GR CONSTRUCTIONS
Sy no:77/4 & 77/5, choodasandra Village, Sarjapura Hobli, Anekal Taluk, Bangalore, Sy no:77/4 & 77/5, choodasandra Village, Sarjapura Hobli, Anekal Taluk, Bangalore
Approved
19th Mar 2018
Completed
30th Aug 2022
Registration No.
PRM/KA/RERA/1251/308/PR/180319/002414
Acknowledgement No.
PR/KN/171117/002414
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | ONE&ONLY (Phase 1 of GR Santhrupthi) |
| Project Description | 1 acre 26.04 Guntas with 45 row villas |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-12-2017 |
| Proposed Project Completion Date | 30-08-2022 |
| Total Area Of Land (Sq Mtr) | 6500 |
| Total Coverd Area (Sq Mtr) | 3197 |
| Total Open Area (Sq Mtr) | 3303 |
| Estimated Cost of Construction (INR) | 480000000 |
| Cost of Land (INR) | 20638903 |
| Total Project Cost (INR) | 660000000 |
| Project Address | Sy no:77/4 & 77/5, choodasandra Village, Sarjapura Hobli, Anekal Taluk, Bangalore, Sy no:77/4 & 77/5, choodasandra Village, Sarjapura Hobli, Anekal Taluk, Bangalore |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 45 |
| Area of Garage for Sale (Sq Mtr) | 1125 |
| No of Parking for Sale | 9 |
| Area of Parking for Sale (Sq Mtr) | 112 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | SYNDICATE BANK |
| Branch | Kumara swamy Layout |
| ifscCode | SYNB0000684 |
| Account No.(70% Account) | 06841010001010 |
| State | Karnataka |
| Name | CIVITECH DESIGNS |
| Address | #186E,GROUND FLOOR,5 th MAIN ROAD,ST BED LAYOUT, 4 th BLOCK, KORAMANGALA,BANGALORE-560034,#186E,GROUND FLOOR,5 th MAIN ROAD,ST BED LAYOUT, 4 th BLOCK, KORAMANGALA,BANGALORE-560034 |
| Pin Code | 560034 |
| Year Of Establishment | 2008 |
| Number of Project Completed | 15 |
| Reg. Of COA No. | BCC/BL-3.6/A-2740 :2016-2017 |
| Local Authority Licence Number | BCC/BL-36/E- 3001/2007-08 |
| Promoter Type | Partnership Firm |
| Name | R.M.Eshwar Naidu |
| PAN Number | AADFG6207A |
| Address | No:161/a,7th cross, teachers colony, Ist stage, Kumara swamy Layout, Bangalore -560078.No:161/a,7th cross, teachers colony, Ist stage, Kumara swamy Layout, Bangalore -560078 |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560078 |
| Company Registration No. | NOT APPLICABLE |
| Type | Director |
| Pin Code | 560078 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-12-2017 | 31-07-2018 |
| 2 | Foundation footing work | Yes | 01-07-2018 | 30-12-2018 |
| 3 | Retaining wall (All types) | Yes | 01-08-2018 | 31-12-2018 |
| 4 | Plinth level Beam | Yes | 01-07-2018 | 30-12-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-09-2018 | 30-03-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | No |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.grsanthrupthi.com |
| Agent Registration No 1 | NOT APPLICABLE |
| FAR Sanctioned | 1.74 |
| Number of Towers | 3 |
| 0 | 13 |
| Total No of Units | 45 |
| Project Start Date | 01-12-2017 |
| Project End Date | 30-08-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 20638903 |
| Cost of construction | 480000000 |
| Total project cost | 660000000 |
| Total amount collected from buyers | 812139826 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 599891850 |
| Balance amount with the promoter | 120735598 |
| Total number of Flats/Apartments of the Project | 45 |
| Total number of Flats/Apartments sold | 45 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 01-02-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Project | No Complaints Found. |