Bhartiya Urban Private Limited
Bhartiya City, Khatha No.6/1, Chokkanahalli Village, Yelahanka Zone
Approved
14th Oct 2017
Completed
30th Mar 2023
Registration No.
PRM/KA/RERA/1251/309/PR/171014/000188
Acknowledgement No.
PR/KN/170729/000188
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru North
State
Karnataka
| Project Name | Nikoo Homes II West |
| Project Description | Residential apartment complex with 3 towers and 913 units |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 31-08-2015 |
| Proposed Project Completion Date | 30-03-2023 |
| Total Area Of Land (Sq Mtr) | 24440 |
| Total Coverd Area (Sq Mtr) | 9993 |
| Total Open Area (Sq Mtr) | 14447 |
| Estimated Cost of Construction (INR) | 4880000000 |
| Cost of Land (INR) | 498600000 |
| Total Project Cost (INR) | 5379900000 |
| Project Address | Bhartiya City, Khatha No.6/1, Chokkanahalli Village, Yelahanka Zone |
| District | Bengaluru Urban |
| Taluk | Bengaluru North |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 60 |
| Area of Parking for Sale (Sq Mtr) | 825 |
| Extent of development carried till date | 19 % |
| Extent of development pending | 81 % |
| Total amount of money collected from allottee | 278200000 |
| Total amount of money used for development of project | 1010400000 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | Yes |
| Reason For Delay | Encountered hard rocks during excavation |
| No of Month Delay | 20 |
| Expected Completion Date | Thu Jun 30 00:00:00 IST 2022 |
| Type of Inventory | as per annexure |
| No of Inventory | 0 |
| Carpet Area (Sq Mtr) | 0SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| BWSSB | Local Authority |
| BESCOM | Local Authority |
| Bank Name | Bank of Baroda |
| Branch | K G Road Main Branch |
| ifscCode | BARB0BANGAL |
| Account No.(70% Account) | 05190200001475 |
| State | Karnataka |
| Name | Urbanac Projects Pvt Ltd |
| Address | 3rd Floor, ,4th Main, Hebbal |
| Pin Code | 560024 |
| Year Of Establishment | 2008 |
| Number of Project Completed | NA |
| Reg. Of COA No. | NA |
| Local Authority Licence Number | NA |
| Number Of Project Completed | NA |
| Promoter Type | Company |
| Name | Arjun Aggarwal |
| PAN Number | AAACZ3571A |
| Address | Bhartiya City, Khatha No.6/2, Chokkanahalli Village, Yelahanka Zone |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560025 |
| Company Registration No. | U45200TN2008PTC103956 |
| Type | Director |
| Pin Code | 560064 |
| Project Name | Nikoo Homes I |
| Project Description | Residential apartment complex with 10 towers with 2415 units |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 29-07-2017 |
| Type of Inventory | as per annexure |
| No of Inventory | 0 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 21-04-2016 | 24-08-2018 |
| 2 | Foundation footing work | Yes | 25-12-2017 | 05-11-2018 |
| 3 | Retaining wall (All types) | Yes | 31-01-2018 | 15-05-2019 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 25-12-2017 | 15-05-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.NIKOO-HOMES.COM |
| FAR Sanctioned | 5.14 |
| Number of Towers | 3 |
| 0 | 0 |
| 1 | 9 |
| 2 | 9 |
| 3 | 11 |
| 4 | 11 |
| 5 | 11 |
| 6 | 11 |
| 7 | 11 |
| 8 | 11 |
| 9 | 11 |
| 10 | 10 |
| 11 | 10 |
| 12 | 10 |
| 13 | 10 |
| 14 | 11 |
| 15 | 11 |
| 16 | 11 |
| 17 | 11 |
| 18 | 11 |
| 19 | 10 |
| 20 | 10 |
| 21 | 10 |
| 22 | 10 |
| 23 | 11 |
| 24 | 11 |
| 25 | 11 |
| 26 | 11 |
| 27 | 11 |
| 28 | 10 |
| 29 | 10 |
| 30 | 10 |
| 31 | 10 |
| 32 | 0 |
| 33 | 0 |
| Total No of Units | 913 |
| Project Start Date | 31-08-2015 |
| Project End Date | 30-03-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 498600000 |
| Cost of construction | 4880000000 |
| Total project cost | 5379900000 |
| Total amount collected from buyers | 6791700000 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 6465400000 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 913 |
| Total number of Flats/Apartments sold | 905 |
| Total number of Flats/Apartments Unsold | 8 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 12-07-2022 |
| Appeals / FNH | NO APPEALS / FNH |