Estella Projects Private Limited
sy.no.70,71/2 & 71/5 of choodasandra village, sarjapura Hoblie anekal taluk
Approved
24th May 2018
Completed
30th Jun 2021
Registration No.
PRM/KA/RERA/1251/308/PR/180524/001815
Acknowledgement No.
PR/KN/180222/002710
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | Estella Maple square Block A |
| Project Description | Estella Maple Square Block A- JDA- project , one building with 2 blocks- Block-1 & 2 and club house between 2 Block joined, Each of 2 common basements, ground & 8 Upper floors - comprising of 70 units out of which 42 units belongs to Estella Projects Private Limited |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 01-02-2018 |
| Proposed Project Completion Date | 30-06-2021 |
| Total Area Of Land (Sq Mtr) | 3237 |
| Total Coverd Area (Sq Mtr) | 1237 |
| Total Open Area (Sq Mtr) | 2000 |
| Estimated Cost of Construction (INR) | 300000000 |
| Cost of Land (INR) | 60000000 |
| Total Project Cost (INR) | 360000000 |
| Project Address | sy.no.70,71/2 & 71/5 of choodasandra village, sarjapura Hoblie anekal taluk |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | HSR Layout |
| ifscCode | HDFC0004094 |
| Account No.(70% Account) | 50200011303172 |
| State | Karnataka |
| Name | Khemraj Sahare |
| Address | No 20, 17th Cross, Rose Graden Road,JP Nagar 5th Phase |
| Pin Code | 560102 |
| Year Of Establishment | 2018 |
| Number of Project Completed | 20 |
| Reg. Of COA No. | CA/2014/65875 |
| Local Authority Licence Number | BCC/BL-3.6SE/183/2014-15 |
| Number Of Project Completed | 1 |
| Promoter Type | Company |
| Name | MOHAN REDDY AGANI |
| PAN Number | AADCE5581G |
| Address | 443,16th corss, 5th main,.HSR layout,6th sector bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560102 |
| Company Registration No. | U70100KA2013PTC0702459 |
| Type | Director |
| Pin Code | 560102 |
| Extension Applied On | 18-03-2020 |
| Extension Approved On | 20-06-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/308/PR/220620/001815 |
| Proposed Project End Date at the time of registration | 30-06-2020 |
| Project End Date provided under Section 6 | 30-06-2021 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | Applied for modification |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 14-12-2017 | 24-02-2018 |
| 2 | Foundation footing work | Yes | 20-02-2018 | 18-09-2018 |
| 3 | Retaining wall (All types) | Yes | 24-01-2018 | 31-05-2018 |
| 4 | Plinth level Beam | Yes | 02-05-2018 | 15-05-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| Prospectus/Brochure | broucher maple square |
| WebSite Link 1 | www.estellaprojects.com |
| Agent Registration No 1 | NA |
| Advertisement Copy 1 | advertisement add |
| FAR Sanctioned | 2.24 |
| Number of Towers | 1 |
| 0 | 1 |
| 1 | 6 |
| 2 | 5 |
| 3 | 5 |
| 4 | 10 |
| 5 | 9 |
| 6 | 9 |
| 7 | 8 |
| 8 | 4 |
| Total No of Units | 57 |
| Project Start Date | 01-02-2018 |
| Project End Date | 30-06-2021 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-06-2020 |
| Extended End Date | 30-06-2021 |
| Cost of land | 60000000 |
| Cost of construction | 300000000 |
| Total project cost | 360000000 |
| Total amount collected from buyers | 215459479 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 496732062 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 57 |
| Total number of Flats/Apartments sold | 55 |
| Total number of Flats/Apartments Unsold | 2 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 20-05-2022 |
| Appeals / FNH | NO APPEALS / FNH |