Relationship Properties Private Limited
Municipal No 1/1, Hosakere Road,, Binnypet, Bangalore
Approved
15th Oct 2017
Completed
31st Mar 2023
Registration No.
PRM/KA/RERA/1251/310/PR/171015/000277
Acknowledgement No.
PR/KN/170730/000277
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Parkwest - Maple - Tower 4 |
| Project Description | Apartment development consisting of 31 Floors 552 units |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 25-10-2016 |
| Proposed Project Completion Date | 30-09-2022 |
| Further Extension Date | 31-03-2023 |
| Total Area Of Land (Sq Mtr) | 22052 |
| Total Coverd Area (Sq Mtr) | 2321 |
| Total Open Area (Sq Mtr) | 19731 |
| Estimated Cost of Construction (INR) | 3032907126 |
| Cost of Land (INR) | 2332011848 |
| Total Project Cost (INR) | 5364918974 |
| Project Address | Municipal No 1/1, Hosakere Road,, Binnypet, Bangalore |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 50 |
| Area of Parking for Sale (Sq Mtr) | 688 |
| Extent of development carried till date | 18 % |
| Extent of development pending | 82 % |
| Total amount of money collected from allottee | 1411410284 |
| Total amount of money used for development of project | 2883367957 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | Yes |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | Refer Annexure - Specification |
| No of Inventory | 0 |
| Carpet Area (Sq Mtr) | 0SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| BWSSB | Self Development |
| BESCOM | Self Development |
| Bank Name | HDFC |
| Branch | FORT BRANCH |
| ifscCode | HDFC00000060 |
| Account No.(70% Account) | 57500000047314 |
| State | Karnataka |
| Name | SIMPLEX INFRASTRUCTURE LIMITED |
| Address | Brigade Plaza Unit C, First floor, ,71/1 Anand Rao Circle, SC Road, Majestic |
| Pin Code | 560009 |
| Year Of Establishment | 1924 |
| Number of Project Completed | 80 |
| Reg. Of COA No. | ca/94/17296 |
| Local Authority Licence Number | BCC/BL-3.6/SE:150:2013-14 |
| Number Of Project Completed | 100+ |
| Promoter Type | Company |
| Name | Makarand Desai |
| PAN Number | AADCR8947D |
| Address | Flat No.201, 20th Floor, Tower A/6,.Godrej- Garden Enclave, Pirojsha Nagar, Vikroli (East), |
| District | Mumbai City |
| State/UT | Maharashtra |
| PIN Code | 400023 |
| Company Registration No. | U45200MH2008PTC178830 |
| Type | Director |
| Pin Code | 400079 |
| Type of Inventory | Refer Annexure - Specification |
| No of Inventory | 0 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Extension Applied On | 15-07-2021 |
| Extension Approved On | 05-10-2021 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/211005/000277 |
| Proposed Project End Date at the time of registration | 30-09-2021 |
| Project End Date provided under Section 6 | 30-09-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | BWSSB - NOC |
| 1 | Force Majeure |
| Document Name_1 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 14-12-2015 | 15-03-2016 |
| 2 | Foundation footing work | Yes | 26-02-2016 | 11-09-2017 |
| 3 | Retaining wall (All types) | Yes | 05-12-2016 | 02-03-2019 |
| 4 | Plinth level Beam | Yes | 20-04-2016 | 07-11-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 13-03-2019 | 31-07-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.shapoorjipallonjiparkwest.net.in |
| FAR Sanctioned | 0.161 |
| Number of Towers | 1 |
| 0 | 14 |
| 1 | 16 |
| 2 | 18 |
| 3 | 18 |
| 4 | 18 |
| 5 | 18 |
| 6 | 18 |
| 7 | 18 |
| 8 | 18 |
| 9 | 18 |
| 10 | 18 |
| 11 | 18 |
| 12 | 18 |
| 13 | 8 |
| 14 | 16 |
| 15 | 18 |
| 16 | 18 |
| 17 | 18 |
| 18 | 18 |
| 19 | 18 |
| 20 | 18 |
| 21 | 18 |
| 22 | 18 |
| 23 | 18 |
| 24 | 18 |
| 25 | 18 |
| 26 | 18 |
| 27 | 18 |
| 28 | 18 |
| 29 | 16 |
| 30 | 18 |
| 31 | 14 |
| Total No of Units | 552 |
| Project Start Date | 25-10-2016 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2021 |
| Extended End Date | 30-09-2022 |
| Cost of land | 2332011848 |
| Cost of construction | 3032907126 |
| Total project cost | 5364918974 |
| Total amount collected from buyers | 4888678121 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 5353841139 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 552 |
| Total number of Flats/Apartments sold | 546 |
| Total number of Flats/Apartments Unsold | 6 |
| Whether the project has been completed within the stipulated Period? | NO |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 25-01-2023 |
| Appeals / FNH | NO APPEALS / FNH |