Embassy Property Development Private Limited
Embassy Lake Terraces,6/1A, Service Road,, Subramani Nagar, Hebbal Kempapura, Next To Columbia Asia Hospital
Approved
16th Oct 2017
Completed
31st Mar 2023
Registration No.
PRM/KA/RERA/1251/309/PR/171016/000602
Acknowledgement No.
PR/KN/170731/000602
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
| Project Name | Embassy Lake Terraces |
| Project Description | Embassy Lake Terraces is a uber-luxury development spread across 14.5 acres with 9 towers and 467 condominiums |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 10-09-2012 |
| Proposed Project Completion Date | 30-03-2021 |
| Further Extension Date | 31-03-2023 |
| Total Area Of Land (Sq Mtr) | 66277 |
| Total Coverd Area (Sq Mtr) | 15827 |
| Total Open Area (Sq Mtr) | 50450 |
| Estimated Cost of Construction (INR) | 15353015993 |
| Cost of Land (INR) | 8616446126 |
| Total Project Cost (INR) | 23969462119 |
| Project Address | Embassy Lake Terraces,6/1A, Service Road,, Subramani Nagar, Hebbal Kempapura, Next To Columbia Asia Hospital |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 127 |
| Area of Parking for Sale (Sq Mtr) | 1746 |
| Extent of development carried till date | 77 % |
| Extent of development pending | 23 % |
| Total amount of money collected from allottee | 7887624858 |
| Total amount of money used for development of project | 18453570238 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | Yes |
| Reason For Delay | Resource scarciity |
| No of Month Delay | 11 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | Richmond road |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 57500000059756 |
| State | Karnataka |
| Name | JMC Projects India Limited |
| Address | Gold Tower, # 50, 2nd Floor, ,Residency Road, Near Konark Hotel |
| Pin Code | 560025 |
| Year Of Establishment | 1986 |
| Number of Project Completed | 134 |
| Reg. Of COA No. | NA |
| Local Authority Licence Number | NA |
| Number Of Project Completed | 100 |
| Promoter Type | Company |
| Name | Jitendra Virwani |
| PAN Number | AAACD6927A |
| Address | 46/1 and 46/2 promanade road ulsoor Meanee Ave Rd Sindhi Colony, Pulikeshi Nagar, Bengaluru, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560001 |
| Company Registration No. | U85110KA1996PTC020897 |
| Type | Director |
| Pin Code | 560042 |
| Project Name | Embassy Oasis |
| Project Description | 26 apartments 12 floors |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 31-07-2017 |
| Extension Applied On | 04-06-2019 |
| Extension Approved On | 30-11-2019 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/309/PR/191130/000602 |
| Proposed Project End Date at the time of registration | 30-06-2019 |
| Project End Date provided under Section 6 | 30-06-2020 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | AFFIDAVIT, REASON FOR DELAY, CLRIFICATION AND SOLD AND UNSOLD DETAILS |
| 1 | others |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 26-09-2012 | 19-12-2013 |
| 2 | Foundation footing work | Yes | 19-05-2013 | 24-11-2013 |
| 3 | Retaining wall (All types) | Yes | 24-05-2013 | 20-05-2015 |
| 4 | Plinth level Beam | Yes | 14-06-2013 | 15-02-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 14-04-2013 | 13-02-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.embassylaketerraces.com |
| Agent Registration No 1 | PRM/KA/RERA/1251/310/AG/170824/000071 |
| Agent Registration No 2 | PRM/KA/RERA/1251/446/AG/170926/000120 |
| FAR Sanctioned | 3.25 |
| Number of Towers | 2 |
| 0 | 5 |
| 1 | 5 |
| 2 | 14 |
| 3 | 14 |
| 4 | 14 |
| 5 | 14 |
| 6 | 14 |
| 7 | 14 |
| 8 | 14 |
| 9 | 14 |
| 10 | 14 |
| 11 | 1 |
| 12 | 3 |
| 13 | 7 |
| 14 | 7 |
| 15 | 7 |
| 16 | 7 |
| 17 | 7 |
| 18 | 7 |
| 19 | 7 |
| 20 | 7 |
| 21 | 4 |
| Total No of Units | 467 |
| Project Start Date | 10-09-2012 |
| Project End Date | 30-03-2021 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-06-2019 |
| Extended End Date | 30-06-2020 |
| Cost of land | 8616446126 |
| Cost of construction | 15353015993 |
| Total project cost | 23969462119 |
| Total amount collected from buyers | 10402378659 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 26205709103 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 467 |
| Total number of Flats/Apartments sold | 356 |
| Total number of Flats/Apartments Unsold | 111 |
| Whether the project has been completed within the stipulated Period? | NO |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 16-05-2022 |
| Appeals / FNH | NO APPEALS / FNH |