PCOC Eastland Structures LLP
No 88 and 89 Shanthinagar HBCS Layout , Srinuvagilu Amanikere Village Begur Hobli
Approved
23rd Dec 2017
Completed
31st Dec 2019
Registration No.
PRM/KA/RERA/1251/310/PR/171223/001579
Acknowledgement No.
PR/KN/170831/001579
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | LANAI By PCOC |
| Project Description | Residential Apartments |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-09-2016 |
| Proposed Project Completion Date | 31-12-2019 |
| Total Area Of Land (Sq Mtr) | 941 |
| Total Coverd Area (Sq Mtr) | 340 |
| Total Open Area (Sq Mtr) | 601 |
| Estimated Cost of Construction (INR) | 120000000 |
| Cost of Land (INR) | 84348500 |
| Total Project Cost (INR) | 204348500 |
| Project Address | No 88 and 89 Shanthinagar HBCS Layout , Srinuvagilu Amanikere Village Begur Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 15 |
| No of Inventory | 15 |
| Carpet Area (Sq Mtr) | 2065SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 287SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 104SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | ICICI Bank |
| Branch | LANGFORD ROAD |
| ifscCode | ICIC0000269 |
| Account No.(70% Account) | 026905005314 |
| State | Karnataka |
| Name | BILDVEL CORPORATION |
| Address | No 2532, 27th Cross, 22nd Main,Banashankari 2nd Stage |
| Pin Code | 560070 |
| Year Of Establishment | 2008 |
| Number of Project Completed | 20 |
| Reg. Of COA No. | CA/205/68084 |
| Local Authority Licence Number | BCC/BL-3.6/STR.ENGG/95/2011-12 |
| Number Of Project Completed | 0 |
| Promoter Type | Other |
| Name | Hasaan Kadli |
| PAN Number | AASFP4034H |
| Address | 101, Landmark Plaza, .299, Langford Road, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560025 |
| Company Registration No. | AAG 1088 |
| Type | Others |
| Pin Code | 560025 |
| Type of Inventory | 15 |
| No of Inventory | 15 |
| Carpet Area (Sq Mtr) | 2065 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 287 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 104 Sq Mtr |
| Extension Applied On | 28-11-2018 |
| Extension Approved On | 03-01-2020 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/200103/001579 |
| Proposed Project End Date at the time of registration | 31-12-2018 |
| Project End Date provided under Section 6 | 31-12-2019 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | Financial crunch |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-07-2015 | 15-08-2015 |
| 2 | Foundation footing work | Yes | 20-08-2015 | 25-10-2015 |
| 3 | Retaining wall (All types) | Yes | 20-10-2015 | 20-11-2015 |
| 4 | Plinth level Beam | Yes | 20-12-2015 | 02-02-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 20-01-2016 | 03-03-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.pcoc.in |
| FAR Sanctioned | 918.0 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 1 |
| 2 | 2 |
| 3 | 2 |
| 4 | 2 |
| 5 | 2 |
| 6 | 2 |
| 7 | 2 |
| 8 | 2 |
| Total No of Units | 15 |
| Project Start Date | 01-09-2016 |
| Project End Date | 31-12-2019 |
| If any extension of time has been granted | YES |
| Extended From Date | 31-12-2018 |
| Extended End Date | 31-12-2019 |
| Cost of land | 84348500 |
| Cost of construction | 120000000 |
| Total project cost | 204348500 |
| Total amount collected from buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 183399632 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 15 |
| Total number of Flats/Apartments sold | 0 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | NO |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 22-02-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |