Godrej Home Constructions Private Limited
Sy.No. 18/1A and 22, Mallasandra Village, , Uttarahalli Village, Bangalore South Taluk, Bangalore
Approved
13th Oct 2017
Completed
15th Jan 2022
Registration No.
PRM/KA/RERA/1251/310/PR/171013/000233
Acknowledgement No.
PR/KN/170729/000233
Project Type
Residential/Group Housing
Approving Authority
BMRDA - Bangalore Metropolitan Region Development Authority
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Godrej Eternity |
| Project Description | Sy.No. 18/1A and 22, Mallasandra Village, Uttarahalli Village, Bangalore South Taluk, Bangalore |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 21-03-2016 |
| Proposed Project Completion Date | 15-01-2022 |
| Total Area Of Land (Sq Mtr) | 33037 |
| Total Coverd Area (Sq Mtr) | 12978 |
| Total Open Area (Sq Mtr) | 3303 |
| Estimated Cost of Construction (INR) | 1898800000 |
| Cost of Land (INR) | 708000000 |
| Total Project Cost (INR) | 2606600000 |
| Project Address | Sy.No. 18/1A and 22, Mallasandra Village, , Uttarahalli Village, Bangalore South Taluk, Bangalore |
| District | Pune |
| Taluk | Bengaluru South |
| Approving Authority | BMRDA - Bangalore Metropolitan Region Development Authority |
| No of Garage for Sale | 409 |
| Area of Garage for Sale (Sq Mtr) | 11108 |
| No of Parking for Sale | 43 |
| Area of Parking for Sale (Sq Mtr) | 774 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | Richmond Road Bangalore |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 57500000045080 |
| State | Maharashtra |
| Name | Viraj Projects (I) Pvt. Ltd., |
| Address | VTP House, 1st Floor, Behind Shakthi Sports, ,Wadgaonsheri, Pune |
| Pin Code | 411014 |
| Year Of Establishment | 2001 |
| Number of Project Completed | 30 |
| Reg. Of COA No. | Ca/96/20717 |
| Local Authority Licence Number | U74200KA2008PTC045478 |
| Number Of Project Completed | 75 |
| Promoter Type | Company |
| Name | Karan Bolaria |
| PAN Number | AAFCG9850L |
| Address | Godrej One, 5th Floor, Pirojshanagar,.Eastern Express Highway, Vikroli East, Mumbai |
| District | Mumbai City |
| State/UT | Maharashtra |
| PIN Code | 400079 |
| Company Registration No. | U70102MH2015PTC263486 |
| Type | Director |
| Pin Code | 400079 |
| Extension Applied On | 23-09-2020 |
| Extension Approved On | 19-02-2021 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/210219/000233 |
| Proposed Project End Date at the time of registration | 15-10-2020 |
| Project End Date provided under Section 6 | 15-10-2021 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | CC |
| 1 | Shortage of Labour |
| Document Name_1 | |
| Document Name_2 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 07-06-2016 | 29-09-2016 |
| 2 | Foundation footing work | Yes | 02-09-2016 | 31-03-2017 |
| 3 | Retaining wall (All types) | Yes | 12-12-2017 | 13-07-2018 |
| 4 | Plinth level Beam | Yes | 15-10-2016 | 20-08-2017 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No | ||
| 6 | Ground Clearance | Yes | 29-10-2016 | 07-08-2018 |
| 7 | Earth Excavation | Yes | 07-08-2016 | 31-12-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | https://www.godrejproperties.com/bangalore/residential/godrej-eternity/overview |
| FAR Sanctioned | 1.245 |
| Number of Towers | 7 |
| 0 | 17 |
| 1 | 17 |
| 2 | 17 |
| 3 | 17 |
| Total No of Units | 409 |
| Project Start Date | 21-03-2016 |
| Project End Date | 15-01-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 15-10-2020 |
| Extended End Date | 15-10-2021 |
| Cost of land | 708000000 |
| Cost of construction | 1898800000 |
| Total project cost | 2606600000 |
| Total amount collected from buyers | 2702108035 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 2766183189 |
| Balance amount with the promoter | -64075154 |
| Total number of Flats/Apartments of the Project | 409 |
| Total number of Flats/Apartments sold | 405 |
| Total number of Flats/Apartments Unsold | 4 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 16-12-2019 |
| Appeals / FNH | NO APPEALS / FNH |