RAMKY ONE KARNIVAL
RAMKY ESTATES AND FARMS LIMITED
Sy. No 36-40 , Maragondanahalli Village
Approved
26th Feb 2020
Pending
30th Dec 2026
Registration No.
PRM/KA/RERA/1251/308/PR/200226/003306
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/200111/003817
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
Project Details
| Project Name | RAMKY ONE KARNIVAL |
| Project Description | Basement + Ground + 14 Floors High Rise Apartments with 503 units |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 01-03-2020 |
| Proposed Project Completion Date | 30-12-2026 |
| Total Area Of Land (Sq Mtr) | 29036 |
| Total Coverd Area (Sq Mtr) | 4115 |
| Total Open Area (Sq Mtr) | 24921 |
| Estimated Cost of Construction (INR) | 1671156396 |
| Cost of Land (INR) | 32953929 |
| Total Project Cost (INR) | 1704110325 |
| Project Address | Sy. No 36-40 , Maragondanahalli Village |
| District | Hyderabad |
| Taluk | Anekal |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 1 |
| Area of Garage for Sale (Sq Mtr) | 14342 |
| No of Parking for Sale | 98 |
| Area of Parking for Sale (Sq Mtr) | 1347 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Axis Bank |
| Branch | Hennur Road Branch |
| ifscCode | UTIB0002179 |
| Account No.(70% Account) | 919020081513351 |
| State | Telangana |
| Name | RAMKY INFRASTRUCTURE LIMITED |
| Address | 2ND FLOOR , RAMKY GRANDIOSE, RAMKY TOWER COMPLEX,GACHIBOWLI |
| Pin Code | 500032 |
| Year Of Establishment | 1994 |
| Number of Project Completed | 305 |
| Reg. Of COA No. | CA/92/15143 |
| Local Authority Licence Number | B.C.C./B.L./3.2.3 E- 784/90-91 |
| Number Of Project Completed | 330 |
Promoter Details
| Promoter Type | Company |
| Name | G Anjaneyulu |
| PAN Number | AAA******* |
| Address | Site No. 25-30, 2nd Cross, Raghavendra Nagar.Hennur Ring Road, Kalyan Nagar Post, Bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560043 |
| Company Registration No. | U70102AP1995PLC021333 |
| Type | Others |
| Pin Code | 560043 |
| Have your said registration been revoked? | No |
| Certificate Number | P02400000505 |
| Sl No. |
Extension Details
| Extension Applied On | 30-12-2025 |
| Extension Approved On | 18-03-2026 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/308/PR/260318/003306 |
| Proposed Project End Date at the time of registration | 30-12-2025 |
| Project End Date provided under Section 6 | 30-12-2026 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | No Consent Affidavit |
| 1 | others |
| Document Name_1 | |
| Document Name_2 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 26-02-2020 | 31-03-2025 |
| 2 | Foundation footing work | Yes | 26-02-2020 | 31-03-2025 |
| 3 | Retaining wall (All types) | Yes | 26-02-2020 | 31-03-2025 |
| 4 | Plinth level Beam | Yes | 26-02-2020 | 31-03-2025 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 26-02-2020 | 31-03-2025 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| FAR Sanctioned | 1.9 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 18 |
| 2 | 17 |
| 3 | 18 |
| 4 | 18 |
| 5 | 18 |
| 6 | 18 |
| 7 | 18 |
| 8 | 18 |
| 9 | 18 |
| 10 | 18 |
| 11 | 18 |
| 12 | 18 |
| 13 | 18 |
| 14 | 18 |
| Total No of Units | 503 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in