Kumar Properties Pvt Ltd
Site No. 214 Nataka Rathna Gubbiveerana Road, , Subedar Chattram Road,Nehru Nagar, Sheshadripuram, Bangalore-560020
Approved
15th Sept 2017
Completed
30th Sept 2022
Registration No.
PRM/KA/RERA/1251/309/PR/170915/000222
Acknowledgement No.
PR/KN/170728/000222
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
| Project Name | Kumar Kino Platinum |
| Project Description | Basement + Ground + 10 upper floors |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 01-03-2017 |
| Proposed Project Completion Date | 30-09-2022 |
| Total Area Of Land (Sq Mtr) | 3277 |
| Total Coverd Area (Sq Mtr) | 798 |
| Total Open Area (Sq Mtr) | 1262 |
| Estimated Cost of Construction (INR) | 267000000 |
| Cost of Land (INR) | 388033504 |
| Total Project Cost (INR) | 655033504 |
| Project Address | Site No. 214 Nataka Rathna Gubbiveerana Road, , Subedar Chattram Road,Nehru Nagar, Sheshadripuram, Bangalore-560020 |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 14 |
| Area of Parking for Sale (Sq Mtr) | 175 |
| Extent of development carried till date | 9 % |
| Extent of development pending | 91 % |
| Total amount of money collected from allottee | 0 |
| Total amount of money used for development of project | 43220458 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | 3 and 4 BHK |
| No of Inventory | 38 |
| Carpet Area (Sq Mtr) | 5865SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 463SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 195SqMtr |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| Bank Name | KOTAK MAHINDRA BANK |
| Branch | East street, Pune |
| ifscCode | KKBK0000721 |
| Account No.(70% Account) | 4545356158 |
| State | Karnataka |
| Name | SRI UMIYA CONSTRUCTION AND CO |
| Address | #165,7th Cross,Nobo Nagar,Bannerghatta Road,Bangalore-560076 |
| Pin Code | 560076 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 200 |
| Reg. Of COA No. | CA/97/22232 |
| Local Authority Licence Number | PMC 46 |
| Number Of Project Completed | 20 |
| Promoter Type | Company |
| Name | HITESH KEWALKUMAR JAIN |
| PAN Number | AABCK8464E |
| Address | Sr No 11/1A, CTS 214, Dhankawadi |
| District | Pune |
| State/UT | Maharashtra |
| PIN Code | 560001 |
| Company Registration No. | U70101MH2000PTC216236 |
| Type | Director |
| Pin Code | 411043 |
| Project Name | Kumar Panchsheel |
| Project Description | Residential |
| Current Status | Completed |
| Type of Land | Residential |
| Type of Inventory | 3 and 4 BHK |
| No of Inventory | 38 |
| Carpet Area (Sq Mtr) | 5865 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 463 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 195 Sq Mtr |
| Extension Applied On | 30-09-2021 |
| Extension Approved On | 11-07-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/309/PR/220711/000222 |
| Proposed Project End Date at the time of registration | 30-09-2021 |
| Project End Date provided under Section 6 | 30-09-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | BOARD RESOLUTION |
| 1 | Shortage of Building Materials, Concrete, Jalli etc |
| 2 | Shortage of Labour |
| 3 | Awaiting Approvals |
| 4 | Awaiting OC |
| Document Name_1 | |
| Document Name_2 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 17-10-2017 | 30-11-2017 |
| 2 | Foundation footing work | Yes | 15-12-2017 | 30-03-2018 |
| 3 | Retaining wall (All types) | Yes | 10-12-2018 | 20-02-2019 |
| 4 | Plinth level Beam | Yes | 15-12-2017 | 15-04-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 20-12-2017 | 25-04-2018 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | www.kumarworld.com |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 4 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 2 |
| Total No of Units | 38 |
| Project Start Date | 01-03-2017 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2021 |
| Extended End Date | 30-09-2022 |
| Cost of land | 388033504 |
| Cost of construction | 267000000 |
| Total project cost | 655033504 |
| Total amount collected from buyers | 257127673 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 655033504 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 38 |
| Total number of Flats/Apartments sold | 23 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 21-03-2022 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate
News, Infographics, Blogs & More! Delivered to your inbox.