Puravankara Limited
Sy.No.3/3,7,8,9/2A,9/2B,26/1, Mallasandra Village Uttarahalli Hobli
Approved
7th May 2018
Completed
30th Jul 2023
Registration No.
PRM/KA/RERA/1251/310/PR/180507/001648
Acknowledgement No.
PR/KN/180307/002838
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Provident Park Square Phase 2 |
| Project Description | Provident Park Square Phase-2 is an affordable housing residential project comprising 2BHK, and 3BHK apartments. The project will also have a host of amenities located in a large clubhouse and a swimming pool. With Park Square, Puravankara wants to establish that affordable housing can also be of good quality. This phase comprises of Towers 2C and 4B with an inventory of approximately 208 apartments |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 24-03-2018 |
| Proposed Project Completion Date | 30-07-2023 |
| Total Area Of Land (Sq Mtr) | 2474 |
| Total Coverd Area (Sq Mtr) | 1552 |
| Total Open Area (Sq Mtr) | 922 |
| Estimated Cost of Construction (INR) | 811863234 |
| Cost of Land (INR) | 126245785 |
| Total Project Cost (INR) | 938109019 |
| Project Address | Sy.No.3/3,7,8,9/2A,9/2B,26/1, Mallasandra Village Uttarahalli Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 16 |
| Area of Parking for Sale (Sq Mtr) | 220 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Standard Chartered Bank |
| Branch | Koramangala |
| ifscCode | SCBL0036073 |
| Account No.(70% Account) | 45505424402 |
| State | Karnataka |
| Name | Starworth Infrastructure and Constructions Private Limited |
| Address | 39 ,Ulsoor Road |
| Pin Code | 560042 |
| Year Of Establishment | 2003 |
| Number Of Project Completed | 15 |
| Promoter Type | Company |
| Name | Nani R Choksey |
| PAN Number | AAACP2550R |
| Address | 130/1 , Ulsoor Road |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560042 |
| Company Registration No. | L45200KA1986PLC051571 |
| Have your said registration been revoked? | No |
| Certificate Number | P52100005377 |
| Extension Applied On | 09-06-2022 |
| Extension Approved On | 11-07-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/220711/001648 |
| Proposed Project End Date at the time of registration | 30-07-2022 |
| Project End Date provided under Section 6 | 30-07-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | others |
| Document Name |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 25-04-2018 | 30-06-2019 |
| 2 | Foundation footing work | Yes | 01-07-2018 | 31-03-2019 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 15-09-2018 | 31-12-2020 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-09-2019 | 31-12-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.249 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 8 |
| 2 | 8 |
| 3 | 8 |
| 4 | 8 |
| 5 | 8 |
| 6 | 8 |
| 7 | 8 |
| 8 | 8 |
| 9 | 8 |
| 10 | 8 |
| 11 | 8 |
| 12 | 8 |
| 13 | 8 |
| 14 | 8 |
| Total No of Units | 216 |
| Project Start Date | 24-03-2018 |
| Project End Date | 30-07-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-07-2022 |
| Extended End Date | 30-07-2023 |
| Cost of land | 126245785 |
| Cost of construction | 811863234 |
| Total project cost | 938109019 |
| Total amount collected from buyers | 844583781 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 844236190 |
| Balance amount with the promoter | 347591 |
| Total number of Flats/Apartments of the Project | 216 |
| Total number of Flats/Apartments sold | 206 |
| Total number of Flats/Apartments Unsold | 10 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 06-08-2022 |
| Appeals / FNH | NO APPEALS / FNH |