Axis Concepts Capstone Pvt. ltd.
8/2, Allasandra village, Yelahanka Hobli,
Approved
22nd Nov 2018
Completed
3rd Jan 2025
Registration No.
PRM/KA/RERA/1251/472/PR/181122/002177
Acknowledgement No.
ACK/KA/RERA/1251/472/PR/181103/002780
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Yelahanka
State
Karnataka
| Project Name | Flowing Tree |
| Project Description | Residential apartment project |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 03-10-2018 |
| Proposed Project Completion Date | 03-01-2025 |
| Total Area Of Land (Sq Mtr) | 8905 |
| Total Coverd Area (Sq Mtr) | 1181 |
| Total Open Area (Sq Mtr) | 7724 |
| Estimated Cost of Construction (INR) | 746656084 |
| Cost of Land (INR) | 127069000 |
| Total Project Cost (INR) | 873725084 |
| Project Address | 8/2, Allasandra village, Yelahanka Hobli, |
| District | Bengaluru Urban |
| Taluk | Yelahanka |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 21 |
| Area of Parking for Sale (Sq Mtr) | 288 |
| Type of Inventory | DUPLEX |
| No of Inventory | 7 |
| Carpet Area (Sq Mtr) | 1001SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 234SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Hardscape and Softscape | Self Development |
| Bank Name | KOTAK MAHINDRA BANK |
| Branch | Lavelle Road Branch |
| ifscCode | KKBK0000422 |
| Account No.(70% Account) | 5912869394 |
| State | Karnataka |
| Name | Bellad Dinesh Kumar |
| Address | No.27/1, 9th Main, ,R.M.V.Extn, Sadashivanagar |
| Pin Code | 560080 |
| Year Of Establishment | 2009 |
| Number of Project Completed | 25 |
| Reg. Of COA No. | CA/2007/40992 |
| Local Authority Licence Number | BCC/BL-3.6/STRL.E.87.10.11 |
| Promoter Type | Company |
| Name | Harish Babu |
| PAN Number | AALCA1121A |
| Address | No. 38, Maini Sadan, 2nd Floor, 7th Cross.Lavelle Road, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560001 |
| Company Registration No. | U45205KA2012PTC066826 |
| Type | Others |
| Pin Code | 560001 |
| Modification Applied On | 20-10-2021 |
| Modification Approved On | 19-04-2023 |
| Type of Inventory | DUPLEX |
| No of Inventory | 7 |
| Carpet Area (Sq Mtr) | 1001 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 234 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | 8 Units are added due to revised FAR by laws |
| Modified plan applied date | 31/05/2020 |
| Modified plan approved date | 23/02/2021 |
| Extend of the work carried out till date of registered project ( % ) | 61.0 |
| Extend of the work pending of registered project ( % ) | 39.0 |
| Total amount collected in respect of registered project ( INR ) | 358697152 |
| Total amount spent for the project ( INR ) | 557911632 |
| Total balance amount lying with the promoter ( INR ) | 0 |
| NOC | BSNL |
| SlNo. |
| Extension Applied On | 23-12-2023 |
| Extension Approved On | 05-02-2024 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/472/PR/240205/002177 |
| Proposed Project End Date at the time of registration | 03-01-2024 |
| Project End Date provided under Section 6 | 03-01-2025 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | 24 Points Checklist |
| 1 | Shortage of Labour |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 03-10-2018 | 28-02-2019 |
| 2 | Foundation footing work | Yes | 01-03-2019 | 02-05-2019 |
| 3 | Retaining wall (All types) | Yes | 03-03-2019 | 31-07-2019 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 26-06-2019 | 02-07-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 9 |
| 2 | 10 |
| 3 | 9 |
| 4 | 10 |
| 5 | 9 |
| 6 | 10 |
| 7 | 9 |
| 8 | 10 |
| 9 | 9 |
| 10 | 10 |
| 11 | 9 |
| 12 | 10 |
| 13 | 9 |
| 14 | 10 |
| 15 | 9 |
| Total No of Units | 142 |
| Project Start Date | 03-10-2018 |
| Project End Date | 03-01-2025 |
| If any extension of time has been granted | YES |
| Extended From Date | 03-01-2024 |
| Extended End Date | 03-01-2025 |
| Cost of land | 127069000 |
| Cost of construction | 746656084 |
| Total project cost | 873725084 |
| Total amount collected from buyers | 980004014 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 954663348 |
| Balance amount with the promoter | 25340666 |
| Total number of Flats/Apartments of the Project | 96 |
| Total number of Flats/Apartments sold | 96 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 11-06-2024 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |