GP Aditya
VIJAYA LAKSHMI CONSTRUCTIONS
Sy No.6 Site No. 148,149 & 150 Sreenivagilu ,, Amanikere Village, Begur Hobli,
Approved
26th Jun 2019
Completed
30th Dec 2023
Registration No.
PRM/KA/RERA/1251/310/PR/190626/002629
Acknowledgement No.
ACK/KA/RERA/1251/310/PR/190403/003193
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
Project Details
| Project Name | GP Aditya |
| Project Description | residential apartments |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-03-2019 |
| Proposed Project Completion Date | 30-12-2023 |
| Total Area Of Land (Sq Mtr) | 1672 |
| Total Coverd Area (Sq Mtr) | 456 |
| Total Open Area (Sq Mtr) | 1216 |
| Estimated Cost of Construction (INR) | 302590000 |
| Cost of Land (INR) | 100184550 |
| Total Project Cost (INR) | 402774550 |
| Project Address | Sy No.6 Site No. 148,149 & 150 Sreenivagilu ,, Amanikere Village, Begur Hobli, |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | RESIDENTIAL APARTMENT 3 BHK 22 2 BHK 22 |
| No of Inventory | 44 |
| Carpet Area (Sq Mtr) | 3645SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1074SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | KORAMANGALA 1ST BLOCK BRANCH |
| ifscCode | HDFC0004460 |
| Account No.(70% Account) | 57500000433249 |
| State | Karnataka |
Promoter Details
| Promoter Type | Partnership Firm |
| Name | Prasanth Parandham Nag Gorantla |
| PAN Number | AAD******* |
| Address | 8-2-801/B/301,Road No.10,.Banjara Hill, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560064 |
| Company Registration No. | 29AADFV1680L1ZP |
| Type | Others |
| Pin Code | 500034 |
Modification Plan Details
| Modification Applied On | 10-03-2021 |
| Modification Approved On | 03-02-2022 |
| Type of Inventory | RESIDENTIAL APARTMENT 3 BHK 22 2 BHK 22 |
| No of Inventory | 44 |
| Carpet Area (Sq Mtr) | 3645 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1074 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | WE HAVE MODIFIED THE PLAN AS WE HAVE BOUGHT TDR |
| Modified plan applied date | 04/11/2019 |
| Modified plan approved date | 05/06/2020 |
| Extend of the work carried out till date of registered project ( % ) | 50.0 |
| Extend of the work pending of registered project ( % ) | 50.0 |
| Total amount collected in respect of registered project ( INR ) | 3800000 |
| Total amount spent for the project ( INR ) | 200489586 |
| Total balance amount lying with the promoter ( INR ) | 105384 |
| NOC | Fire force Departement |
| SlNo. |
Extension Details
| Extension Applied On | 23-01-2023 |
| Extension Approved On | 25-04-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/230425/002629 |
| Proposed Project End Date at the time of registration | 30-12-2022 |
| Project End Date provided under Section 6 | 30-12-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | Shortage of Building Materials, Concrete, Jalli etc |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-04-2019 | 30-06-2019 |
| 2 | Foundation footing work | Yes | 10-04-2019 | 05-07-2019 |
| 3 | Retaining wall (All types) | Yes | 01-04-2019 | 25-07-2019 |
| 4 | Plinth level Beam | Yes | 01-05-2019 | 25-07-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-07-2019 | 10-11-2019 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
Post Registration Details
| WebSite Link 1 | www.gpinfra.com |
| Agent Registration No 1 | NA |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 0 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 4 |
| 11 | 4 |
| 12 | 4 |
| Total No of Units | 44 |
Completion Details
| Project Start Date | 01-03-2019 |
| Project End Date | 30-12-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-12-2022 |
| Extended End Date | 30-12-2023 |
| Cost of land | 100184550 |
| Cost of construction | 302590000 |
| Total project cost | 402774550 |
| Total amount collected from buyers | 356004197 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 378452624 |
| Balance amount with the promoter | 99039583 |
| Total number of Flats/Apartments of the Project | 44 |
| Total number of Flats/Apartments sold | 6 |
| Total number of Flats/Apartments Unsold | 38 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 16-01-2024 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in