


Ask Pulse Ai anything about real estate