Godrej Housing Projects LLP.,
Sy.No. 15/2, Hoodi Village, K.R. Puram Hobli, , Bangalore East Taluk, Bangalore
Approved
30th Mar 2019
Completed
30th Apr 2024
Registration No.
PRM/KA/RERA/1251/446/PR/190330/002517
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/190315/003130
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | GODREJ AIR NXT |
| Project Description | Sy.No. 15/2, Hoodi Village, K.R. Puram Hobli, Bangalore East Taluk, Bangalore |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 01-07-2019 |
| Proposed Project Completion Date | 30-04-2024 |
| Total Area Of Land (Sq Mtr) | 5261 |
| Total Coverd Area (Sq Mtr) | 1105 |
| Total Open Area (Sq Mtr) | 2678 |
| Estimated Cost of Construction (INR) | 729885982 |
| Cost of Land (INR) | 308101799 |
| Total Project Cost (INR) | 1037987781 |
| Project Address | Sy.No. 15/2, Hoodi Village, K.R. Puram Hobli, , Bangalore East Taluk, Bangalore |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 12 |
| Area of Parking for Sale (Sq Mtr) | 165 |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | Manekji Wadia Building |
| ifscCode | HDFC0000060 |
| Account No.(70% Account) | 57500000344110 |
| State | Karnataka |
| Name | Design Tree Service Consultants Pvt. Ltd., |
| Address | No. 7, Lakshmi Narashima Complex, 15th Cross,,100 Feet Ring Road, 4th Phase, JP Nagar, |
| Pin Code | 560078 |
| Year Of Establishment | 2008 |
| Number of Project Completed | 30 |
| Reg. Of COA No. | CA/2013/62254 |
| Local Authority Licence Number | U74200KA2008PTC045478 |
| Promoter Type | Other |
| Name | K. Ramaswamy |
| PAN Number | AANHG9969R |
| Address | Level-10, Prestige Obelisk, No. 3,.Kasturba Road, |
| District | Mumbai City |
| State/UT | Maharashtra |
| PIN Code | 400079 |
| Company Registration No. | AAD0883 |
| Type | Others |
| Pin Code | 560001 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 20-03-2019 | 21-08-2020 |
| 2 | Foundation footing work | Yes | 24-09-2019 | 22-01-2020 |
| 3 | Retaining wall (All types) | Yes | 15-03-2020 | 29-07-2020 |
| 4 | Plinth level Beam | Yes | 07-02-2020 | 10-04-2020 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 13-06-2020 | 26-06-2021 |
| 6 | Ground Clearance | Yes | 20-03-2019 | 22-08-2019 |
| 7 | Earth Excavation | Yes | 21-03-2019 | 21-12-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | https://www.godrejproperties.com/bangalore/residential/godrej-air-nxt/overview |
| FAR Sanctioned | 2.9989 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 7 |
| 2 | 7 |
| 3 | 7 |
| 4 | 7 |
| 5 | 7 |
| 6 | 7 |
| 7 | 7 |
| 8 | 7 |
| 9 | 7 |
| 10 | 7 |
| 11 | 7 |
| 12 | 7 |
| 13 | 7 |
| 14 | 7 |
| 15 | 7 |
| 16 | 2 |
| 17 | 2 |
| Total No of Units | 109 |
| Project Start Date | 01-07-2019 |
| Project End Date | 30-04-2024 |
| If any extension of time has been granted | NO |
| Cost of land | 308101799 |
| Cost of construction | 729885982 |
| Total project cost | 1037987781 |
| Total amount collected from buyers | 1116351582 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 961817808 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 109 |
| Total number of Flats/Apartments sold | 109 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 03-02-2023 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |