L&T Realty Developers Limited
Yelahanka
Approved
10th Mar 2025
Pending
31st Mar 2030
Registration No.
PRM/KA/RERA/1251/472/PR/100325/007564
Acknowledgement No.
ACK/KA/RERA/1251/472/PR/060225/008929
Project Type
Residential/Group Housing
District
Bengaluru Urban
Taluka
Yelahanka
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Company |
| Promoter Name | L&T Realty Developers Limited |
| Main Objectives | To develop Real estate for Sales & Marketing |
| Registration Number | U29119MH1997PLC109700 |
| PAN | AFTPK0129E |
| GSTIN | 29AAACL4175C3ZL |
| Promoter Website | https://www.lntrealty.com |
| Promoter Address | L&T Realty Developers Limited, Project Office, Shabari Nagar,Bellary Road, Byatarayanapura, BEngaluru (Bangalore) Urban ,Yelahanka ,Bengaluru Urban-560092 |
| District | Bengaluru Urban |
| Taluk | Yelahanka |
| PIN Code | 560092 |
| Name of Authorized Signatory | Sreepada V |
| Name of CEO/MD | Anupam Kumar |
| Designation | CEO & MD |
| Director Identification (DIN) Number | 10086651 |
| Number of Directors | 1 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | NO |
| Present Address | L&T Realty Developers Limited, Project Office, Shabari Nagar, Bellary Road, Byatarayanapura, BEngaluru (Bangalore) Urban , Bengaluru Urban , Karnataka - 560092 |
| Permanent Address | B702 Eldora, Hiranandani Gardens, L. H. Hiranandani Hospital, POwai , Mumbai Suburban , Maharashtra - 400076 |
| Official Address | L&T Realty Developers Limited, Project Office, Shabari Nagar, Bellary Road, Byatarayanapura, BEngaluru (Bangalore) Urban , Bengaluru Urban , Karnataka - 560092 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 | |
| Sl No._3 |
| Type of Inventory | 4BHK |
| No of Inventory | 144 |
| Carpet Area (Sq Mtr) | 26630 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 2521 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-02-2025 | 31-12-2025 |
| 2 | Foundation footing work | Yes | 01-01-2026 | 31-05-2026 |
| 3 | Upto Plinth Level | Yes | 15-11-2026 | 15-05-2027 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-05-2026 | 15-11-2026 |
| 5 | Retaining wall (All types) | Yes | 15-05-2026 | 31-07-2027 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | Yes |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | No |
| 5 | Fire protection and fire safety requirements | Yes |
| 6 | Solid waste management and disposal | Yes |
| 7 | Emergency Evacuation services | Yes |
| FAR Sanctioned | 3.25 |
| Number of Towers | 3 |
| 0 | 11 |
| 1 | 13 |
| 2 | 14 |
| 3 | 16 |
| 4 | 16 |
| 5 | 16 |
| 6 | 16 |
| 7 | 16 |
| 8 | 16 |
| 9 | 16 |
| 10 | 16 |
| 11 | 16 |
| 12 | 13 |
| 13 | 9 |
| Total No of Units | 634 |