Helio at Brigade El Dorado

Brigade Tetrarch Private Limited

Plot No. R-8, Sy No: 177 (P) of Bagluru Village (Hardware Sector) Hitech, Defence & Aerospace Park, , Industrial Area, Jala Hobli,

Approved

13th Sept 2019

Completed

30th Sept 2024

Registration No.

PRM/KA/RERA/1251/472/PR/190913/002889

Acknowledgement No.

ACK/KA/RERA/1251/472/PR/190829/003525

Project Type

Residential/Group Housing

Approving Authority

KIADB - Karnataka Industrial Areas Development Board

District

Bengaluru Urban

Taluka

Yelahanka

State

Karnataka

Project Details

Project NameHelio at Brigade El Dorado
Project DescriptionResidential Development
Project TypeResidential/Group Housing
Project StatusNew Project Launch
Project Start Date29-08-2019
Proposed Project Completion Date30-09-2024
Total Area Of Land (Sq Mtr)17942
Total Coverd Area (Sq Mtr)2369
Total Open Area (Sq Mtr)15573
Estimated Cost of Construction (INR)1950000000
Cost of Land (INR)143332751
Total Project Cost (INR)2093332751
Project AddressPlot No. R-8, Sy No: 177 (P) of Bagluru Village (Hardware Sector) Hitech, Defence & Aerospace Park, , Industrial Area, Jala Hobli,
DistrictBengaluru Urban
TalukYelahanka
Approving AuthorityKIADB - Karnataka Industrial Areas Development Board
No of Garage for Sale480
Area of Garage for Sale (Sq Mtr)6600
No of Parking for Sale95
Area of Parking for Sale (Sq Mtr)1306
Type of Inventory3 BEDROOM + 2 TOILET
No of Inventory237
Carpet Area (Sq Mtr)58SqMtr
Area of exclusive balcony/verandah (Sq Mtr)1SqMtr
Area of exclusive open terrace if any (Sq Mtr)0SqMtr
Road SystemSelf Development
Water SupplySelf Development
Sewege and Drainage SystemSelf Development
Electricity Supply Transformer And Sub StationSelf Development
Solid Waste Management And DisposalSelf Development
Fire Fighting facilitySelf Development
Drinking Water FacilitySelf Development
Emergency Evacuation ServicesSelf Development
Use of Renewable EnergySelf Development
Bank NameHDFC
BranchKasturba Road
ifscCodeHDFC0000009
Account No.(70% Account)50200043699725
StateKarnataka
NameN.N.Nagendra Kumar
AddressSterling Engineering Consultancy Services Pvt. Ltd.,1307 Brigade Towers, 135 Brigade Road
Pin Code560025
Year Of Establishment1983
Number of Project Completed16
Reg. Of COA No.CA/2010/47015
Local Authority Licence NumberBCC/BL-3.2.3E-248/86-87

Promoter Details

Promoter TypeCompany
NameViswa Prathap Desu
PAN NumberAAACT7266Q
Address29th & 30th Floor, World Trade Center, Brigade Gateway Campus , 26/1, Dr. Rajkumar Road, Malleswaram-Rajajinagar
DistrictBengaluru Urban
State/UTKarnataka
PIN Code560055
Company Registration No.U92412KA1995PTC018247

Modification Plan Details

Modification Applied On13-05-2024
Modification Approved On21-09-2024
Type of Inventory3 BEDROOM + 2 TOILET
No of Inventory237
Carpet Area (Sq Mtr)58 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)1 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr
Details of Modification of plan sanction / layout brief descriptionBrigade obtained NOCs from all the concerned departments/ authorities for the construction of the said project and accordingly, KIADB issued building plan sanction vide No. KIADB/DO-3&EE/457/2019-20 dated 22.08.2019, thereby permitting Brigade to construct 1 Basement + Ground + 24 Upper Floors for Helio Block. Subsequently, considering that the project is in close proximity to Yelahanka Airbase, in the interest of the project at large, Brigade applied to the authorities to seek their approval for height, though that was not part of mandatory requirements of the approval authority, i.e., KIADB. Thereafter, Brigade received response from the authorities giving clearances for heights lower than what was previously approved by KIADB with height restriction. In view of imposition of height restriction, Brigade sought for revised plan sanction before KIADB. Accordingly, KIADB issued the revised building plan sanction on 12.01.2024. By virtue of which the Helio block is being modified to reduce the floors from 1 Basement + Ground + 24 Upper Floors to 1 Basement + Ground + 21 Upper Floors and slight variations in the typology of the units, thus resulting in slight changes in areas of the apartment/ units to match the requirements of the Project. Apart from the above, there are no other changes in the said project.
Modified plan applied date07/07/2023
Modified plan approved date12/01/2024
Extend of the work carried out till date of registered project ( % )88.0
Extend of the work pending of registered project ( % )12.0
Total amount collected in respect of registered project ( INR )1928714865
Total amount spent for the project ( INR )1477087427
Total balance amount lying with the promoter ( INR )0
NOCAir Port Authority
SlNo.

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes01-11-201928-05-2020
2Foundation footing workYes11-12-201913-06-2020
3Retaining wall (All types)Yes26-12-201910-07-2020
4Plinth level BeamNo
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)Yes08-08-202016-10-2020

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsYes
3Sewage and Drainage SystemYes
4Parks & Tree plantingYes
5Street LightingNo
6Provision for community buildings and for treatment and disposal of sewage and sullage waterYes
7Solid waste management and disposalYes
8Water conservationNo
9Energy managementYes
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesNo

Post Registration Details

FAR Sanctioned0.21
Number of Towers1
04
119
219
321
421
526
626
726
826
926
1026
1126
1226
1326
1426
1526
1626
1726
1826
1926
2024
2126
Total No of Units524

Completion Details

Project Start Date29-08-2019
Project End Date30-09-2024
If any extension of time has been grantedNO
Cost of land143332751
Cost of construction1950000000
Total project cost2093332751
Total amount collected from buyers2002530450
Whether any loan has been raisedNO
Total amount spent for completion of the project1534496164
Balance amount with the promoter0
Total number of Flats/Apartments of the Project524
Total number of Flats/Apartments sold524
Total number of Flats/Apartments Unsold0
Whether the project has been completed within the stipulated Period?YES
Whether there is any Change in inventory list or specification?YES
As built drawing approved by the planning AuthorityYES
Occupancy certificate received?YES
Occupancy certificate received date10-02-2023

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH

Top Properties in Mangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy