Total Environment Habitat Private Limited
Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1, Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore
Approved
2nd Jan 2019
Pending
30th Mar 2027
Registration No.
PRM/KA/RERA/1251/446/PR/190102/002271
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/181013/002717
Project Type
Mixed Development
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | PURSUIT OF A RADICAL RHAPSODY PHASE 2 |
| Project Description | ProjectnamedPursuitofaRadicalRhapsodyPhase2consistingofresidentialTower6tower7and15villasnumbered49to63 |
| Project Type | Mixed Development |
| Project Status | New Project Launch |
| Project Start Date | 01-11-2018 |
| Proposed Project Completion Date | 30-03-2027 |
| Total Area Of Land (Sq Mtr) | 28131 |
| Total Coverd Area (Sq Mtr) | 10024 |
| Total Open Area (Sq Mtr) | 18107 |
| Estimated Cost of Construction (INR) | 8487357900 |
| Cost of Land (INR) | 1449018272 |
| Total Project Cost (INR) | 9936376172 |
| Project Address | Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1, Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 5 BHK |
| No of Inventory | 2 |
| Carpet Area (Sq Mtr) | 1000SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 421SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Water supply | Local Authority |
| Sewerage and drainage | Local Authority |
| Road and road systems | Local Authority |
| Electric supply, transformers, sub station | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | COMMERCIAL BRANCH, BANGALORE |
| ifscCode | SBIN0004196 |
| Account No.(100% Account) | 42528163769 |
| Account No.(70% Account) | 42528162620 |
| Account No.(30% Account) | 42528163135 |
| State | Karnataka |
| Promoter Type | Company |
| Name | Sanjeev Garg |
| PAN Number | AADCT5683N |
| Address | No. 78, Imagine, EPIP Zone , ITPL Main Road, Whitefield |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560066 |
| Company Registration No. | U45201KA2010PTC054651 |
| Modification Applied On | 02-11-2022 |
| Modification Approved On | 19-12-2022 |
| Type of Inventory | 5 BHK |
| No of Inventory | 2 |
| Carpet Area (Sq Mtr) | 1000 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 421 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Due to height limit imposed from Airport Authority (HAL) NOC, we were restricted to register less floor. Now, we received the height clearance from the Airport Authority (HAL) and accordingly this modification plan been submitted. |
| Modified plan applied date | 03/08/2022 |
| Modified plan approved date | 15/09/2022 |
| Extend of the work carried out till date of registered project ( % ) | 36.0 |
| Extend of the work pending of registered project ( % ) | 64.0 |
| Total amount collected in respect of registered project ( INR ) | 2882502611 |
| Total amount spent for the project ( INR ) | 3586229439 |
| Total balance amount lying with the promoter ( INR ) | 1305252883 |
| NOC | KSPCB |
| SlNo. |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-01-2019 | 10-01-2020 |
| 2 | Foundation footing work | Yes | 10-01-2020 | 10-03-2020 |
| 3 | Retaining wall (All types) | Yes | 10-03-2020 | 30-03-2023 |
| 4 | Plinth level Beam | Yes | 05-11-2020 | 04-01-2021 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 09-05-2020 | 30-06-2023 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 2.79 |
| Number of Towers | 3 |
| 0 | 20 |
| 1 | 0 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 4 |
| 11 | 4 |
| 12 | 4 |
| 13 | 4 |
| 14 | 4 |
| 15 | 4 |
| 16 | 4 |
| 17 | 4 |
| 18 | 4 |
| 19 | 4 |
| 20 | 4 |
| 21 | 4 |
| 22 | 4 |
| 23 | 4 |
| 24 | 4 |
| 25 | 4 |
| 26 | 4 |
| 27 | 4 |
| 28 | 2 |
| 29 | 4 |
| 30 | 2 |
| Total No of Units | 264 |
| Appeals / FNH | NO APPEALS / FNH |


Ask Pulse Ai anything about real estate