KATARIA INFFRA
SY NO 52/1 KUMBALGODU VILLAGE, KENGERI HOBLI
Approved
24th May 2018
Completed
30th Jun 2019
Registration No.
PRM/KA/RERA/1251/310/PR/180524/001814
Acknowledgement No.
PR/KN/180124/002687
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | EXCELSIOR |
| Project Description | THIS PROJECT HAS 6 BLOCKS EACH BLOCK HAS 20 UNITS |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 01-02-2018 |
| Proposed Project Completion Date | 30-06-2019 |
| Total Area Of Land (Sq Mtr) | 3844 |
| Total Coverd Area (Sq Mtr) | 2403 |
| Total Open Area (Sq Mtr) | 1441 |
| Estimated Cost of Construction (INR) | 41149034 |
| Cost of Land (INR) | 15000000 |
| Total Project Cost (INR) | 56149034 |
| Project Address | SY NO 52/1 KUMBALGODU VILLAGE, KENGERI HOBLI |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 8 |
| Area of Parking for Sale (Sq Mtr) | 96 |
| Road System | Local Authority |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | VIJAYANAGAR |
| ifscCode | HDFC0000312 |
| Account No.(70% Account) | 50200029322920 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | VIMAL JAIN |
| PAN Number | ABCPJ7856L |
| Address | 1ST FLOOR, 459, NEW NO 10 , 12TH MAIN ROAD, M C LAYOUT, VIJAYNAGAR |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560040 |
| Company Registration No. | NOT APPLICABLE |
| Extension Applied On | 27-06-2019 |
| Extension Approved On | 26-05-2020 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/200526/001814 |
| Proposed Project End Date at the time of registration | 26-03-2019 |
| Project End Date provided under Section 6 | 30-06-2019 |
| whether 2/3rd concern from the allottees has taken? | YES |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | AFFIDAVIT U/S 18(1) |
| 1 | Shortage of Labour |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 20-01-2018 | 19-02-2018 |
| 2 | Foundation footing work | Yes | 20-02-2018 | 31-03-2018 |
| 3 | Retaining wall (All types) | Yes | 02-03-2018 | 10-03-2018 |
| 4 | Plinth level Beam | Yes | 01-02-2018 | 15-02-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-03-2018 | 01-04-2018 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 2.0 |
| Number of Towers | 3 |
| 0 | 4 |
| 1 | 4 |
| 2 | 4 |
| 3 | 4 |
| Total No of Units | 48 |
| Name | Registered conveyance deed for an individual unit |
| Approval Date | 23-08-2019 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |