M/S NAVA JYOTHI SHELTERS PRIVATE LIMITED
Survey No.124/1, Banasawadi Village,, (B.Channasandra) K R Puram Hobli, Bangalore East Taluk, Bangalore
Approved
31st Jul 2019
Completed
30th Sept 2021
Registration No.
PRM/KA/RERA/1251/446/PR/190731/002752
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/190611/003354
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | NAVA SUBHA SAMRUDDHI |
| Project Description | Residential Apartments Constructed on 25 Guntas |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-06-2019 |
| Proposed Project Completion Date | 30-09-2021 |
| Total Area Of Land (Sq Mtr) | 2530 |
| Total Coverd Area (Sq Mtr) | 1392 |
| Total Open Area (Sq Mtr) | 1138 |
| Estimated Cost of Construction (INR) | 170000000 |
| Cost of Land (INR) | 220000000 |
| Total Project Cost (INR) | 390000000 |
| Project Address | Survey No.124/1, Banasawadi Village,, (B.Channasandra) K R Puram Hobli, Bangalore East Taluk, Bangalore |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 6 |
| Area of Parking for Sale (Sq Mtr) | 82 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | Axis Bank |
| Branch | Ramamurthy Nagar |
| ifscCode | UTIB0003569 |
| Account No.(70% Account) | 918020062316992 |
| State | Karnataka |
| Name | G .Chinnanarasanna |
| Address | Survey No.124/1, Banasawadi Village, (B.Channasandra) K R Puram Hobli,, Bangalore East Taluk, Bangalore |
| Pin Code | 560043 |
| Year Of Establishment | NA |
| Number of Project Completed | NA |
| Reg. Of COA No. | BCC/BL-3.6/E-4350/2018-19 |
| Local Authority Licence Number | BCC/BL-3.6/SE-0315/2019-20 |
| Number Of Project Completed | NA |
| Promoter Type | Company |
| Name | Mr.K.MURALI BABU |
| PAN Number | AAFCN1496D |
| Address | No.581/A, 7th Main, NRI Layout, Ramamurthy Nagar Bangalore , No.581/A, 7th Main, NRI Layout, Ramamurthy Nagar Bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560016 |
| Company Registration No. | U45205KA2016PTC085448 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-08-2019 | 31-08-2019 |
| 2 | Foundation footing work | Yes | 05-08-2019 | 31-08-2019 |
| 3 | Retaining wall (All types) | Yes | 01-07-2019 | 30-07-2019 |
| 4 | Plinth level Beam | Yes | 11-09-2019 | 10-10-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 20-10-2019 | 25-10-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 14 |
| 1 | 14 |
| 2 | 14 |
| 3 | 14 |
| Total No of Units | 56 |
| Project Start Date | 01-06-2019 |
| Project End Date | 30-09-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 220000000 |
| Cost of construction | 170000000 |
| Total project cost | 390000000 |
| Total amount collected from buyers | 152148809 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 152148809 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 28 |
| Total number of Flats/Apartments sold | 28 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 29-08-2023 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate