Limited Liability Partnershio
S.No. 13/2, 14/1, 14/2, 15/1, 15/2, 16/1A, 16/1B, 16/2, 17/1 & 18/1, Maragondanahalli village, Jigni Hobli
Approved
20th Dec 2019
Completed
30th Dec 2025
Registration No.
PRM/KA/RERA/1251/308/PR/191220/003093
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/191126/003709
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | Godrej Nurture |
| Project Description | High Rise residential apartment |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 31-03-2020 |
| Proposed Project Completion Date | 30-12-2025 |
| Total Area Of Land (Sq Mtr) | 23321 |
| Total Coverd Area (Sq Mtr) | 3719 |
| Total Open Area (Sq Mtr) | 19602 |
| Estimated Cost of Construction (INR) | 2643800000 |
| Cost of Land (INR) | 312349967 |
| Total Project Cost (INR) | 2956149967 |
| Project Address | S.No. 13/2, 14/1, 14/2, 15/1, 15/2, 16/1A, 16/1B, 16/2, 17/1 & 18/1, Maragondanahalli village, Jigni Hobli |
| District | Chandigarh |
| Taluk | Anekal |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 116 |
| Area of Parking for Sale (Sq Mtr) | 1592 |
| Type of Inventory | 3 BHK Type 2A |
| No of Inventory | 12 |
| Carpet Area (Sq Mtr) | 1136SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 159SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | FORT , MUMBAI |
| ifscCode | HDFC0000060 |
| Account No.(70% Account) | 57500000414620 |
| State | Chandigarh |
| Name | Sanjeev Kumar Sharma |
| Address | Melior Structural Solutions Pvt Ltd,No 2174/2, Sector 38C |
| Pin Code | 160014 |
| Year Of Establishment | 2002 |
| Number of Project Completed | 50 |
| Reg. Of COA No. | CA/98/23290 |
| Local Authority Licence Number | M-140940-3 |
| Promoter Type | Other |
| Name | Siddharh Raman |
| PAN Number | AARFG0012D |
| Address | Level 10, Prestige Obelisk, No.3 .Kasturba Road |
| District | Mumbai City |
| State/UT | Maharashtra |
| PIN Code | 400079 |
| Company Registration No. | AAJ2172 |
| Type | Others |
| Pin Code | 560001 |
| Type of Inventory | 3 BHK Type 2A |
| No of Inventory | 12 |
| Carpet Area (Sq Mtr) | 1136 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 159 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-08-2020 | 16-12-2020 |
| 2 | Foundation footing work | Yes | 14-11-2020 | 03-03-2021 |
| 3 | Retaining wall (All types) | Yes | 21-01-2021 | 31-01-2022 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 10-04-2023 | 07-09-2023 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.25 |
| Number of Towers | 7 |
| 0 | 0 |
| 1 | 10 |
| 2 | 10 |
| 3 | 10 |
| 4 | 10 |
| 5 | 10 |
| 6 | 10 |
| 7 | 10 |
| 8 | 10 |
| 9 | 10 |
| 10 | 10 |
| 11 | 10 |
| 12 | 10 |
| 13 | 10 |
| 14 | 10 |
| 15 | 10 |
| 16 | 10 |
| 17 | 10 |
| 18 | 10 |
| 19 | 10 |
| 20 | 9 |
| 21 | 10 |
| Total No of Units | 684 |
| Project Start Date | 31-03-2020 |
| Project End Date | 30-12-2025 |
| If any extension of time has been granted | NO |
| Cost of land | 312349967 |
| Cost of construction | 2643800000 |
| Total project cost | 2956149967 |
| Total amount collected from buyers | 3808863188 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 3267707215 |
| Balance amount with the promoter | 541155973 |
| Total number of Flats/Apartments of the Project | 684 |
| Total number of Flats/Apartments sold | 675 |
| Total number of Flats/Apartments Unsold | 9 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 28-12-2022 |
| Appeals / FNH | NO APPEALS / FNH |