Total Environment Habitat Private Limited
Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1 , Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore
Approved
17th Aug 2020
Pending
30th Jun 2026
Registration No.
PRM/KA/RERA/1251/446/PR/200817/003551
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/200723/004146
Project Type
Commercial
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | PURSUIT OF A RADICAL RHAPSODY PHASE III |
| Project Description | The total area of the project Pursuit of a Radical Rhapsody is 34 acres 20 guntas. The total number of towers are 8 residential towers 1 commerical tower and 63 villas. Phase 3 of the project named Pursuitof a Radical Rhapsody Phase3 consisting of Tower-9 (Commercial) is being registered with K-RERA currently. |
| Project Type | Commercial |
| Project Status | New Project Launch |
| Project Start Date | 01-11-2018 |
| Proposed Project Completion Date | 30-06-2026 |
| Total Area Of Land (Sq Mtr) | 4844 |
| Total Coverd Area (Sq Mtr) | 1845 |
| Total Open Area (Sq Mtr) | 2999 |
| Estimated Cost of Construction (INR) | 2766600000 |
| Cost of Land (INR) | 324700000 |
| Total Project Cost (INR) | 3091300000 |
| Project Address | Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1 , Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 28 |
| Area of Parking for Sale (Sq Mtr) | 556 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| "Road and road systems abuting ITPL main road Water supply - BWSSB Sewerage and drainage - Zero discharge (self execution) Electric supply, transformers, sub station- BESCOM" | Self Development |
| Bank Name | RATNAKAR BANK |
| Branch | Residency Road Branch |
| ifscCode | RATN0000156 |
| Account No.(70% Account) | 409000965789 |
| State | Karnataka |
| Name | Total Environment Habitat Pvt Ltd |
| Address | No. 78, Imagine, EPIP Zone,ITPL Main Road, Whitefield |
| Pin Code | 560066 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 20 |
| Reg. Of COA No. | CA 94 17784 |
| Local Authority Licence Number | BCC BL 3.6 SE 19 2012-13 |
| Number Of Project Completed | 0 |
| Promoter Type | Company |
| Name | Kamal Sagar |
| PAN Number | AADCT5683N |
| Address | Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1 Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560066 |
| Company Registration No. | U45201KA2010PTC054651 |
| Type | Director |
| Pin Code | 560066 |
| Project Name | PURSUIT OF A RADICAL RHAPSODY PHASE 1 |
| Project Description | Residential Apartment and Villas |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 31-07-2024 |
| Sl No. |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 17-08-2020 | 30-06-2026 |
| 2 | Foundation footing work | Yes | 17-08-2020 | 31-03-2026 |
| 3 | Retaining wall (All types) | Yes | 17-08-2020 | 31-03-2026 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-07-2025 | 30-06-2026 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | https://www.total-environment.com/workspaces/pursuit-of-a-radical-rhapsody-workcation |
| Agent Registration No 1 | Nil |
| FAR Sanctioned | 2.73 |
| Number of Towers | 1 |
| 0 | 2 |
| 1 | 2 |
| 2 | 2 |
| 3 | 2 |
| 4 | 2 |
| 5 | 1 |
| 6 | 1 |
| 7 | 1 |
| 8 | 1 |
| 9 | 1 |
| 10 | 1 |
| 11 | 1 |
| 12 | 1 |
| 13 | 1 |
| 14 | 1 |
| 15 | 1 |
| 16 | 1 |
| Total No of Units | 22 |
| Project Start Date | 01-11-2018 |
| Project End Date | 30-06-2026 |
| If any extension of time has been granted | NO |
| Cost of land | 324700000 |
| Cost of construction | 2766600000 |
| Total project cost | 3091300000 |
| Total amount collected from buyers | 2184090116 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 3254135131 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 22 |
| Total number of Flats/Apartments sold | 18 |
| Total number of Flats/Apartments Unsold | 4 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 06-05-2024 |
| Complaints on Project | No Complaints Found. |