Happy Valley Developers
112-113 HAPPY VALLEY LAYOUT, 4TH MAIN, 4TH CROSS, UTTARAHALLI, BSK 5TH STAGE
Approved
30th Jan 2018
Completed
31st Aug 2017
Registration No.
PRM/KA/RERA/1251/310/PR/180130/002142
Acknowledgement No.
PR/KN/170926/002142
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | HAPPY VALLEY PEARL |
| Project Description | 2BHK, 3BHK FLTS AND 3 BHK PENTHOUSES |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 25-10-2013 |
| Proposed Project Completion Date | 31-08-2017 |
| Total Area Of Land (Sq Mtr) | 2317 |
| Total Coverd Area (Sq Mtr) | 1197 |
| Total Open Area (Sq Mtr) | 1120 |
| Estimated Cost of Construction (INR) | 250000000 |
| Cost of Land (INR) | 90000000 |
| Total Project Cost (INR) | 340000000 |
| Project Address | 112-113 HAPPY VALLEY LAYOUT, 4TH MAIN, 4TH CROSS, UTTARAHALLI, BSK 5TH STAGE |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 49 |
| Area of Garage for Sale (Sq Mtr) | 674 |
| No of Parking for Sale | 16 |
| Area of Parking for Sale (Sq Mtr) | 220 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| RAMPS | Self Development |
| Bank Name | STATE BANK OF INDIA |
| Branch | RAMANASHREE ARCADE BSK 2ND STAGE |
| ifscCode | SBIN0040463 |
| Account No.(70% Account) | 54018413532 |
| State | Karnataka |
| Name | PLANOTECH CONSULTANTS & CONTRACTORS |
| Address | #519, Ground Floor, 10th Main, ,11th cross, Railwaymen’s Bhavani Nagar Layout, PH-1, Mallathahalli, |
| Pin Code | 560056 |
| Year Of Establishment | 1997 |
| Number of Project Completed | 25 |
| Reg. Of COA No. | 1809 |
| Local Authority Licence Number | 26590103 |
| Number Of Project Completed | 20 |
| Firm Type | Individual |
| Name | Happy Valley Developers |
| Father's Name | Madan N Baldota |
| PAN Number | AAAAH1868A |
| Address | 112-113, HAPPY VALLEY LAYOUT, 4TH MAIN 4TH CROSS,,UTTARAHALLI, BSK 5TH STAGE |
| State/UT | Karnataka |
| PIN Code | 560061 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-09-2014 | 14-01-2015 |
| 2 | Foundation footing work | Yes | 15-01-2015 | 15-03-2015 |
| 3 | Retaining wall (All types) | Yes | 16-03-2015 | 15-06-2015 |
| 4 | Plinth level Beam | Yes | 16-06-2015 | 15-09-2015 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 16-09-2015 | 15-12-2015 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | http://www.happyvalleyindia.com/apartments.html |
| FAR Sanctioned | 5395.0 |
| Number of Towers | 1 |
| 0 | 8 |
| 1 | 8 |
| 2 | 8 |
| 3 | 4 |
| 4 | 4 |
| Total No of Units | 32 |
| Project Start Date | 25-10-2013 |
| Project End Date | 31-08-2017 |
| If any extension of time has been granted | NO |
| Cost of land | 90000000 |
| Cost of construction | 250000000 |
| Total project cost | 340000000 |
| Total amount collected from buyers | 180000000 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 320000000 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 32 |
| Total number of Flats/Apartments sold | 22 |
| Total number of Flats/Apartments Unsold | 10 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 28-01-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |