PIONIER PPROJECT
Sy. No. 48/2, Gattahalli Village Sarjapura Hobli, Anekal taluk
Approved
4th Feb 2022
Completed
31st Dec 2024
Registration No.
PRM/KA/RERA/1251/308/PR/220204/004668
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/210925/005280
Project Type
Plotted Development
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | EAST AVVENUE |
| Project Description | BDA APPROVED RESIDENTIAL PLOTS WITH BASIC AMENITIES CONSISTING OF 19 PLOTS |
| Project Type | Plotted Development |
| Project Status | New Project Launch |
| Project Start Date | 18-10-2021 |
| Proposed Project Completion Date | 31-12-2024 |
| Total Area Of Land (Sq Mtr) | 3895 |
| Total Coverd Area (Sq Mtr) | 1812 |
| Total Open Area (Sq Mtr) | 2083 |
| Estimated Cost of Construction (INR) | 11210706 |
| Cost of Land (INR) | 70000000 |
| Total Project Cost (INR) | 81210706 |
| Project Address | Sy. No. 48/2, Gattahalli Village Sarjapura Hobli, Anekal taluk |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | EWS |
| No of Inventory | 2 |
| Carpet Area (Sq Mtr) | 223SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | KOTAK MAHINDRA BANK |
| Branch | M G ROAD |
| ifscCode | KKBK0008066 |
| Account No.(70% Account) | 7745098736 |
| State | Karnataka |
| Name | M/s. CREATIVE SPACE |
| Address | #6, 1st C' main, chikkayellappa industrial area, ,koramangala 1st block, |
| Pin Code | 560034 |
| Year Of Establishment | 2015 |
| Number of Project Completed | 15 |
| Reg. Of COA No. | CA/2006/3754 |
| Local Authority Licence Number | BCC/BL-3.6/SE-129/2012-2013 |
| Number Of Project Completed | 30 |
| Promoter Type | Partnership Firm |
| Name | KAVITHA V REDDY |
| PAN Number | ABBFP3517F |
| Address | SY.NO.55, GATTAHALLI VILLAGE SARJAPURA HOBLI ANEKAL TALUK ANEKAL |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560034 |
| Company Registration No. | JNRF758 2021 22 |
| Type | Others |
| Pin Code | 560099 |
| Project Name | PIONIER LIFESTYLE |
| Project Description | BDA APPROVED PLOTS, WITH BASIC AMENITIES, CONSISTING OF 107 PLOTS |
| Current Status | Ongoing |
| Type of Land | Plotted Development |
| Expected Completion Date | 28-02-2022 |
| Sl No. |
| Type of Inventory | EWS |
| No of Inventory | 2 |
| Carpet Area (Sq Mtr) | 223 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | ODD | ODD | 45.71 | NA | NA | 8.94 | 7.85 | 5.41 | 5.49 | Site no.02 | Private Property | Road | Site no.03 |
| 2 | 2 | ODD | ODD | 52.86 | NA | NA | 10.06 | 8.94 | 5.61 | 5.51 | Road | Site no.01 | Road | Site no.03 |
| 3 | 3 | ODD | ODD | 101.36 | NA | NA | 9.14 | 9.14 | 11 | 11.17 | Road | Private Property | Site no.01&02 | Site no.04 |
| 4 | 4 | ODD | ODD | 103.12 | NA | NA | 9.14 | 9.14 | 11.17 | 11.38 | Road | Private Property | Site no.03 | Site no.05 |
| 5 | 5 | ODD | ODD | 104.98 | NA | NA | 9.14 | 9.14 | 11.38 | 11.58 | Road | Private Property | Site no.04 | Site no.06 |
| 6 | 6 | ODD | ODD | 106.93 | NA | NA | 9.14 | 9.14 | 11.58 | 11.81 | Road | Private Property | Site no.05 | Site no.07 |
| 7 | 7 | ODD | ODD | 108.88 | NA | NA | 9.14 | 9.14 | 11.81 | 12.01 | Road | Private Property | Site no.06 | Site no.08 |
| 8 | 8 | ODD | ODD | 110.74 | NA | NA | 9.14 | 9.14 | 12.01 | 12.22 | Road | Private Property | Site no.07 | Site no.09 |
| 9 | 9 | ODD | ODD | 112.6 | NA | NA | 9.14 | 9.14 | 12.22 | 12.42 | Road | Private Property | Site no.08 | Site no.10 |
| 10 | 10 | ODD | ODD | 114.46 | NA | NA | 9.14 | 9.14 | 12.42 | 12.62 | Road | Private Property | Site no.09 | Site no.11 |
| 11 | 11 | ODD | ODD | 114.92 | NA | NA | 9.14 | 9.14 | 12.62 | 12.83 | Road | Private Property | Site no.10 | Site no.12 |
| 12 | 12 | ODD | ODD | 118.17 | NA | NA | 9.14 | 9.14 | 12.83 | 13.03 | Road | Private Property | Site no.11 | Site no.13 |
| 13 | 13 | ODD | ODD | 120.03 | NA | NA | 9.14 | 9.14 | 13.03 | 13.23 | Road | Private Property | Site no.12 | Site no.14 |
| 14 | 14 | ODD | ODD | 121.89 | NA | NA | 9.14 | 9.14 | 13.23 | 13.44 | Road | Private Property | Site no.13 | Site no.15 |
| 15 | 15 | ODD | ODD | 123.93 | NA | NA | 9.14 | 9.14 | 13.44 | 13.67 | Road | Private Property | Site no.14 | Site no.16 |
| 16 | 16 | ODD | ODD | 125.88 | NA | NA | 9.14 | 9.14 | 13.67 | 13.87 | Road | Private Property | Site no.15 | Site no.17 |
| 17 | 17 | ODD | ODD | 127.74 | NA | NA | 9.14 | 9.14 | 13.87 | 14.07 | Road | Private Property | Site no.16 | Site no.18 |
| 18 | 18 | ODD | ODD | 154.4 | NA | NA | 10.91 | 10.91 | 14.07 | 14.3 | Road | Private Property | Site no.17 | Site no.19 |
| 19 | 19 | ODD | ODD | 2.51 | NA | NA | 0.3 | 0.06 | 14.3 | 14.33 | Road | Private Property | Site no.18 | Park |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 14-03-2022 | 31-08-2022 |
| 2 | Formation Of Road, Footpath | No | ||
| 3 | Construction Of WaterSupply Infrastucture | Yes | 02-05-2022 | 30-09-2022 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 02-05-2022 | 30-09-2022 |
| 5 | Power Supply Work(Tansformer And Substation) | No | ||
| 6 | Construction Of Storm Water Drainage | Yes | 03-05-2022 | 30-09-2022 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | No | ||
| 9 | Street Lighting | Yes | 14-03-2022 | 30-06-2022 |
| 10 | Other Miscellaneous Work | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | Yes |
| 5 | Community Hall | Yes |
| 6 | Outdoor Sports facility | Yes |
| 7 | Indoor sports facility | Yes |
| 8 | Swimming Pools | Yes |
| 9 | Gym | Yes |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | No |
| 14 | Air conditioning and incarnation | No |
| WebSite Link 1 | www.pionierdevelopers.com |
| Total number of Plots | 19 |
| No. of Public and Semi Pubic Sites | 19 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 1811 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 614 |
| Area of Road/Transportation(in Sq.m) | 1469 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Project | No Complaints Found. |