NARYA 5 ELEMENTS

Narya Constructions and Developers

Sy.No.10/2,Belthur Village, , Bidarahalli Hobli,

Approved

14th Dec 2017

Completed

28th Feb 2021

Registration No.

PRM/KA/RERA/1251/446/PR/171214/001859

Acknowledgement No.

PR/KN/170831/001859

Project Type

Residential/Group Housing

Approving Authority

BBMP - Bruhat Bengaluru Mahanagara Palike

District

Bengaluru Urban

Taluka

Bengaluru East

State

Karnataka

Project Details

Project NameNARYA 5 ELEMENTS
Project DescriptionRESIDENTIAL APARTMENTS 139 units at Sy.No.10/2,Belthur Village, Bidarahalli Hobli, Bangalore -560067
Project TypeResidential/Group Housing
Project StatusNew Project Launch
Project Start Date01-06-2017
Proposed Project Completion Date28-02-2021
Total Area Of Land (Sq Mtr)6376
Total Coverd Area (Sq Mtr)13368
Total Open Area (Sq Mtr)3159
Estimated Cost of Construction (INR)323642376
Cost of Land (INR)105174531
Total Project Cost (INR)428816907
Project AddressSy.No.10/2,Belthur Village, , Bidarahalli Hobli,
DistrictBengaluru Urban
TalukBengaluru East
Approving AuthorityBBMP - Bruhat Bengaluru Mahanagara Palike
No of Garage for Sale0
Area of Garage for Sale (Sq Mtr)0
No of Parking for Sale0
Area of Parking for Sale (Sq Mtr)0
Type of InventoryApartments
No of Inventory139
Carpet Area (Sq Mtr)11276SqMtr
Area of exclusive balcony/verandah (Sq Mtr)0SqMtr
Area of exclusive open terrace if any (Sq Mtr)137SqMtr
Road SystemLocal Authority
Water SupplyLocal Authority
Sewege and Drainage SystemSelf Development
Electricity Supply Transformer And Sub StationSelf Development
Solid Waste Management And DisposalLocal Authority
Fire Fighting facilityLocal Authority
Drinking Water FacilitySelf Development
Emergency Evacuation ServicesSelf Development
Use of Renewable EnergySelf Development
Bank NameKarnataka Bank Ltd.
BranchCHANNASANDRA
ifscCodeKARB0000952
Account No.(70% Account)9522000100016801
StateKarnataka
NameDineesha Contracts
AddressBangalore,Bangalore
Pin Code560084
Year Of Establishment2015
Number of Project Completed10
Reg. Of COA No.222253532
Local Authority Licence Number80234 18378
Number Of Project Completed10

Promoter Details

Promoter TypePartnership Firm
NameK Indusekhar
PAN NumberAAMFN8431C
AddressNo 1150,Bangarumita Avilala ,tirupathi Rural,.Chittoor Andhra Pradesh
DistrictBengaluru Urban
State/UTKarnataka
PIN Code560041
Company Registration No.FirmJNR116201617
TypeOthers
Pin Code517501

Modification Plan Details

Type of InventoryApartments
No of Inventory139
Carpet Area (Sq Mtr)11276 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)137 Sq Mtr

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes19-02-201707-03-2017
2Foundation footing workYes22-03-201717-06-2017
3Retaining wall (All types)Yes22-03-201715-04-2017
4Plinth level BeamNo
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)Yes26-07-201717-11-2017

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsYes
3Sewage and Drainage SystemYes
4Parks & Tree plantingYes
5Street LightingNo
6Provision for community buildings and for treatment and disposal of sewage and sullage waterNo
7Solid waste management and disposalNo
8Water conservationNo
9Energy managementNo
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesNo

Post Registration Details

FAR Sanctioned2.24
Number of Towers2
012
112
212
312
412
Total No of Units139

Completion Details

Project Start Date01-06-2017
Project End Date28-02-2021
If any extension of time has been grantedNO
Cost of land105174531
Cost of construction323642376
Total project cost428816907
Total amount collected from buyers170176747
Whether any loan has been raisedNO
Total amount spent for completion of the project306920467
Balance amount with the promoter0
Total number of Flats/Apartments of the Project139
Total number of Flats/Apartments sold49
Total number of Flats/Apartments Unsold90
Whether the project has been completed within the stipulated Period?YES
Whether there is any Change in inventory list or specification?NO
As built drawing approved by the planning AuthorityYES
Occupancy certificate received?YES
Occupancy certificate received date26-04-2019

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH
Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy